1/17/2023 Construction Update
Work Completed for Week ending 01/13/2023
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete pavement
- Complete pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements
- Continue water main installation on Alder Avenue (Academy to Park)
- Continue water main installation
Work in progress this week (1/16/2023 - 1/20/2023)
- Kincaid Avenue (Academy to Kincaid)
- Complete water service transfers
- Kincaid Avenue (Park to Academy)
- Complete water service transfers
- Park Street (Kincaid to Alder)
- Complete water service transfers
- Alder Avenue (Academy to Park)
- Continue water main installation
- Alder Avenue (Academy to Maple)
- Begin water main installation
Upcoming Work through (02/03/2023)
- Cherry Avenue (Maple to Main)
- Set up traffic control
- Complete clear and grub
- Begin demolition
- Begin storm drainage installation
- Alder Avenue (Academy to Park)
- Complete water main installation
- Complete water services and hydrants
- Complete water testing
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Begin grading for concrete curbs and sidewalk
- Prepping for HMA (Maple to Main)