11/28/22 Construction Update

Work completed for Week Ending 11/25/2022:

  • Kincaid Avenue (Maple to Main)
    • Started pouring concrete curbs and sidewalk

11/21/22: Concrete curb formwork on Kincaid between Main Street and Maple Street.

11/21/22: Concrete sidewalk poured on the west side of Kincaid Avenue south of Main Street.

11/23/22: New concrete sidewalk on the west side of Kincaid Avenue south of Main Street.

11/23/22: Grading Kincaid Avenue for concrete roadway south of Main Street.

Work in progress this week (11/28/2022 - 12/02/2022):

  • Kincaid Avenue (Maple to Main)
    • Complete grading for concrete
    • Complete pouring curbs and sidewalks
    • Start pouring concrete roadway
  • Intersection of Kincaid Avenue and Park Street
    • Complete demolition of sidewalks
    • Begin storm drainage improvements

Upcoming Work through 12/16/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete pouring concrete roadway
  • Kincaid Avenue (Academy to Maple)
    • Begin pouring curbs and sidewalks
  • Kincaid Avenue (Park to Academy)
    • Begin pouring curbs and sidewalks
  • Intersection of Kincaid Avenue and Park Street
    • Complete storm drainage improvements
    • Complete roadway excavation and grading for intersection paving
  • Academy Street
    • Begin water main installation