06/26/2023 Construction Update

WORK COMPLETED FOR WEEK ENDING 06/23/2023

  • Main Street
    • HMA base Lift
  • Academy/Cherry
    • Begin Storm system
    • Complete Water Main Testing
    • Begin Subgrade and place rock
  • Cherry Avenue (Maple to Main)
    • Complete pouring concrete sidewalk
    • Complete pouring concrete roadway
    • Complete pouring concrete curb
    • Complete bollards
    • Complete decorative strip
  • Kincaid/Park
    • Complete water service transfers
    • Continue Landscaping
  • Kincaid Avenue
    • Continue water service transfers
    • Continue Landscaping


6/22/2023 Kincaid Avenue - Continue Landscaping


6/22/2023 Cherry Avenue - Complete Bollard Install



WORK IN PROGRESS THIS WEEK (06/26/2023 - 06/30/2023)

  • Main Street
    • HMA base Lift
    • Continue Landscaping
  • Academy/Cherry
    • Continue Storm system
    • Continue curb and sidewalk
    • Begin Subgrade and place rock
  • Cherry Avenue (Maple to Main)
    • Continue Landscaping
  • Kincaid/Park
    • Complete HMA
    • Complete curb and sidewalk
    • Complete water service transfers
    • Continue Landscaping
  • Kincaid Avenue
    • Continue water service transfers
    • Continue Landscaping
  • Academy/Wood
    • Begin Demolition
    • Begin Subgrade and Rock
    • Begin curb and sidewalk
    • Begin HMA

UPCOMING WORK THROUGH 07/14/2023

  • Main Street
    • Complete landscaping
    • Complete grind/overlay
  • Academy/Cherry
    • Complete Storm System
    • Complete water main tie in
    • Complete curbs/sidewalks
    • Complete HMA Base Lift
    • Complete Landscaping
  • Cherry Avenue (Maple to Main)
    • Complete landscaping
  • Kincaid/Park
    • Complete grind & overlay
    • Complete sidewalks
    • Complete landscaping
  • Install permanent striping and signage
Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>