WORK COMPLETED FOR WEEK ENDING 06/02/2023

  • Main Street
    • Complete pouring crosswalk
    • Complete pouring roadway
    • Begin pouring concrete at nose of heritage park
  • Academy/Cherry
    • Continue Demolition
    • Complete storm system
  • Landscaping and hydroseeding throughout project


5/30/2023 Main Street - Complete pouring crosswalks




6/01/2023 - Begin Pouring Concrete at Heritage Park




6/02/2023 Academy/Cherry - Continue Demolition



WORK IN PROGRESS THIS WEEK (06/05/2023 - 06/09/2023)

  • Main Street
    • Concrete Roadway Cure
  • Academy/Cherry
    • Begin Water Main Tie In
    • Complete Pressure Test
  • Cherry
    • Complete pouring Sidewalk
    • Complete pouring Roadway
    • Complete pouring Curb
    • Raise Hardware to finish road grade
  • Kincaid/Park
    • Begin water service transfers
    • Complete Landscape and hydroseeding

UPCOMING WORK THROUGH (06/23/2023)

  • Cherry Avenue (Maple to Main)
    • Complete sidewalks
    • Complete concrete roadway
    • Complete decorative strips
    • Complete crosswalks
    • Complete bollard install
  • Main St
    • Complete HMA Base Lift
  • Academy/Cherry
    • Complete Demolition
    • Complete Storm System
    • Complete water line
    • Complete subgrade
    • Complete HMA Base Lift
    • Complete Landscaping and Hydroseeding
    • Complete Water Main Tie In