1/3/2022 Construction Update

Work Completed for Week ending 12/30/2022

  • No Construction Due to Holiday

Work in progress this week (1/03/2023 - 1/06/2023)

  • Kincaid Avenue (Maple to Main)
    • Complete grading for concrete pavement
    • Complete pouring concrete pavement
  • Intersection of Kincaid Avenue and Park Street
    • Continue storm drainage improvements
  • Alder Avenue (Academy to Park)
    • Begin water main installation

Upcoming Work through (1/20/2023)

  • Cherry Avenue (Maple to Main)
    • Set up traffic control
    • Complete clear and grub
    • Begin demolition
    • Begin storm drainage installation
  • Alder Avenue (Academy to Park)
    • Complete water main installation