10/31/22 Construction Update

Work completed for Week Ending 10/28/2022:

  • Kincaid Avenue (Maple to Main)
    • Water Testing
    • Complete subgrade preparation and place/compact gravel
  • Kincaid Avenue (Academy to Maple)
    • Water Testing
    • Install rebar over watermain trenches and prepare for concrete pours.
  • Academy Street (Kincaid to Alder)
    • Water Testing
    • Install rebar over watermain trenches and prepare for concrete pours.

10/24/22: Pouring concrete on watermain trench on Academy Street between Kincaid Avenue and Alder Avenue10/25/22: Grading the exit from the parking area east of Kincaid Avenue in preparation for temporary re-opening 10/26/22: Exit from the parking area east of Kincaid Avenue prepared for temporary re-opening 10/27/22: Kincaid Avenue temporarily re-opened north of Maple Street

Work in progress this week (10/31/2022 - 11/04/2022):

  • Kincaid Avenue (Maple to Main)
    • Begin illumination system.
  • Intersection of Kincaid Avenue and Academy Street
    • Complete demolition of sidewalks
    • Complete storm drainage improvements

Upcoming Work through 11/18/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete irrigation system.
    • Begin installation of curbs
  • Intersection of Kincaid Avenue and Academy Street
    • Complete grading of intersection
  • Intersection of Kincaid Avenue and Park Street
    • Complete demolition of sidewalks
    • Begin storm drainage improvements
Categories: Construction Update