10/17/22 Construction Update

Work completed for Week Ending 10/14/2022:

  • Kincaid (Academy to Maple)
    • Complete water service connection crossings (still need to connect to make connections)
  • Kincaid Avenue (Park to Academy)
    • Complete water service connection crossings (still need to connect to make connections)
  • Kincaid Avenue (south of Park to tie-in)
    • Complete water service connection crossings (still need to connect to make connections)
  • Park Street (Kincaid to Alder)
    • Complete water service connection crossings (still need to connect to make connections)

10/10/22: Sawcutting for water service connections on Park Street between Kincaid Avenue and Alder Avenue 10/11/22: Removing asphalt for water service connections on Kincaid Avenue between Maple Street and Academy Street

10/12/22: Asphalt over Concrete pavement removed for water service connections on Kincaid Avenue between Academy Street and Park Street.

10/13/22: Compacting after water service connection crossing on Park Street east of Kincaid Avenue.

Work in progress this week (10/17/2022 - 10/21/2022):

  • Kincaid Avenue (Maple to Main)
    • Water Testing
    • Complete subgrade preparation and place/compact gravel
  • Kincaid Avenue (Academy to Maple)
    • Water Testing
  • Academy Street (Kincaid to Alder)
    • Water Testing

Upcoming Work through 11/04/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
  • Kincaid Avenue (Academy to Maple):
    • Continue water service connections.
    • Pour concrete and place asphalt over waterline trenches.
  • Kincaid Avenue/Academy Street Intersection
    • Demolition for storm drainage installation.
  • Kincaid Avenue (Park to Academy)
    • Continue water service connections.
    • Water Testing
    • Pour concrete and place asphalt over waterline trenches.
  • Kincaid Avenue (south of Park to tie-in)
    • Continue water service connections.
    • Water Testing
    • Pour concrete and place asphalt over waterline trenches.
  • Academy Street (Kincaid to Alder)
    • Continue water service connections.
  • Park Street (Kincaid to Alder)
    • Continue water service connections.
Categories: Construction Update