05/15/2023 Construction Update

Upcoming Construction Traffic Impact

  • MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY

  • May 17th - ALLEYWAY BETWEEN KINCAID AND ALDER WILL BE RETURNED TO TRADITIONAL EASTBOUND CONFIGURATION



WORK COMPLETED FOR WEEK ENDING 05/12/2023

  • Alder/Main/Academy/Ryan
    • Complete roadway grinding
    • Complete roadway overlay
  • Cherry Avenue (Maple to Main)
    • Begin pouring concrete sidewalk
    • Begin pouring concrete roadway
    • Continue pouring concrete curb
  • Main Street
    • Concrete pavement cure
  • Kincaid
    • Complete water service transfer

05/08/2023 Cherry Ave - Pouring Concrete Sidewalk

05/09/2023 Academy Street - Roadway Grinding

05/11/2023 Main Street - Roadway Overlay

WORK IN PROGRESS THIS WEEK (05/15/2023 - 05/19/2023)

  • Alder/Main/Academy/Ryan
    • Begin rising hardware on roadway
    • Begin sign install
  • Cherry Avenue (Maple to Main)
    • Continue pouring concrete sidewalk
    • Continue pouring concrete roadway
    • Continue pouring concrete curb
    • Begin subgrade and CSCT
    • Begin storm system
  • Main Street
    • Transfer traffic to eastbound only
    • Begin demolition of the North side of Main Street
    • Begin installing storm system
    • Begin JUT

UPCOMING WORK THROUGH (06/02/2023)

  • Alder/Main/Academy/Ryan/Park
    • Complete raising hardware on roadway
    • Complete installation of signs
    • Complete seeding
  • Cherry Avenue (Maple to Main)
    • Complete sidewalks
    • Complete CSBC
    • Complete concrete roadway
  • Cherry Ave and Maple St intersection
    • Complete roadway grinding
    • Complete roadway paving
    • Complete storm system
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Complete roadway excavation and grading
    • Complete pouring concrete curb and gutter
    • Complete pouring concrete sidewalks and ramps
    • Complete CSBC
    • Complete pouring concrete roadway
  • Academy/Cherry
    • Complete Demolition
    • Complete Storm System
    • Complete water line
Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>