12/05/22 Construction Update
Work completed for Week Ending 12/02/2022:
- Kincaid Avenue (Maple to Main)
- Continued pouring concrete curbs and sidewalk
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
11/28/22: Pouring and finishing new concrete sidewalk on the west side of Kincaid Avenue north of Maple Street
11/29/22: Demolishing intersection of Kincaid Avenue and Park Street.
11/29/22: Temporary asphalt on the south side of intersection of Main Street/Kincaid Avenue/Cherry Avenue for the Santa Parade.
11/30/22: Formwork for planters on the east side of Kincaid Avenue south of Main Street.
Work in progress this week (12/05/2022 - 12/09/2022):
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete
- Complete pouring curbs and sidewalks
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition
- Begin storm drainage improvements
Upcoming Work through 12/23/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Kincaid Avenue (Academy to Maple)
- Begin pouring curbs
- Kincaid Avenue (Park to Academy)
- Begin pouring curbs
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete roadway excavation and grading for intersection paving
- Alder Avenue (Academy to Maple)
- Begin water main installation