6/05/2023 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/02/2023
- Main Street
- Complete pouring crosswalk
- Complete pouring roadway
- Begin pouring concrete at nose of heritage park
- Academy/Cherry
- Continue Demolition
- Complete storm system
- Landscaping and hydroseeding throughout project
WORK IN PROGRESS THIS WEEK (06/05/2023 - 06/09/2023)
- Main Street
- Concrete Roadway Cure
- Academy/Cherry
- Begin Water Main Tie In
- Complete Pressure Test
- Cherry
- Complete pouring Sidewalk
- Complete pouring Roadway
- Complete pouring Curb
- Raise Hardware to finish road grade
- Kincaid/Park
- Begin water service transfers
- Complete Landscape and hydroseeding
UPCOMING WORK THROUGH (06/23/2023)
- Cherry Avenue (Maple to Main)
- Complete sidewalks
- Complete concrete roadway
- Complete decorative strips
- Complete crosswalks
- Complete bollard install
- Main St
- Complete HMA Base Lift
- Academy/Cherry
- Complete Demolition
- Complete Storm System
- Complete water line
- Complete subgrade
- Complete HMA Base Lift
- Complete Landscaping and Hydroseeding
- Complete Water Main Tie In