Category Construction Update   Show all

  • 06/26/2023 Construction Update

    WORK COMPLETED FOR WEEK ENDING 06/23/2023

    • Main Street
      • HMA base Lift
    • Academy/Cherry
      • Begin Storm system
      • Complete Water Main Testing
      • Begin Subgrade and place rock
    • Cherry Avenue (Maple to Main)
      • Complete pouring concrete sidewalk
      • Complete pouring concrete roadway
      • Complete pouring concrete curb
      • Complete bollards
      • Complete decorative strip
    • Kincaid/Park
      • Complete water service transfers
      • Continue Landscaping
    • Kincaid Avenue
      • Continue water service transfers
      • Continue Landscaping


    6/22/2023 Kincaid Avenue - Continue Landscaping


    6/22/2023 Cherry Avenue - Complete Bollard Install



    WORK IN PROGRESS THIS WEEK (06/26/2023 - 06/30/2023)

    • Main Street
      • HMA base Lift
      • Continue Landscaping
    • Academy/Cherry
      • Continue Storm system
      • Continue curb and sidewalk
      • Begin Subgrade and place rock
    • Cherry Avenue (Maple to Main)
      • Continue Landscaping
    • Kincaid/Park
      • Complete HMA
      • Complete curb and sidewalk
      • Complete water service transfers
      • Continue Landscaping
    • Kincaid Avenue
      • Continue water service transfers
      • Continue Landscaping
    • Academy/Wood
      • Begin Demolition
      • Begin Subgrade and Rock
      • Begin curb and sidewalk
      • Begin HMA

    UPCOMING WORK THROUGH 07/14/2023

    • Main Street
      • Complete landscaping
      • Complete grind/overlay
    • Academy/Cherry
      • Complete Storm System
      • Complete water main tie in
      • Complete curbs/sidewalks
      • Complete HMA Base Lift
      • Complete Landscaping
    • Cherry Avenue (Maple to Main)
      • Complete landscaping
    • Kincaid/Park
      • Complete grind & overlay
      • Complete sidewalks
      • Complete landscaping
    • Install permanent striping and signage
  • 6/12/2023 Construction Update

    WORK COMPLETED FOR WEEK ENDING 06/09/2023

    • Main Street
      • Concrete Roadway Cure
    • Academy/Cherry
      • Begin Water Main Tie In
      • Complete Pressure Test
    • Cherry Avenue (Maple to Main)
      • Complete pouring Sidewalk
      • Complete pouring Roadway
      • Complete pouring Curb
      • Raise Hardware to finish road grade
    • Kincaid/Park
      • Begin water service transfers
      • Complete Landscape and hydroseeding
    • Kincaid
      • Complete Bollard install
      • Continue Irrigation install

    06/08/2023 Cherry Avenue - Continue pouring Concrete

    06/09/2023 Kincaid Avenue - Continue Irrigation Install



    WORK IN PROGRESS THIS WEEK (06/12/2023 - 06/16/2023)

    • Main Street
      • HMA base Lift
    • Academy/Cherry
      • Begin Storm system
      • Begin Water Main Testing
      • Begin Curb & Sidewalk
      • Begin Water Main Tie In
      • Begin Subgrade and place rock
    • Cherry Avenue (Maple to Main)
      • Continue pouring concrete sidewalk
      • Continue pouring concrete roadway
      • Continue pouring concrete curb
    • Kincaid/Park
      • Continue water service transfers
      • Continue Landscaping
    • Kincaid Avenue
      • Continue Irrigation install
      • Continue Landscaping

    UPCOMING WORK THROUGH (06/30/2023)

    • Main Street
      • Complete HMA Base Lift
      • Complete landscaping
    • Academy/Cherry
      • Complete Demolition
      • Complete Storm System
      • Complete water line
      • Complete subgrade
      • Complete HMA Base Lift
      • Complete Landscaping
      • Complete Water Main Tie In
    • Cherry Avenue (Maple to Main)
      • Complete sidewalks
      • Complete concrete roadway
      • Complete decorative strips
      • Complete crosswalks
      • Complete bollard install
      • Complete landscaping
    • Kincaid/Park
      • Complete Water Services
      • Complete grind & overlay
      • Complete landscaping
  • 6/05/2023 Construction Update

    WORK COMPLETED FOR WEEK ENDING 06/02/2023

    • Main Street
      • Complete pouring crosswalk
      • Complete pouring roadway
      • Begin pouring concrete at nose of heritage park
    • Academy/Cherry
      • Continue Demolition
      • Complete storm system
    • Landscaping and hydroseeding throughout project


    5/30/2023 Main Street - Complete pouring crosswalks




    6/01/2023 - Begin Pouring Concrete at Heritage Park




    6/02/2023 Academy/Cherry - Continue Demolition



    WORK IN PROGRESS THIS WEEK (06/05/2023 - 06/09/2023)

    • Main Street
      • Concrete Roadway Cure
    • Academy/Cherry
      • Begin Water Main Tie In
      • Complete Pressure Test
    • Cherry
      • Complete pouring Sidewalk
      • Complete pouring Roadway
      • Complete pouring Curb
      • Raise Hardware to finish road grade
    • Kincaid/Park
      • Begin water service transfers
      • Complete Landscape and hydroseeding

    UPCOMING WORK THROUGH (06/23/2023)

    • Cherry Avenue (Maple to Main)
      • Complete sidewalks
      • Complete concrete roadway
      • Complete decorative strips
      • Complete crosswalks
      • Complete bollard install
    • Main St
      • Complete HMA Base Lift
    • Academy/Cherry
      • Complete Demolition
      • Complete Storm System
      • Complete water line
      • Complete subgrade
      • Complete HMA Base Lift
      • Complete Landscaping and Hydroseeding
      • Complete Water Main Tie In
  • 5/30/2023 Construction Update

    Upcoming Construction Traffic Impact

    • Starting MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY

    • Starting May 31st - KINCAID AVE WILL BE CLOSED FROM 7AM TO 10AM FOR LANDSCAPING.



    WORK COMPLETED FOR WEEK ENDING 05/12/2023

    • Cherry Avenue (Maple to Main)
      • Continue pouring concrete sidewalk
      • Continue pouring concrete roadway
      • Continue pouring concrete curb
    • Cherry Avenue / Maple St Intersection
      • Begin grading
      • Begin paving
    • Main Street
      • Complete installing conduit
      • Complete grading
      • Complete pouring curb
    • Academy/Cherry
      • Begin Demolition

    05/26/2023 Cherry Ave/Kincaid Ave/Main Street Intersection - Demolition of Nose of Heritage Park

    05/26/2023 Academy/Cherry Intersection - Begin Demolition

    05/23/2023 Main St - Complete Grading

    WORK IN PROGRESS THIS WEEK (05/22/2023 - 05/26/2023)

    • Main Street
      • Complete pouring crosswalk
      • Complete pouring roadway
    • Academy/Cherry
      • Continue Demolition
      • Complete storm system
    • Landscaping and hydroseeding throughout project

    UPCOMING WORK THROUGH (06/09/2023)

    • Cherry Avenue (Maple to Main)
      • Complete sidewalks
      • Complete concrete roadway
      • Complete decorative strips
      • Complete crosswalks
      • Complete bollard install
    • Main St
      • Complete HMA Base Lift
    • Academy/Cherry
      • Complete Demolition
      • Complete Storm System
      • Complete water line
      • Complete subgrade
      • Complete HMA Base Lift
  • 05/22/2023 Construction Update

    Upcoming Construction Traffic Impact

    • Starting MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY



    WORK COMPLETED FOR WEEK ENDING 05/12/2023

    • Alder/Main/Academy/Ryan
      • Completed raising hardware on roadway after overlay
      • Completed sign installation
    • Cherry Avenue (Maple to Main)
      • Continue pouring concrete sidewalk
      • Continue pouring concrete roadway
      • Continue pouring concrete curb
      • Begin subgrade and CSTC
      • Begin storm system
    • Main Street
      • Transfer traffic to eastbound only
      • Completed demolition of the North side of Main Street
      • Completed installing storm system
      • Begin installing conduit

    05/17/2023 Main Street - Begin Demolition on North Side 05/17/2023 Cherry Ave - Pouring Concrete

    05/16/2023 Cherry Ave - Pouring Concrete



    WORK IN PROGRESS THIS WEEK (05/22/2023 - 05/26/2023)

    • Cherry Avenue (Maple to Main)
      • Continue pouring concrete sidewalk
      • Continue pouring concrete roadway
      • Continue pouring concrete curb
    • Cherry Avenue / Maple St Intersection
      • Begin grading
      • Begin paving
    • Main Street
      • Complete installing conduit
      • Complete grading
      • Complete pouring curb
      • Begin pouring concrete roadway
    • Academy/Cherry
      • Begin Demolition

    UPCOMING WORK THROUGH (06/09/2023)

    • Alder/Park
      • Complete pouring concrete ramps
    • Cherry Avenue (Maple to Main)
      • Complete sidewalks
      • Complete concrete roadway
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete pouring concrete sidewalks and ramps
      • Complete pouring concrete roadway
    • Academy/Cherry
      • Complete Demolition
      • Complete Storm System
      • Complete water line
      • Complete subgrade
      • Complete HMA Base Lift
  • 05/15/2023 Construction Update

    Upcoming Construction Traffic Impact

    • MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY

    • May 17th - ALLEYWAY BETWEEN KINCAID AND ALDER WILL BE RETURNED TO TRADITIONAL EASTBOUND CONFIGURATION



    WORK COMPLETED FOR WEEK ENDING 05/12/2023

    • Alder/Main/Academy/Ryan
      • Complete roadway grinding
      • Complete roadway overlay
    • Cherry Avenue (Maple to Main)
      • Begin pouring concrete sidewalk
      • Begin pouring concrete roadway
      • Continue pouring concrete curb
    • Main Street
      • Concrete pavement cure
    • Kincaid
      • Complete water service transfer

    05/08/2023 Cherry Ave - Pouring Concrete Sidewalk

    05/09/2023 Academy Street - Roadway Grinding

    05/11/2023 Main Street - Roadway Overlay

    WORK IN PROGRESS THIS WEEK (05/15/2023 - 05/19/2023)

    • Alder/Main/Academy/Ryan
      • Begin rising hardware on roadway
      • Begin sign install
    • Cherry Avenue (Maple to Main)
      • Continue pouring concrete sidewalk
      • Continue pouring concrete roadway
      • Continue pouring concrete curb
      • Begin subgrade and CSCT
      • Begin storm system
    • Main Street
      • Transfer traffic to eastbound only
      • Begin demolition of the North side of Main Street
      • Begin installing storm system
      • Begin JUT

    UPCOMING WORK THROUGH (06/02/2023)

    • Alder/Main/Academy/Ryan/Park
      • Complete raising hardware on roadway
      • Complete installation of signs
      • Complete seeding
    • Cherry Avenue (Maple to Main)
      • Complete sidewalks
      • Complete CSBC
      • Complete concrete roadway
    • Cherry Ave and Maple St intersection
      • Complete roadway grinding
      • Complete roadway paving
      • Complete storm system
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete roadway excavation and grading
      • Complete pouring concrete curb and gutter
      • Complete pouring concrete sidewalks and ramps
      • Complete CSBC
      • Complete pouring concrete roadway
    • Academy/Cherry
      • Complete Demolition
      • Complete Storm System
      • Complete water line
  • 05/08/2023 Construction Update

    Upcoming Construction Traffic Impact

    • MAY 9TH - ROADWAY GRINDING IN THE FOLLOWING LOCATIONS:

      1. Main Street from Kincaid to Alder (south side only)

      2. Alder Ave (Park to Maple)

      3. Academy Street (Ryan to Kincaid)

    • MAY 10th 7:00pm - 5:00am - MAIN STREET (TRAFFIC AVE TO ALDER AVE) CLOSED AT RAILROAD TRACKS

    • MAY 11TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:

      1. Eastbound Main Street from Kincaid to Alder

      2. Northbound Alder Ave (Park to Maple)

      3. Southbound Alder (Academy to Park)

    • MAY 12TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:
      1. Alder & Maple Intersection

      2. Academy St (including Ryan Ave)

    • MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY

    • May 16th - ALLEYWAY BETWEEN KINCAID AND ALDER WILL BE RETURNED TO TRADITIONAL EASTBOUND CONFIGURATION



    WORK COMPLETED FOR WEEK ENDING 05/05/2023

    • Alder Ave and Park St intersection
      • Complete CSTC
      • Complete Water Tie in at Maple and Alder intersection (Thursday morning starting at 2am)
      • Pour Concrete
      • Complete CSBC
    • Cherry Avenue (Maple to Main)
      • Continue pouring concrete curb
      • Complete CSBC
      • PSE completed pole removals

    05/02/2023 Cherry Ave - Continue pouring concrete curb

    05/03/2023 Alder Ave/Park St Intersection - Pouring Concrete Curb



    WORK IN PROGRESS THIS WEEK (05/08/2023 - 05/12/2023)

    • Alder/Main/Academy/Ryan
      • Complete roadway grinding
      • Complete roadway overlay
    • Cherry Avenue (Maple to Main)
      • Begin pouring concrete sidewalk
      • Begin pouring concrete roadway
      • Continue pouring concrete curb
    • Main Street
      • Concrete pavement cure
    • Kincaid
      • Begin water service transfer

    UPCOMING WORK THROUGH (05/26/2023)

    • Alder/Main/Academy/Ryan/Park
      • Complete raising hardware on roadway
      • Complete installation of signs
    • Cherry Avenue (Maple to Main)
      • Complete sidewalks
      • Complete CSBC
      • Complete concrete roadway
    • Cherry Ave and Maple St intersection
      • Complete roadway grinding
      • Complete roadway paving
      • Complete storm system
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Transfer traffic to eastbound only
      • Begin demolition of the North side of Main Street
      • Complete roadway excavation and grading
      • Complete pouring concrete curb and gutter
      • Complete pouring concrete sidewalks and ramps
      • Complete CSBC
      • Complete pouring concrete roadway
  • 05/05/2023 PSE Update

    Puget Sound Energy's contractor Potelco is on site this morning pulling out the old power poles in the alley parking lot south of Main Street between Kincaid Avenue and Alder Avenue. Parking in this area will be limited until PSE/Potelco is done. They were able to squeeze us in last minute to get this done, so the City was just informed of it this morning. That is how PSE rolls, and the City is just happy that they made us a priority. PSE/Potelco will also be pulling out the old poles on the west side of Cherry Avenue between Maple Street and Main Street today - this is just in time to align with the TCUW schedule that is planning on beginning to pour concrete sidewalks on the west side of Cherry Avenue on Monday 5/8.

  • 5/01/2023 Construction Update

    Upcoming Construction Traffic Impact

    MAY 9TH - ROADWAY GRINDING IN THE FOLLOWING LOCATIONS:

    • Academy Street (Ryan to Kincaid)

    • Alder Ave (Park to Maple)

    • Main Street from Kincaid to Alder (south side only).

    MAY 11TH & 12TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:

    • Academy Street (Ryan to Kincaid)

    • Alder Ave (Park to Maple)

    • Main Street from Kincaid to Alder (south side only).

    MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY



    WORK COMPLETED FOR WEEK ENDING 04/28/2023

    • Alder Ave and Park St intersection
      • Begin installing storm system
      • Begin roadway excavation and grading
    • Cherry Avenue (Maple to Main)
      • Begin pouring concrete curb and gutter
      • Begin CSBC
    • Cherry Ave and Maple St intersection
      • Continue installing storm drainage
      • Continue roadway excavation and grading
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Continue pouring cement pavement


    04/27/2023 Main Street intersection - Continue Pouring Cement Pavement



    WORK IN PROGRESS THIS WEEK (05/01/2023 - 05/05/2023)

    • Alder Ave and Park St intersection
      • Complete CSTC
      • Complete Water Tie in at Maple and Alder intersection (Thursday morning starting at 2am)
      • Pour Concrete Roadway
      • Complete CSBC
    • Cherry Avenue (Maple to Main)
      • Complete pouring concrete curb
      • Complete CSBC

    UPCOMING WORK THROUGH (05/19/2023)

    • Alder Ave and Park St intersection
      • Complete roadway grinding
      • Complete roadway paving
    • Cherry Avenue (Maple to Main)
      • Complete sidewalks
      • Complete CSBC
      • Complete concrete roadway
    • Cherry Ave and Maple St intersection
      • Complete roadway grinding
      • Complete roadway paving
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete roadway excavation and grading
      • Complete pouring concrete curb and gutter
      • Complete pouring concrete sidewalks and ramps
      • Complete CSBC
      • Complete pouring concrete roadway
      • Begin demolition of the North side of Main Street
  • 4/24/2023 Construction Update


    WORK COMPLETED FOR WEEK ENDING 04/21/2023

    • Alder Ave and Park St intersection
      • Complete water service transfers
      • Complete water tie-ins on Alder
    • Cherry Avenue (Maple to Main)
      • Complete installing irrigation sleeves
      • Complete roadway excavation
      • Continue CSBS
    • Cherry Ave and Maple St intersection
      • Begin installing storm system
      • Begin roadway excavation
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Begin pouring concrete curb and gutter
      • Begin pouring concrete sidewalks and ramps

    04/19/2023 Main St Intersection - Pouring concrete curb

    04/21/2023 Main St Intersection - Pouring Concrete Crosswalk
    04/18/2023 Cherry Ave - Complete Road Excavation



    WORK IN PROGRESS THIS WEEK (4/24/2023 - 04/28/2023)

    • Alder Ave and Park St intersection
      • Begin installing storm system
      • Begin roadway excavation and grading
    • Cherry Avenue (Maple to Main)
      • Complete pouring concrete curb and gutter
      • Complete CSBC
    • Cherry Ave and Maple St intersection
      • Continue installing storm drainage
      • Continue roadway excavation and grading
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Continue pouring cement pavement

    UPCOMING WORK THROUGH (05/12/2023)

    • Alder Ave and Park St intersection
      • Complete installing storm drainage
      • Complete roadway excavation and grading
    • Cherry Avenue (Maple to Main)
      • Complete installing irrigation sleeves
      • Complete roadway excavation and grading
    • Cherry Ave and Maple St intersection
      • Complete installing storm drainage
      • Complete roadway excavation and grading
      • Complete pouring concrete curb and gutter
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete roadway excavation and grading
      • Complete pouring concrete curb and gutter
      • Complete pouring concrete sidewalks and ramps
      • Complete pouring concrete roadway