5/30/2023 Construction Update

Upcoming Construction Traffic Impact

  • Starting MAY 15th - MAIN STREET WILL BE EASTBOUND ONLY

  • Starting May 31st - KINCAID AVE WILL BE CLOSED FROM 7AM TO 10AM FOR LANDSCAPING.



WORK COMPLETED FOR WEEK ENDING 05/12/2023

  • Cherry Avenue (Maple to Main)
    • Continue pouring concrete sidewalk
    • Continue pouring concrete roadway
    • Continue pouring concrete curb
  • Cherry Avenue / Maple St Intersection
    • Begin grading
    • Begin paving
  • Main Street
    • Complete installing conduit
    • Complete grading
    • Complete pouring curb
  • Academy/Cherry
    • Begin Demolition

05/26/2023 Cherry Ave/Kincaid Ave/Main Street Intersection - Demolition of Nose of Heritage Park

05/26/2023 Academy/Cherry Intersection - Begin Demolition

05/23/2023 Main St - Complete Grading

WORK IN PROGRESS THIS WEEK (05/22/2023 - 05/26/2023)

  • Main Street
    • Complete pouring crosswalk
    • Complete pouring roadway
  • Academy/Cherry
    • Continue Demolition
    • Complete storm system
  • Landscaping and hydroseeding throughout project

UPCOMING WORK THROUGH (06/09/2023)

  • Cherry Avenue (Maple to Main)
    • Complete sidewalks
    • Complete concrete roadway
    • Complete decorative strips
    • Complete crosswalks
    • Complete bollard install
  • Main St
    • Complete HMA Base Lift
  • Academy/Cherry
    • Complete Demolition
    • Complete Storm System
    • Complete water line
    • Complete subgrade
    • Complete HMA Base Lift