12/19/22 Construction Update

Work Completed for Week ending 12/16/22

  • Kincaid Avenue (Maple to Main)
    • Pouring concrete curbs and sidewalk
  • Intersection of Kincaid Avenue and Park Street
    • Excavation of intersection

12/12/2022 Excavation of intersection at Kincaid Avenue and Park Street

12/13/2022 Pouring parking strip on North end of Kincaid Avenue

12/13/2022 Stamping concrete parking strip on North end of Kincaid Avenue

Work in progress this week (12/19/2022 - 12/23/2022)

  • Intersection of Kincaid Avenue and Park Street
    • Begin water service transfers
    • Water tie in on Kincaid south of Park
    • Begin storm drainage improvements
  • Kincaid Avenue (Maple to Main)
    • Continue grading for concrete pavement
    • Continue pouring concrete pavement

Upcoming Work through (1/6/2023)

  • Week of 12/25 - 12/30 No construction due to Holiday
  • Kincaid Avenue (Maple to Main)
    • Complete grading for concrete pavement
    • Complete pouring concrete pavement
  • Alder Avenue (Academy to Maple)
    • Begin water main installation
  • Intersection of Kincaid Avenue and Park Street
    • Continue storm drainage improvements
Categories: Construction Update