Town Center: Utility & Woonerf Project
The City of Sumner adopted the Town Center Plan in 2018 allowing for redevelopment of properties in and adjacent to the historical Sumner downtown corridor. To provide public services in accordance with that plan the City seeks to upgrade road, sidewalk, storm drainage, sanitary sewer, and domestic water facilities within and adjacent to Alder Avenue and Kincaid Avenue between Main Street and Park Street.
In addition, the City of Sumner has secured grant funding for the delineation of a bike route between the Sumner Sound Transit Station and Wood Avenue. The project will involve the reconstruction of curbs, sidewalks, signage, street striping, and utilities to accommodate the bike lanes.
In 2021, the City of Sumner adopted the Main Street Visioning Plan. This plan captured the community's vision that eventally led to the inclusion of the woonerfs around Heritage Park (Cherry Avenue and Kincaid Avenue between Main St and Maple Street) in this project.
Project extents are shown below:
The City of Sumner adopted the Town Center Plan in 2018 allowing for redevelopment of properties in and adjacent to the historical Sumner downtown corridor. To provide public services in accordance with that plan the City seeks to upgrade road, sidewalk, storm drainage, sanitary sewer, and domestic water facilities within and adjacent to Alder Avenue and Kincaid Avenue between Main Street and Park Street.
In addition, the City of Sumner has secured grant funding for the delineation of a bike route between the Sumner Sound Transit Station and Wood Avenue. The project will involve the reconstruction of curbs, sidewalks, signage, street striping, and utilities to accommodate the bike lanes.
In 2021, the City of Sumner adopted the Main Street Visioning Plan. This plan captured the community's vision that eventally led to the inclusion of the woonerfs around Heritage Park (Cherry Avenue and Kincaid Avenue between Main St and Maple Street) in this project.
Project extents are shown below:
-
12/05/22 Construction Update
Work completed for Week Ending 12/02/2022:
- Kincaid Avenue (Maple to Main)
- Continued pouring concrete curbs and sidewalk
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
Work in progress this week (12/05/2022 - 12/09/2022):
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete
- Complete pouring curbs and sidewalks
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition
- Begin storm drainage improvements
Upcoming Work through 12/23/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Kincaid Avenue (Academy to Maple)
- Begin pouring curbs
- Kincaid Avenue (Park to Academy)
- Begin pouring curbs
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete roadway excavation and grading for intersection paving
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Kincaid Avenue (Maple to Main)
-
11/28/22 Construction Update
Work completed for Week Ending 11/25/2022:
- Kincaid Avenue (Maple to Main)
- Started pouring concrete curbs and sidewalk
Work in progress this week (11/28/2022 - 12/02/2022):
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete
- Complete pouring curbs and sidewalks
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
Upcoming Work through 12/16/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Kincaid Avenue (Academy to Maple)
- Begin pouring curbs and sidewalks
- Kincaid Avenue (Park to Academy)
- Begin pouring curbs and sidewalks
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete roadway excavation and grading for intersection paving
- Academy Street
- Begin water main installation
- Kincaid Avenue (Maple to Main)
-
11/21/22 Construction Update
Work completed for Week Ending 11/18/2022:
- Kincaid Avenue (Maple to Main)
- Completed sidewalk demolition and grading
- Completed pouring concrete curb
- Started pouring concrete sidewalk
- Kincaid Avenue (Park to Academy)
- Completed trench restoration
11/15/22: Checking subgrade elevation on Kincaid Avenue south of Main Street.Work in progress this week (11/21/2022 - 11/25/2022):
- Kincaid Avenue (Maple to Main)
- Continue pouring curbs and sidewalks
Upcoming Work through 12/09/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring curbs and sidewalks
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Complete roadway excavation for intersection paving
- Kincaid Avenue (Maple to Main)
-
11/14/22 Construction Update
Work completed for Week Ending 11/11/2022:
- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Maple Street
- Complete water main connections.
Work in progress this week (11/14/2022 - 11/18/2022):
- Kincaid Avenue (Maple to Main)
- Complete demolition of sidewalks
- Complete grading for concrete
- Pour curbs and sidewalks
Upcoming Work through 12/02/2022:
- Kincaid Avenue (Maple to Main):
- Pour flush curbs
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Complete roadway excavation for intersection paving
- Kincaid Avenue (Maple to Main)
-
11/07/22 Construction Update
Work completed for Week Ending 11/04/2022:
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Complete trench restoration
Upcoming Work through 11/25/2022:
- Kincaid Avenue (Maple to Main):
- Complete installation of curbs
- Complete sidewalks (currently projected 11/21-11/23, but this may change)
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
- Intersection of Kincaid Avenue and Academy Street
-
10/31/22 Construction Update
Work completed for Week Ending 10/28/2022:
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
- Academy Street (Kincaid to Alder)
- Water Testing
Install rebar over watermain trenches and prepare for concrete pours.
- Kincaid Avenue (Maple to Main)
- Begin illumination system.
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
Upcoming Work through 11/18/2022:
- Kincaid Avenue (Maple to Main):
- Complete irrigation system.
- Begin installation of curbs
- Intersection of Kincaid Avenue and Academy Street
- Complete grading of intersection
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
- Kincaid Avenue (Maple to Main)
-
10/24/22 Construction Update
Work completed for Week Ending 10/21/2022:
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
- Academy Street (Kincaid to Alder)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
Work in progress this week (10/24/2022 - 10/28/2022):
- Kincaid Avenue (Academy to Maple)
- Pour concrete over watermain trenches.
- Place asphalt over watermain trenches.
- Kincaid Avenue (Park to Academy)
- Water Testing
- Kincaid Avenue (south of Park)
- Water Testing
- Academy Street (Kincaid to Alder)
- Pour concrete over watermain trenches.
- Place asphalt over watermain trenches.
- Park Street (Kincaid to Alder)
- Water Testing
Upcoming Work through 11/11/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Kincaid Avenue/Academy Street Intersection
- Demolition for storm drainage installation.
- Install storm drainage pipes and structures.
- Grade for concrete placement.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Park Street (Kincaid to Alder)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (Maple to Main)
-
10/17/22 Construction Update
Work completed for Week Ending 10/14/2022:
- Kincaid (Academy to Maple)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (Park to Academy)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (south of Park to tie-in)
- Complete water service connection crossings (still need to connect to make connections)
- Park Street (Kincaid to Alder)
- Complete water service connection crossings (still need to connect to make connections)
Work in progress this week (10/17/2022 - 10/21/2022):
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Academy Street (Kincaid to Alder)
- Water Testing
Upcoming Work through 11/04/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue/Academy Street Intersection
- Demolition for storm drainage installation.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Academy Street (Kincaid to Alder)
- Continue water service connections.
- Park Street (Kincaid to Alder)
- Continue water service connections.
- Kincaid (Academy to Maple)
-
10/10/22 Construction Update
There was a recent question about this project on the Rumors & Questions page. Click here to see the question and response.
Work completed for Week Ending 10/07/2022:
- Kincaid Avenue (south of Park to tie-in)
- Complete waterline installation (still need to complete water service connections)
- Park Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (10/10/2022 - 10/14/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin water service connection installation
Upcoming Work through 10/28/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Begin testing watermain.
- Complete roadway subgrade.
- Kincaid Avenue (Academy to Maple):
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Begin testing watermain.
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Begin testing watermain.
- Continue water service connections
- Park Street (Kincaid to Alder)
- Begin testing watermain.
- Continue waterline and water service connection installation
- Kincaid Avenue (south of Park to tie-in)
-
10/03/22 Construction Update
Work completed for Week Ending 09/30/2022:
- Academy Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (10/03/2022 - 10/07/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin waterline and water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin waterline and water service connection installation
Upcoming Work through 10/21/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Continue water service connections
- Park Street (Kincaid to Alder)
- Continue waterline and water service connection installation
- Academy Street (Kincaid to Alder)
Life Cycle
-
June 2021 - April 2022: Final Design
Town Center: Utility & Woonerf Project has finished this stage -
May - June 2022: Advertisement, Bid Opening, and Contract Award
Town Center: Utility & Woonerf Project has finished this stage -
July 2022 - Summer 2023: Construction
Town Center: Utility & Woonerf Project is currently at this stage
Who's listening
-
Deputy Public Works Director – Engineering • Public Works
Phone 253-299-5703 Email alisao@sumnerwa.gov
News Categories
- Construction Update (47)
- Contruction Update (1)
- Pre-Construction (3)