10/17/22 Construction Update
Work completed for Week Ending 10/14/2022:
- Kincaid (Academy to Maple)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (Park to Academy)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (south of Park to tie-in)
- Complete water service connection crossings (still need to connect to make connections)
- Park Street (Kincaid to Alder)
- Complete water service connection crossings (still need to connect to make connections)
Work in progress this week (10/17/2022 - 10/21/2022):
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Academy Street (Kincaid to Alder)
- Water Testing
Upcoming Work through 11/04/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue/Academy Street Intersection
- Demolition for storm drainage installation.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Academy Street (Kincaid to Alder)
- Continue water service connections.
- Park Street (Kincaid to Alder)
- Continue water service connections.