5/01/2023 Construction Update
Upcoming Construction Traffic Impact
MAY 9TH - ROADWAY GRINDING IN THE FOLLOWING LOCATIONS:
Academy Street (Ryan to Kincaid)
Alder Ave (Park to Maple)
Main Street from Kincaid to Alder (south side only).
MAY 11TH & 12TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:
Academy Street (Ryan to Kincaid)
Alder Ave (Park to Maple)
Main Street from Kincaid to Alder (south side only).
MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY
WORK COMPLETED FOR WEEK ENDING 04/28/2023
- Alder Ave and Park St intersection
- Begin installing storm system
- Begin roadway excavation and grading
- Cherry Avenue (Maple to Main)
- Begin pouring concrete curb and gutter
- Begin CSBC
- Cherry Ave and Maple St intersection
- Continue installing storm drainage
- Continue roadway excavation and grading
- Main St intersection with Kincaid Ave and Cherry Ave
- Continue pouring cement pavement
WORK IN PROGRESS THIS WEEK (05/01/2023 - 05/05/2023)
- Alder Ave and Park St intersection
- Complete CSTC
- Complete Water Tie in at Maple and Alder intersection (Thursday morning starting at 2am)
- Pour Concrete Roadway
- Complete CSBC
- Cherry Avenue (Maple to Main)
- Complete pouring concrete curb
- Complete CSBC
UPCOMING WORK THROUGH (05/19/2023)
- Alder Ave and Park St intersection
- Complete roadway grinding
- Complete roadway paving
- Cherry Avenue (Maple to Main)
- Complete sidewalks
- Complete CSBC
- Complete concrete roadway
- Cherry Ave and Maple St intersection
- Complete roadway grinding
- Complete roadway paving
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Complete pouring concrete curb and gutter
- Complete pouring concrete sidewalks and ramps
- Complete CSBC
- Complete pouring concrete roadway
- Begin demolition of the North side of Main Street