10/10/22 Construction Update
There was a recent question about this project on the Rumors & Questions page. Click here to see the question and response.
Work completed for Week Ending 10/07/2022:
- Kincaid Avenue (south of Park to tie-in)
- Complete waterline installation (still need to complete water service connections)
- Park Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (10/10/2022 - 10/14/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin water service connection installation
Upcoming Work through 10/28/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Begin testing watermain.
- Complete roadway subgrade.
- Kincaid Avenue (Academy to Maple):
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Begin testing watermain.
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Begin testing watermain.
- Continue water service connections
- Park Street (Kincaid to Alder)
- Begin testing watermain.
- Continue waterline and water service connection installation