-
12/05/22 Construction Update
Work completed for Week Ending 12/02/2022:
- Kincaid Avenue (Maple to Main)
- Continued pouring concrete curbs and sidewalk
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
11/28/22: Pouring and finishing new concrete sidewalk on the west side of Kincaid Avenue north of Maple Street
11/29/22: Demolishing intersection of Kincaid Avenue and Park Street.
11/29/22: Temporary asphalt on the south side of intersection of Main Street/Kincaid Avenue/Cherry Avenue for the Santa Parade.
11/30/22: Formwork for planters on the east side of Kincaid Avenue south of Main Street.
Work in progress this week (12/05/2022 - 12/09/2022):
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete
- Complete pouring curbs and sidewalks
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition
- Begin storm drainage improvements
Upcoming Work through 12/23/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Kincaid Avenue (Academy to Maple)
- Begin pouring curbs
- Kincaid Avenue (Park to Academy)
- Begin pouring curbs
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete roadway excavation and grading for intersection paving
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Kincaid Avenue (Maple to Main)
-
11/28/22 Construction Update
Work completed for Week Ending 11/25/2022:
- Kincaid Avenue (Maple to Main)
- Started pouring concrete curbs and sidewalk
11/21/22: Concrete curb formwork on Kincaid between Main Street and Maple Street.
11/21/22: Concrete sidewalk poured on the west side of Kincaid Avenue south of Main Street.
11/23/22: New concrete sidewalk on the west side of Kincaid Avenue south of Main Street.
11/23/22: Grading Kincaid Avenue for concrete roadway south of Main Street.
Work in progress this week (11/28/2022 - 12/02/2022):
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete
- Complete pouring curbs and sidewalks
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
Upcoming Work through 12/16/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Kincaid Avenue (Academy to Maple)
- Begin pouring curbs and sidewalks
- Kincaid Avenue (Park to Academy)
- Begin pouring curbs and sidewalks
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete roadway excavation and grading for intersection paving
- Academy Street
- Begin water main installation
- Kincaid Avenue (Maple to Main)
-
11/21/22 Construction Update
Work completed for Week Ending 11/18/2022:
- Kincaid Avenue (Maple to Main)
- Completed sidewalk demolition and grading
- Completed pouring concrete curb
- Started pouring concrete sidewalk
- Kincaid Avenue (Park to Academy)
- Completed trench restoration
11/14/22: Pouring concrete over water service connection crossings on Kincaid Avenue south of Academy Street.
11/15/22: Checking subgrade elevation on Kincaid Avenue south of Main Street.11/16/22: Pouring concrete curb on the east side of Kincaid Avenue between Maple Street and Main Street.
11/17/22: Formwork for concrete planter on the east side of Kincaid Avenue between Maple Street and Main Street.
11/18/22: New concrete sidewalk on the east side of Kincaid Avenue south of Main Street.
Work in progress this week (11/21/2022 - 11/25/2022):
- Kincaid Avenue (Maple to Main)
- Continue pouring curbs and sidewalks
Upcoming Work through 12/09/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring curbs and sidewalks
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Complete roadway excavation for intersection paving
- Kincaid Avenue (Maple to Main)
-
11/14/22 Construction Update
Work completed for Week Ending 11/11/2022:
- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Maple Street
- Complete water main connections.
11/09/22: Pounding rebar into existing concrete roadway over water service connection trenches.
11/10/22: Completed water main connections on Maple Street on either side of Kincaid Avenue.
Work in progress this week (11/14/2022 - 11/18/2022):
- Kincaid Avenue (Maple to Main)
- Complete demolition of sidewalks
- Complete grading for concrete
- Pour curbs and sidewalks
Upcoming Work through 12/02/2022:
- Kincaid Avenue (Maple to Main):
- Pour flush curbs
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Complete roadway excavation for intersection paving
- Kincaid Avenue (Maple to Main)
-
11/07/22 Construction Update
Work completed for Week Ending 11/04/2022:
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
11/01/22: Demolition on Kincaid Avenue north of Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings.
11/03/22: Excavation on the NW corner of Kincaid Avenue and Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings.
11/03/22: Laying geotextile fabric on the subgrade to support the roadway structure on the NW corner of Kincaid Avenue and Academy Street.
11/03/22: Rolling to compact on the NW corner of Kincaid Avenue and Academy Street.
- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Complete trench restoration
Upcoming Work through 11/25/2022:
- Kincaid Avenue (Maple to Main):
- Complete installation of curbs
- Complete sidewalks (currently projected 11/21-11/23, but this may change)
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
- Intersection of Kincaid Avenue and Academy Street
-
10/31/22 Construction Update
Work completed for Week Ending 10/28/2022:
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
- Academy Street (Kincaid to Alder)
- Water Testing
Install rebar over watermain trenches and prepare for concrete pours.
10/24/22: Pouring concrete on watermain trench on Academy Street between Kincaid Avenue and Alder Avenue
10/25/22: Grading the exit from the parking area east of Kincaid Avenue in preparation for temporary re-opening
10/26/22: Exit from the parking area east of Kincaid Avenue prepared for temporary re-opening
10/27/22: Kincaid Avenue temporarily re-opened north of Maple Street
- Kincaid Avenue (Maple to Main)
- Begin illumination system.
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
Upcoming Work through 11/18/2022:
- Kincaid Avenue (Maple to Main):
- Complete irrigation system.
- Begin installation of curbs
- Intersection of Kincaid Avenue and Academy Street
- Complete grading of intersection
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
- Kincaid Avenue (Maple to Main)
-
10/24/22 Construction Update
Work completed for Week Ending 10/21/2022:
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
- Academy Street (Kincaid to Alder)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
10/17/22: Grading on Kincaid Avenue south of Main Street.
10/18/22: Grading on Kincaid Avenue north of Maple Street
10/19/22: Place rock on Kincaid Avenue between Main Street and Maple Street
10/20/22: Compacting rock on Kincaid Avenue south of Main Street
10/21/22: Placing temporary asphalt on Kincaid Avenue south of Maple Street
Work in progress this week (10/24/2022 - 10/28/2022):
- Kincaid Avenue (Academy to Maple)
- Pour concrete over watermain trenches.
- Place asphalt over watermain trenches.
- Kincaid Avenue (Park to Academy)
- Water Testing
- Kincaid Avenue (south of Park)
- Water Testing
- Academy Street (Kincaid to Alder)
- Pour concrete over watermain trenches.
- Place asphalt over watermain trenches.
- Park Street (Kincaid to Alder)
- Water Testing
Upcoming Work through 11/11/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Kincaid Avenue/Academy Street Intersection
- Demolition for storm drainage installation.
- Install storm drainage pipes and structures.
- Grade for concrete placement.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Park Street (Kincaid to Alder)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (Maple to Main)
-
10/17/22 Construction Update
Work completed for Week Ending 10/14/2022:
- Kincaid (Academy to Maple)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (Park to Academy)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (south of Park to tie-in)
- Complete water service connection crossings (still need to connect to make connections)
- Park Street (Kincaid to Alder)
- Complete water service connection crossings (still need to connect to make connections)
10/10/22: Sawcutting for water service connections on Park Street between Kincaid Avenue and Alder Avenue
10/11/22: Removing asphalt for water service connections on Kincaid Avenue between Maple Street and Academy Street
10/12/22: Asphalt over Concrete pavement removed for water service connections on Kincaid Avenue between Academy Street and Park Street.
10/13/22: Compacting after water service connection crossing on Park Street east of Kincaid Avenue.
Work in progress this week (10/17/2022 - 10/21/2022):
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Academy Street (Kincaid to Alder)
- Water Testing
Upcoming Work through 11/04/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue/Academy Street Intersection
- Demolition for storm drainage installation.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Academy Street (Kincaid to Alder)
- Continue water service connections.
- Park Street (Kincaid to Alder)
- Continue water service connections.
- Kincaid (Academy to Maple)
-
10/10/22 Construction Update
There was a recent question about this project on the Rumors & Questions page. Click here to see the question and response.
Work completed for Week Ending 10/07/2022:
- Kincaid Avenue (south of Park to tie-in)
- Complete waterline installation (still need to complete water service connections)
- Park Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
10/03/22: Removing asphalt for water service connections on Kincaid Avenue between Park Street and Academy Street.
10/04/22: Compacting the backfill on the waterline trench on the NW corner of Kincaid Avenue and Park Street.
10/06/22: Excavating for watermain installation on Park Street west of Alder Avenue.
Work in progress this week (10/10/2022 - 10/14/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin water service connection installation
Upcoming Work through 10/28/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Begin testing watermain.
- Complete roadway subgrade.
- Kincaid Avenue (Academy to Maple):
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Begin testing watermain.
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Begin testing watermain.
- Continue water service connections
- Park Street (Kincaid to Alder)
- Begin testing watermain.
- Continue waterline and water service connection installation
- Kincaid Avenue (south of Park to tie-in)
-
10/03/22 Construction Update
Work completed for Week Ending 09/30/2022:
- Academy Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
Looking south from Main Street towards Heritage Park
09/26/2022: Installing waterline on Academy Street between Kincaid Avenue and Alder Avenue.
09/27/2022: Continuing excavation for waterline installation on Academy Street between Kincaid Avenue and Alder Avenue.
09/28/2022: Installing water service connection to 902 Kincaid Avenue.
09/29/2022: Compacting water service connection crossings on Kincaid Avenue between Academy Street and Maple Street.
Work in progress this week (10/03/2022 - 10/07/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin waterline and water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin waterline and water service connection installation
Upcoming Work through 10/21/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Continue water service connections
- Park Street (Kincaid to Alder)
- Continue waterline and water service connection installation
- Academy Street (Kincaid to Alder)