05/15/2023 Construction Update
Upcoming Construction Traffic Impact
MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY
May 17th - ALLEYWAY BETWEEN KINCAID AND ALDER WILL BE RETURNED TO TRADITIONAL EASTBOUND CONFIGURATION
WORK COMPLETED FOR WEEK ENDING 05/12/2023
- Alder/Main/Academy/Ryan
- Complete roadway grinding
- Complete roadway overlay
- Cherry Avenue (Maple to Main)
- Begin pouring concrete sidewalk
- Begin pouring concrete roadway
- Continue pouring concrete curb
- Main Street
- Concrete pavement cure
- Kincaid
- Complete water service transfer
WORK IN PROGRESS THIS WEEK (05/15/2023 - 05/19/2023)
- Alder/Main/Academy/Ryan
- Begin rising hardware on roadway
- Begin sign install
- Cherry Avenue (Maple to Main)
- Continue pouring concrete sidewalk
- Continue pouring concrete roadway
- Continue pouring concrete curb
- Begin subgrade and CSCT
- Begin storm system
- Main Street
- Transfer traffic to eastbound only
- Begin demolition of the North side of Main Street
- Begin installing storm system
- Begin JUT
UPCOMING WORK THROUGH (06/02/2023)
- Alder/Main/Academy/Ryan/Park
- Complete raising hardware on roadway
- Complete installation of signs
- Complete seeding
- Cherry Avenue (Maple to Main)
- Complete sidewalks
- Complete CSBC
- Complete concrete roadway
- Cherry Ave and Maple St intersection
- Complete roadway grinding
- Complete roadway paving
- Complete storm system
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Complete pouring concrete curb and gutter
- Complete pouring concrete sidewalks and ramps
- Complete CSBC
- Complete pouring concrete roadway
- Academy/Cherry
- Complete Demolition
- Complete Storm System
- Complete water line