11/01/22: Demolition on Kincaid Avenue north of Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings.11/03/22: Excavation on the NW corner of Kincaid Avenue and Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings.11/03/22: Laying geotextile fabric on the subgrade to support the roadway structure on the NW corner of Kincaid Avenue and Academy Street.
11/03/22: Rolling to compact on the NW corner of Kincaid Avenue and Academy Street.
Work in progress this week (11/07/2022 - 11/11/2022):
Kincaid Avenue (Maple to Main)
Complete illumination system.
Complete irrigation system
Complete trench restoration
Upcoming Work through 11/25/2022:
Kincaid Avenue (Maple to Main):
Complete installation of curbs
Complete sidewalks (currently projected 11/21-11/23, but this may change)