05/08/2023 Construction Update
Upcoming Construction Traffic Impact
-
MAY 9TH - ROADWAY GRINDING IN THE FOLLOWING LOCATIONS:
Main Street from Kincaid to Alder (south side only)
Alder Ave (Park to Maple)
Academy Street (Ryan to Kincaid)
MAY 10th 7:00pm - 5:00am - MAIN STREET (TRAFFIC AVE TO ALDER AVE) CLOSED AT RAILROAD TRACKS
-
MAY 11TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:
Eastbound Main Street from Kincaid to Alder
Northbound Alder Ave (Park to Maple)
Southbound Alder (Academy to Park)
-
MAY 12TH - ROADWAY OVERLAY IN THE FOLLOWING LOCATIONS:
Alder & Maple Intersection
Academy St (including Ryan Ave)
MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY
May 16th - ALLEYWAY BETWEEN KINCAID AND ALDER WILL BE RETURNED TO TRADITIONAL EASTBOUND CONFIGURATION
WORK COMPLETED FOR WEEK ENDING 05/05/2023
- Alder Ave and Park St intersection
- Complete CSTC
- Complete Water Tie in at Maple and Alder intersection (Thursday morning starting at 2am)
- Pour Concrete
- Complete CSBC
- Cherry Avenue (Maple to Main)
- Continue pouring concrete curb
- Complete CSBC
- PSE completed pole removals
WORK IN PROGRESS THIS WEEK (05/08/2023 - 05/12/2023)
- Alder/Main/Academy/Ryan
- Complete roadway grinding
- Complete roadway overlay
- Cherry Avenue (Maple to Main)
- Begin pouring concrete sidewalk
- Begin pouring concrete roadway
- Continue pouring concrete curb
- Main Street
- Concrete pavement cure
- Kincaid
- Begin water service transfer
UPCOMING WORK THROUGH (05/26/2023)
- Alder/Main/Academy/Ryan/Park
- Complete raising hardware on roadway
- Complete installation of signs
- Cherry Avenue (Maple to Main)
- Complete sidewalks
- Complete CSBC
- Complete concrete roadway
- Cherry Ave and Maple St intersection
- Complete roadway grinding
- Complete roadway paving
- Complete storm system
- Main St intersection with Kincaid Ave and Cherry Ave
- Transfer traffic to eastbound only
- Begin demolition of the North side of Main Street
- Complete roadway excavation and grading
- Complete pouring concrete curb and gutter
- Complete pouring concrete sidewalks and ramps
- Complete CSBC
- Complete pouring concrete roadway