06/26/2023 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/23/2023
- Main Street
- HMA base Lift
- Academy/Cherry
- Begin Storm system
- Complete Water Main Testing
- Begin Subgrade and place rock
- Cherry Avenue (Maple to Main)
- Complete pouring concrete sidewalk
- Complete pouring concrete roadway
- Complete pouring concrete curb
- Complete bollards
- Complete decorative strip
- Kincaid/Park
- Complete water service transfers
- Continue Landscaping
- Kincaid Avenue
- Continue water service transfers
- Continue Landscaping
WORK IN PROGRESS THIS WEEK (06/26/2023 - 06/30/2023)
- Main Street
- HMA base Lift
- Continue Landscaping
- Academy/Cherry
- Continue Storm system
- Continue curb and sidewalk
- Begin Subgrade and place rock
- Cherry Avenue (Maple to Main)
- Continue Landscaping
- Kincaid/Park
- Complete HMA
- Complete curb and sidewalk
- Complete water service transfers
- Continue Landscaping
- Kincaid Avenue
- Continue water service transfers
- Continue Landscaping
- Academy/Wood
- Begin Demolition
- Begin Subgrade and Rock
- Begin curb and sidewalk
- Begin HMA
UPCOMING WORK THROUGH 07/14/2023
- Main Street
- Complete landscaping
- Complete grind/overlay
- Academy/Cherry
- Complete Storm System
- Complete water main tie in
- Complete curbs/sidewalks
- Complete HMA Base Lift
- Complete Landscaping
- Cherry Avenue (Maple to Main)
- Complete landscaping
- Kincaid/Park
- Complete grind & overlay
- Complete sidewalks
- Complete landscaping
- Install permanent striping and signage