6/12/2023 Construction Update

WORK COMPLETED FOR WEEK ENDING 06/09/2023

  • Main Street
    • Concrete Roadway Cure
  • Academy/Cherry
    • Begin Water Main Tie In
    • Complete Pressure Test
  • Cherry Avenue (Maple to Main)
    • Complete pouring Sidewalk
    • Complete pouring Roadway
    • Complete pouring Curb
    • Raise Hardware to finish road grade
  • Kincaid/Park
    • Begin water service transfers
    • Complete Landscape and hydroseeding
  • Kincaid
    • Complete Bollard install
    • Continue Irrigation install

06/08/2023 Cherry Avenue - Continue pouring Concrete

06/09/2023 Kincaid Avenue - Continue Irrigation Install



WORK IN PROGRESS THIS WEEK (06/12/2023 - 06/16/2023)

  • Main Street
    • HMA base Lift
  • Academy/Cherry
    • Begin Storm system
    • Begin Water Main Testing
    • Begin Curb & Sidewalk
    • Begin Water Main Tie In
    • Begin Subgrade and place rock
  • Cherry Avenue (Maple to Main)
    • Continue pouring concrete sidewalk
    • Continue pouring concrete roadway
    • Continue pouring concrete curb
  • Kincaid/Park
    • Continue water service transfers
    • Continue Landscaping
  • Kincaid Avenue
    • Continue Irrigation install
    • Continue Landscaping

UPCOMING WORK THROUGH (06/30/2023)

  • Main Street
    • Complete HMA Base Lift
    • Complete landscaping
  • Academy/Cherry
    • Complete Demolition
    • Complete Storm System
    • Complete water line
    • Complete subgrade
    • Complete HMA Base Lift
    • Complete Landscaping
    • Complete Water Main Tie In
  • Cherry Avenue (Maple to Main)
    • Complete sidewalks
    • Complete concrete roadway
    • Complete decorative strips
    • Complete crosswalks
    • Complete bollard install
    • Complete landscaping
  • Kincaid/Park
    • Complete Water Services
    • Complete grind & overlay
    • Complete landscaping
Categories: Construction Update