• 02/13/2023 Construction Update

    Work Completed for Week ending 02/10/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue grading for concrete sidewalks and ADA ramps.
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
      • Continue installing storm drainage
    • Cherry Avenue (Maple to Main)
      • Begin demolition

    02/07/2023 - Installing meter and setter boxes along Kincaid.

    2/10/2023 - Demolition on Cherry Ave (Maple to Main)



    Work in progress this week (2/13/2023 - 2/17/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Begin potholing for water.
    • Academy Street (Alder to Park)
      • Continue Water Main installation.
    • Kincaid Avenue and Park Street Intersection
      • Continue concrete sidewalks and ADA ramps
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.

    Upcoming Work through (03/03/2023)

    • Alder Avenue (Park to Academy)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
    • Kincaid Avenue (Park to Maple)
      • Curb Patches
      • Water Testing
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • PSE setting new poles and transferring services to new poles.
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • 02/06/2023 Construction Update

    Work Completed for Week ending 02/03/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue grading for concrete sidewalks and ADA ramps.
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
      • Continue installing storm drainage
    • Cherry Avenue (Maple to Main)
      • Begin demolition.


    Cherry Ave (Maple to Main Street) - Beginning Demolition


    02/01/2023 Cherry Ave (Maple to Main Street) - Beginning Demolition




    02/01/2023 Park Street (Kincaid to Alder) - Water Service Transfers

    Work in progress this week (2/06/2023 - 2/10/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Begin potholing for water.
    • Academy Street (Alder to Park)
      • Begin Water Main installation.
    • Kincaid Avenue and Park Street Intersection
      • Begin concrete sidewalks and ADA ramps

    Upcoming Work through (02/24/2023)

    • Alder Avenue (Park to Academy)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
    • Kincaid Avenue (Park to Maple)
      • Curb Patches
      • Water Testing
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • PSE setting new poles and transferring services to new poles.
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
      • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • 1/30/2023 Construction Update

    Work Completed for Week ending 01/27/2023

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street.
      • Continue storm drainage improvements.
    • Intersection of Kincaid Avenue and Academy Street
      • Continue grading for concrete curbs and sidewalk.
    • Alder Avenue (Park to Academy)
      • Continue water main installation.
    • Alder Avenue (Academy to Maple)
      • Begin water main installation.

    01/25/2023 - Intersection of Kincaid Avenue and Academy Street - Continue concrete curbs and sidewalk

    01/26/2023 - Kincaid Avenue (Maple to Main) - Complete pouring concrete pavement


    Work in progress this week (1/30/2023 - 2/03/2023)

    • Park Street (Kincaid to Alder)
      • Continue water service transfers.
      • Continue grade for concrete.
    • Alder Avenue (Park to Maple)
      • Continue installation of water services, hydrants, and sample station
      • Continue Storm drainage installation.
    • Cherry Avenue (Maple to Main)
      • Set up traffic control.
      • Complete clear and grub
      • Begin demolition.
      • Begin storm drainage installation.

    Upcoming Work through (02/17/2023)

    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
  • 1/23/2023 Construction Update

    Work Completed for Week ending 01/20/2023

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Intersection of Kincaid Avenue and Academy Street
      • Begin grading for concrete curbs and sidewalk
    • Alder Avenue (Park to Academy)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    01/17/2023 - Alder Avenue (Academy to Maple) - Water main installation

    01/17/2023 - Kincaid Avenue (Maple to Main) - Complete pouring concrete pavement
    1/17/2023 - Intersection of Kincaid Avenue and Academy Street - Begin concrete curbs and sidewalk


    Work in progress this week (1/23/2023 - 1/27/2023)

    • Park Street (Kincaid to Alder)
      • Continue water service transfers
      • Complete HMA
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Complete HMA
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
      • Complete HMA
    • Kincaid Avenue (Academy to Maple)
      • Complete water service transfers
      • Complete HMA
    • Kincaid Avenue (Maple to Main)
      • Complete ADA strip concrete
      • Complete sewer CIPP
    • Alder Avenue (Park to Maple
      • Begin installation of water services, hydrants, and sample station
    • Alder Avenue (Maple to Main)
      • Complete sewer CIPP
    • Cherry Avenue (Maple to Main)
      • Complete sewer CIPP
      • Complete tree removal

    Upcoming Work through (02/10/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
  • 1/17/2023 Construction Update

    Work Completed for Week ending 01/13/2023

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Continue water main installation on Alder Avenue (Academy to Park)
    • Continue water main installation

    Work in progress this week (1/16/2023 - 1/20/2023)

    • Kincaid Avenue (Academy to Kincaid)
      • Complete water service transfers
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
    • Park Street (Kincaid to Alder)
      • Complete water service transfers
    • Alder Avenue (Academy to Park)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    Upcoming Work through (02/03/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Begin grading for concrete curbs and sidewalk
    • Prepping for HMA (Maple to Main)
  • 1/09/2023 Construction Update

    Work Completed for Week ending 01/06/2023

    • Kincaid Avenue (Maple to Main)
      • Completed grading for concrete pavement
      • Continued pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continued storm drainage improvements
    • Alder Avenue (Academy to Park)
    • Begin water main installation
    • 1/06/2023 - Kincaid Avenue Maple to Main Street Concrete Pavement1/06/2023 - Intersection of Kincaid Avenue and Park Street storm drain improvements

    1/06/2023 - Alder Avenue Academy to Park Water Main Installation

    Work in progress this week (1/09/2023 - 1/13/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Kincaid Avenue (Academy to Kincaid)
      • Complete water service transfers
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
    • Park Street (Kincaid to Alder)
      • Complete water service transfers
    • Alder Avenue (Academy to Park)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    Upcoming Work through (1/27/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Begin grading for concrete curbs and sidewalks
  • 1/3/2022 Construction Update

    Work Completed for Week ending 12/30/2022

    • No Construction Due to Holiday

    Work in progress this week (1/03/2023 - 1/06/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Alder Avenue (Academy to Park)
      • Begin water main installation

    Upcoming Work through (1/20/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation


  • 12/26/2022 Construction Update

    Work Completed for Week ending 12/23/22

    • Intersection of Kincaid Avenue and Park Street
      • Continue excavation of intersection
      • Begin water service transfers
      • Water tie in on Kincaid south of Park
      • Begin storm drainage improvements
    • Kincaid Avenue (Maple to Main)
      • Continue pouring concrete curbs and sidewalk
      • Continue grading for concrete pavement
      • Continue pouring concrete pavement

    12/19/2022 Pouring Concrete Sidewalk North End of Kincaid Avenue

    12/19/2022 Excavation of Intersection at Kincaid Avenue and Park Street

    12/20/2022 Water Tie In On Kincaid Avenue South of Park Street

    Work in progress this week (12/26/2022 - 12/30/2022)

    • Week of 12/25 - 12/30 No construction due to Holiday

    Upcoming Work through (1/13/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
  • 12/19/22 Construction Update

    Work Completed for Week ending 12/16/22

    • Kincaid Avenue (Maple to Main)
      • Pouring concrete curbs and sidewalk
    • Intersection of Kincaid Avenue and Park Street
      • Excavation of intersection

    12/12/2022 Excavation of intersection at Kincaid Avenue and Park Street

    12/13/2022 Pouring parking strip on North end of Kincaid Avenue

    12/13/2022 Stamping concrete parking strip on North end of Kincaid Avenue

    Work in progress this week (12/19/2022 - 12/23/2022)

    • Intersection of Kincaid Avenue and Park Street
      • Begin water service transfers
      • Water tie in on Kincaid south of Park
      • Begin storm drainage improvements
    • Kincaid Avenue (Maple to Main)
      • Continue grading for concrete pavement
      • Continue pouring concrete pavement

    Upcoming Work through (1/6/2023)

    • Week of 12/25 - 12/30 No construction due to Holiday
    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
  • 12/12/22 Construction Update

    Work completed for Week Ending 12/09/2022:

    • Kincaid Avenue (Maple to Main)
      • Continue pouring concrete curbs and sidewalk
    • Intersection of Kincaid Avenue and Park Street
      • Complete excavation of intersection.

    12/06/22: Finishing concrete sidewalk on the east side of Kincaid Avenue north of Maple Street. 12/07/22: Spreading geotextile fabric over the roadway subgrade at the intersection of Kincaid Avenue and Park Street. 12/08/22: Concrete formwork for driveway on the east side of Kincaid Avenue north of Maple Street 12/09/22: Finishing concrete driveway on east side of Kincaid Avenue north of Maple Street.

    Work in progress this week (12/12/2022 - 12/16/2022):

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete curbs and sidewalk
      • Complete grading for concrete
      • Start pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete intersection grading
      • Begin storm drainage improvements

    Upcoming Work through 12/30/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
    • Alder Avenue (Academy to Maple)
      • Begin water main installation