05/22/2023 Construction Update
Upcoming Construction Traffic Impact
Starting MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY
WORK COMPLETED FOR WEEK ENDING 05/12/2023
- Alder/Main/Academy/Ryan
- Completed raising hardware on roadway after overlay
- Completed sign installation
- Cherry Avenue (Maple to Main)
- Continue pouring concrete sidewalk
- Continue pouring concrete roadway
- Continue pouring concrete curb
- Begin subgrade and CSTC
- Begin storm system
- Main Street
- Transfer traffic to eastbound only
- Completed demolition of the North side of Main Street
- Completed installing storm system
- Begin installing conduit
WORK IN PROGRESS THIS WEEK (05/22/2023 - 05/26/2023)
- Cherry Avenue (Maple to Main)
- Continue pouring concrete sidewalk
- Continue pouring concrete roadway
- Continue pouring concrete curb
- Cherry Avenue / Maple St Intersection
- Begin grading
- Begin paving
- Main Street
- Complete installing conduit
- Complete grading
- Complete pouring curb
- Begin pouring concrete roadway
- Academy/Cherry
- Begin Demolition
UPCOMING WORK THROUGH (06/09/2023)
- Alder/Park
- Complete pouring concrete ramps
- Cherry Avenue (Maple to Main)
- Complete sidewalks
- Complete concrete roadway
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete pouring concrete sidewalks and ramps
- Complete pouring concrete roadway
- Academy/Cherry
- Complete Demolition
- Complete Storm System
- Complete water line
- Complete subgrade
- Complete HMA Base Lift