10/03/22 Construction Update

Work completed for Week Ending 09/30/2022:

  • Academy Street (Kincaid to Alder)
    • Complete waterline installation (still need to complete water service connections)

Looking south from Main Street towards Heritage Park

09/26/2022: Installing waterline on Academy Street between Kincaid Avenue and Alder Avenue. 09/27/2022: Continuing excavation for waterline installation on Academy Street between Kincaid Avenue and Alder Avenue. 09/28/2022: Installing water service connection to 902 Kincaid Avenue.

09/29/2022: Compacting water service connection crossings on Kincaid Avenue between Academy Street and Maple Street.

Work in progress this week (10/03/2022 - 10/07/2022):

  • Kincaid Avenue (Maple to Main)
    • Continue water service connections
  • Kincaid Avenue (Academy to Maple)
    • Continue water service connections
  • Kincaid Avenue (Park to Academy)
    • Continue water service connections
  • Kincaid Avenue (south of Park to tie-in)
    • Begin waterline and water service connection installation
  • Academy Street (Kincaid to Alder)
    • Begin water service connections
    • Complete Installing dowels for concrete panels
  • Park Street (Kincaid to Alder)
    • Begin waterline and water service connection installation

Upcoming Work through 10/21/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
  • Kincaid Avenue (Academy to Maple):
    • Continue water service connections.
  • Kincaid Avenue (Park to Academy)
    • Continue water service connections.
  • Kincaid Avenue (south of Park to tie-in)
    • Continue water service connections
  • Academy Street (Kincaid to Alder)
    • Continue water service connections
  • Park Street (Kincaid to Alder)
    • Continue waterline and water service connection installation
Categories: Construction Update