Work completed for Week Ending 11/18/2022:
- Kincaid Avenue (Maple to Main)
- Completed sidewalk demolition and grading
- Completed pouring concrete curb
- Started pouring concrete sidewalk
- Kincaid Avenue (Park to Academy)
- Completed trench restoration
11/15/22: Checking subgrade elevation on Kincaid Avenue south of Main Street.
Work in progress this week (11/21/2022 - 11/25/2022):
- Kincaid Avenue (Maple to Main)
- Continue pouring curbs and sidewalks
Upcoming Work through 12/09/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring curbs and sidewalks
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements