11/14/22 Construction Update

Work completed for Week Ending 11/11/2022:

  • Kincaid Avenue (Maple to Main)
    • Complete illumination system.
    • Complete irrigation system
  • Maple Street
    • Complete water main connections.

11/09/22: Pounding rebar into existing concrete roadway over water service connection trenches.

11/10/22: Completed water main connections on Maple Street on either side of Kincaid Avenue.

Work in progress this week (11/14/2022 - 11/18/2022):

  • Kincaid Avenue (Maple to Main)
    • Complete demolition of sidewalks
    • Complete grading for concrete
    • Pour curbs and sidewalks

Upcoming Work through 12/02/2022:

  • Kincaid Avenue (Maple to Main):
    • Pour flush curbs
    • Pour concrete roadway
  • Intersection of Kincaid Avenue and Park Street
    • Complete demolition of sidewalks
    • Complete storm drainage improvements
    • Complete roadway excavation for intersection paving
Categories: Construction Update