11/14/22 Construction Update
Work completed for Week Ending 11/11/2022:
- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Maple Street
- Complete water main connections.
Work in progress this week (11/14/2022 - 11/18/2022):
- Kincaid Avenue (Maple to Main)
- Complete demolition of sidewalks
- Complete grading for concrete
- Pour curbs and sidewalks
Upcoming Work through 12/02/2022:
- Kincaid Avenue (Maple to Main):
- Pour flush curbs
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements