10/31/22 Construction Update
Work completed for Week Ending 10/28/2022:
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
- Academy Street (Kincaid to Alder)
- Water Testing
Install rebar over watermain trenches and prepare for concrete pours.
10/24/22: Pouring concrete on watermain trench on Academy Street between Kincaid Avenue and Alder Avenue
10/25/22: Grading the exit from the parking area east of Kincaid Avenue in preparation for temporary re-opening
10/26/22: Exit from the parking area east of Kincaid Avenue prepared for temporary re-opening
10/27/22: Kincaid Avenue temporarily re-opened north of Maple Street
Work in progress this week (10/31/2022 - 11/04/2022):
- Kincaid Avenue (Maple to Main)
- Begin illumination system.
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
Upcoming Work through 11/18/2022:
- Kincaid Avenue (Maple to Main):
- Complete irrigation system.
- Begin installation of curbs
- Intersection of Kincaid Avenue and Academy Street
- Complete grading of intersection
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
