12/05/22 Construction Update

Work completed for Week Ending 12/02/2022:

  • Kincaid Avenue (Maple to Main)
    • Continued pouring concrete curbs and sidewalk
  • Intersection of Kincaid Avenue and Park Street
    • Complete demolition of sidewalks

11/28/22: Pouring and finishing new concrete sidewalk on the west side of Kincaid Avenue north of Maple Street 11/29/22: Demolishing intersection of Kincaid Avenue and Park Street.

11/29/22: Temporary asphalt on the south side of intersection of Main Street/Kincaid Avenue/Cherry Avenue for the Santa Parade.

11/30/22: Formwork for planters on the east side of Kincaid Avenue south of Main Street.

Work in progress this week (12/05/2022 - 12/09/2022):

  • Kincaid Avenue (Maple to Main)
    • Complete grading for concrete
    • Complete pouring curbs and sidewalks
    • Start pouring concrete roadway
  • Intersection of Kincaid Avenue and Park Street
    • Complete demolition
    • Begin storm drainage improvements

Upcoming Work through 12/23/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete pouring concrete roadway
  • Kincaid Avenue (Academy to Maple)
    • Begin pouring curbs
  • Kincaid Avenue (Park to Academy)
    • Begin pouring curbs
  • Intersection of Kincaid Avenue and Park Street
    • Complete storm drainage improvements
    • Complete roadway excavation and grading for intersection paving
  • Alder Avenue (Academy to Maple)
    • Begin water main installation