11/07/22 Construction Update
Work completed for Week Ending 11/04/2022:
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
11/01/22: Demolition on Kincaid Avenue north of Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings.
11/03/22: Excavation on the NW corner of Kincaid Avenue and Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings.
11/03/22: Laying geotextile fabric on the subgrade to support the roadway structure on the NW corner of Kincaid Avenue and Academy Street.

- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Complete trench restoration
Upcoming Work through 11/25/2022:
- Kincaid Avenue (Maple to Main):
- Complete installation of curbs
- Complete sidewalks (currently projected 11/21-11/23, but this may change)
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements