05/22/2023 Construction Update

Upcoming Construction Traffic Impact

  • Starting MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY



WORK COMPLETED FOR WEEK ENDING 05/12/2023

  • Alder/Main/Academy/Ryan
    • Completed raising hardware on roadway after overlay
    • Completed sign installation
  • Cherry Avenue (Maple to Main)
    • Continue pouring concrete sidewalk
    • Continue pouring concrete roadway
    • Continue pouring concrete curb
    • Begin subgrade and CSTC
    • Begin storm system
  • Main Street
    • Transfer traffic to eastbound only
    • Completed demolition of the North side of Main Street
    • Completed installing storm system
    • Begin installing conduit

05/17/2023 Main Street - Begin Demolition on North Side 05/17/2023 Cherry Ave - Pouring Concrete

05/16/2023 Cherry Ave - Pouring Concrete



WORK IN PROGRESS THIS WEEK (05/22/2023 - 05/26/2023)

  • Cherry Avenue (Maple to Main)
    • Continue pouring concrete sidewalk
    • Continue pouring concrete roadway
    • Continue pouring concrete curb
  • Cherry Avenue / Maple St Intersection
    • Begin grading
    • Begin paving
  • Main Street
    • Complete installing conduit
    • Complete grading
    • Complete pouring curb
    • Begin pouring concrete roadway
  • Academy/Cherry
    • Begin Demolition

UPCOMING WORK THROUGH (06/09/2023)

  • Alder/Park
    • Complete pouring concrete ramps
  • Cherry Avenue (Maple to Main)
    • Complete sidewalks
    • Complete concrete roadway
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Complete pouring concrete sidewalks and ramps
    • Complete pouring concrete roadway
  • Academy/Cherry
    • Complete Demolition
    • Complete Storm System
    • Complete water line
    • Complete subgrade
    • Complete HMA Base Lift
Categories: Construction Update