11/21/22 Construction Update

Work completed for Week Ending 11/18/2022:

  • Kincaid Avenue (Maple to Main)
    • Completed sidewalk demolition and grading
    • Completed pouring concrete curb
    • Started pouring concrete sidewalk
  • Kincaid Avenue (Park to Academy)
    • Completed trench restoration

11/14/22: Pouring concrete over water service connection crossings on Kincaid Avenue south of Academy Street.

11/15/22: Checking subgrade elevation on Kincaid Avenue south of Main Street.


11/16/22: Pouring concrete curb on the east side of Kincaid Avenue between Maple Street and Main Street.


11/17/22: Formwork for concrete planter on the east side of Kincaid Avenue between Maple Street and Main Street.



11/18/22: New concrete sidewalk on the east side of Kincaid Avenue south of Main Street.


Work in progress this week (11/21/2022 - 11/25/2022):

  • Kincaid Avenue (Maple to Main)
    • Continue pouring curbs and sidewalks

Upcoming Work through 12/09/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete pouring curbs and sidewalks
    • Pour concrete roadway
  • Intersection of Kincaid Avenue and Park Street
    • Complete demolition of sidewalks
    • Complete storm drainage improvements
    • Complete roadway excavation for intersection paving