10/24/22 Construction Update

Work completed for Week Ending 10/21/2022:

  • Kincaid Avenue (Maple to Main)
    • Water Testing
    • Complete subgrade preparation and place/compact gravel
  • Kincaid Avenue (Academy to Maple)
    • Water Testing
    • Install rebar over watermain trenches and prepare for concrete pours.
  • Academy Street (Kincaid to Alder)
    • Water Testing
    • Install rebar over watermain trenches and prepare for concrete pours.

10/17/22: Grading on Kincaid Avenue south of Main Street. 10/18/22: Grading on Kincaid Avenue north of Maple Street 10/19/22: Place rock on Kincaid Avenue between Main Street and Maple Street 10/20/22: Compacting rock on Kincaid Avenue south of Main Street 10/21/22: Placing temporary asphalt on Kincaid Avenue south of Maple Street

Work in progress this week (10/24/2022 - 10/28/2022):

  • Kincaid Avenue (Academy to Maple)
    • Pour concrete over watermain trenches.
    • Place asphalt over watermain trenches.
  • Kincaid Avenue (Park to Academy)
    • Water Testing
  • Kincaid Avenue (south of Park)
    • Water Testing
  • Academy Street (Kincaid to Alder)
    • Pour concrete over watermain trenches.
    • Place asphalt over watermain trenches.
  • Park Street (Kincaid to Alder)
    • Water Testing

Upcoming Work through 11/11/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
  • Kincaid Avenue (Academy to Maple):
    • Continue water service connections.
  • Kincaid Avenue/Academy Street Intersection
    • Demolition for storm drainage installation.
    • Install storm drainage pipes and structures.
    • Grade for concrete placement.
  • Kincaid Avenue (Park to Academy)
    • Continue water service connections.
    • Water Testing
    • Pour concrete and place asphalt over waterline trenches.
  • Kincaid Avenue (south of Park to tie-in)
    • Continue water service connections.
    • Water Testing
    • Pour concrete and place asphalt over waterline trenches.
  • Park Street (Kincaid to Alder)
    • Continue water service connections.
    • Water Testing
    • Pour concrete and place asphalt over waterline trenches.