6/12/2023 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/09/2023
- Main Street
- Concrete Roadway Cure
- Academy/Cherry
- Begin Water Main Tie In
- Complete Pressure Test
- Cherry Avenue (Maple to Main)
- Complete pouring Sidewalk
- Complete pouring Roadway
- Complete pouring Curb
- Raise Hardware to finish road grade
- Kincaid/Park
- Begin water service transfers
- Complete Landscape and hydroseeding
- Kincaid
- Complete Bollard install
- Continue Irrigation install
WORK IN PROGRESS THIS WEEK (06/12/2023 - 06/16/2023)
- Main Street
- HMA base Lift
- Academy/Cherry
- Begin Storm system
- Begin Water Main Testing
- Begin Curb & Sidewalk
- Begin Water Main Tie In
- Begin Subgrade and place rock
- Cherry Avenue (Maple to Main)
- Continue pouring concrete sidewalk
- Continue pouring concrete roadway
- Continue pouring concrete curb
- Kincaid/Park
- Continue water service transfers
- Continue Landscaping
- Kincaid Avenue
- Continue Irrigation install
- Continue Landscaping
UPCOMING WORK THROUGH (06/30/2023)
- Main Street
- Complete HMA Base Lift
- Complete landscaping
- Academy/Cherry
- Complete Demolition
- Complete Storm System
- Complete water line
- Complete subgrade
- Complete HMA Base Lift
- Complete Landscaping
- Complete Water Main Tie In
- Cherry Avenue (Maple to Main)
- Complete sidewalks
- Complete concrete roadway
- Complete decorative strips
- Complete crosswalks
- Complete bollard install
- Complete landscaping
- Kincaid/Park
- Complete Water Services
- Complete grind & overlay
- Complete landscaping