10/10/22 Construction Update

There was a recent question about this project on the Rumors & Questions page. Click here to see the question and response.

Work completed for Week Ending 10/07/2022:

  • Kincaid Avenue (south of Park to tie-in)
    • Complete waterline installation (still need to complete water service connections)
  • Park Street (Kincaid to Alder)
    • Complete waterline installation (still need to complete water service connections)

10/03/22: Removing asphalt for water service connections on Kincaid Avenue between Park Street and Academy Street. 10/04/22: Compacting the backfill on the waterline trench on the NW corner of Kincaid Avenue and Park Street. 10/06/22: Excavating for watermain installation on Park Street west of Alder Avenue.

Work in progress this week (10/10/2022 - 10/14/2022):

  • Kincaid Avenue (Maple to Main)
    • Continue water service connections
  • Kincaid Avenue (Academy to Maple)
    • Continue water service connections
  • Kincaid Avenue (Park to Academy)
    • Continue water service connections
  • Kincaid Avenue (south of Park to tie-in)
    • Begin water service connection installation
  • Academy Street (Kincaid to Alder)
    • Begin water service connections
    • Complete Installing dowels for concrete panels
  • Park Street (Kincaid to Alder)
    • Begin water service connection installation

Upcoming Work through 10/28/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
    • Begin testing watermain.
    • Complete roadway subgrade.
  • Kincaid Avenue (Academy to Maple):
    • Begin testing watermain.
    • Continue water service connections.
  • Kincaid Avenue (Park to Academy)
    • Begin testing watermain.
    • Continue water service connections.
  • Kincaid Avenue (south of Park to tie-in)
    • Begin testing watermain.
    • Continue water service connections
  • Academy Street (Kincaid to Alder)
    • Begin testing watermain.
    • Continue water service connections
  • Park Street (Kincaid to Alder)
    • Begin testing watermain.
    • Continue waterline and water service connection installation
Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>