12/19/22 Construction Update
Work Completed for Week ending 12/16/22
- Kincaid Avenue (Maple to Main)
- Pouring concrete curbs and sidewalk
- Intersection of Kincaid Avenue and Park Street
- Excavation of intersection
12/12/2022 Excavation of intersection at Kincaid Avenue and Park Street
12/13/2022 Pouring parking strip on North end of Kincaid Avenue
12/13/2022 Stamping concrete parking strip on North end of Kincaid Avenue
Work in progress this week (12/19/2022 - 12/23/2022)
- Intersection of Kincaid Avenue and Park Street
- Begin water service transfers
- Water tie in on Kincaid south of Park
- Begin storm drainage improvements
- Kincaid Avenue (Maple to Main)
- Continue grading for concrete pavement
- Continue pouring concrete pavement
Upcoming Work through (1/6/2023)
- Week of 12/25 - 12/30 No construction due to Holiday
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete pavement
- Complete pouring concrete pavement
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements