Upcoming Construction Traffic Impact

  • MAY 9TH - ROADWAY GRINDING IN THE FOLLOWING LOCATIONS:

    1. Main Street from Kincaid to Alder (south side only)

    2. Alder Ave (Park to Maple)

    3. Academy Street (Ryan to Kincaid)

  • MAY 10th 7:00pm - 5:00am - MAIN STREET (TRAFFIC AVE TO ALDER AVE) CLOSED AT RAILROAD TRACKS

  • MAY 11TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:

    1. Eastbound Main Street from Kincaid to Alder

    2. Northbound Alder Ave (Park to Maple)

    3. Southbound Alder (Academy to Park)

  • MAY 12TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:
    1. Alder & Maple Intersection

    2. Academy St (including Ryan Ave)

  • MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY

  • May 16th - ALLEYWAY BETWEEN KINCAID AND ALDER WILL BE RETURNED TO TRADITIONAL EASTBOUND CONFIGURATION



WORK COMPLETED FOR WEEK ENDING 05/05/2023

  • Alder Ave and Park St intersection
    • Complete CSTC
    • Complete Water Tie in at Maple and Alder intersection (Thursday morning starting at 2am)
    • Pour Concrete
    • Complete CSBC
  • Cherry Avenue (Maple to Main)
    • Continue pouring concrete curb
    • Complete CSBC
    • PSE completed pole removals

05/02/2023 Cherry Ave - Continue pouring concrete curb

05/03/2023 Alder Ave/Park St Intersection - Pouring Concrete Curb



WORK IN PROGRESS THIS WEEK (05/08/2023 - 05/12/2023)

  • Alder/Main/Academy/Ryan
    • Complete roadway grinding
    • Complete roadway overlay
  • Cherry Avenue (Maple to Main)
    • Begin pouring concrete sidewalk
    • Begin pouring concrete roadway
    • Continue pouring concrete curb
  • Main Street
    • Concrete pavement cure
  • Kincaid
    • Begin water service transfer

UPCOMING WORK THROUGH (05/26/2023)

  • Alder/Main/Academy/Ryan/Park
    • Complete raising hardware on roadway
    • Complete installation of signs
  • Cherry Avenue (Maple to Main)
    • Complete sidewalks
    • Complete CSBC
    • Complete concrete roadway
  • Cherry Ave and Maple St intersection
    • Complete roadway grinding
    • Complete roadway paving
    • Complete storm system
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Transfer traffic to eastbound only
    • Begin demolition of the North side of Main Street
    • Complete roadway excavation and grading
    • Complete pouring concrete curb and gutter
    • Complete pouring concrete sidewalks and ramps
    • Complete CSBC
    • Complete pouring concrete roadway