10/03/22 Construction Update
Work completed for Week Ending 09/30/2022:
- Academy Street (Kincaid to Alder)- Complete waterline installation (still need to complete water service connections)
 
 Looking south from Main Street towards Heritage Park
Looking south from Main Street towards Heritage Park
 09/26/2022: Installing waterline on Academy Street between Kincaid Avenue and Alder Avenue.
09/26/2022: Installing waterline on Academy Street between Kincaid Avenue and Alder Avenue.  09/27/2022: Continuing excavation for waterline installation on Academy Street between Kincaid Avenue and Alder Avenue.
09/27/2022: Continuing excavation for waterline installation on Academy Street between Kincaid Avenue and Alder Avenue.  09/28/2022: Installing water service connection to 902 Kincaid Avenue.
09/28/2022: Installing water service connection to 902 Kincaid Avenue.
 09/29/2022: Compacting water service connection crossings on Kincaid Avenue between Academy Street and Maple Street.
09/29/2022: Compacting water service connection crossings on Kincaid Avenue between Academy Street and Maple Street.Work in progress this week (10/03/2022 - 10/07/2022):
- Kincaid Avenue (Maple to Main)- Continue water service connections
 
- Kincaid Avenue (Academy to Maple)- Continue water service connections
 
- Kincaid Avenue (Park to Academy)- Continue water service connections
 
- Kincaid Avenue (south of Park to tie-in)- Begin waterline and water service connection installation
 
- Academy Street (Kincaid to Alder)- Begin water service connections
- Complete Installing dowels for concrete panels
 
- Park Street (Kincaid to Alder)- Begin waterline and water service connection installation
 
Upcoming Work through 10/21/2022:
- Kincaid Avenue (Maple to Main):- Begin illumination system.
- Begin irrigation system.
 
- Kincaid Avenue (Academy to Maple):- Continue water service connections.
 
- Kincaid Avenue (Park to Academy)- Continue water service connections.
 
- Kincaid Avenue (south of Park to tie-in)- Continue water service connections
 
- Academy Street (Kincaid to Alder)- Continue water service connections
 
- Park Street (Kincaid to Alder)- Continue waterline and water service connection installation
 
 