5/30/2023 Construction Update
Upcoming Construction Traffic Impact
Starting MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY
Starting May 31st - KINCAID AVE WILL BE CLOSED FROM 7AM TO 10AM FOR LANDSCAPING.
WORK COMPLETED FOR WEEK ENDING 05/12/2023
- Cherry Avenue (Maple to Main)
- Continue pouring concrete sidewalk
- Continue pouring concrete roadway
- Continue pouring concrete curb
- Cherry Avenue / Maple St Intersection
- Begin grading
- Begin paving
- Main Street
- Complete installing conduit
- Complete grading
- Complete pouring curb
- Academy/Cherry
- Begin Demolition
WORK IN PROGRESS THIS WEEK (05/22/2023 - 05/26/2023)
- Main Street
- Complete pouring crosswalk
- Complete pouring roadway
- Academy/Cherry
- Continue Demolition
- Complete storm system
- Landscaping and hydroseeding throughout project
UPCOMING WORK THROUGH (06/09/2023)
- Cherry Avenue (Maple to Main)
- Complete sidewalks
- Complete concrete roadway
- Complete decorative strips
- Complete crosswalks
- Complete bollard install
- Main St
- Complete HMA Base Lift
- Academy/Cherry
- Complete Demolition
- Complete Storm System
- Complete water line
- Complete subgrade
- Complete HMA Base Lift