10/03/22 Construction Update
Work completed for Week Ending 09/30/2022:
- Academy Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (10/03/2022 - 10/07/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin waterline and water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin waterline and water service connection installation
Upcoming Work through 10/21/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Continue water service connections
- Park Street (Kincaid to Alder)
- Continue waterline and water service connection installation