12/12/22 Construction Update

Work completed for Week Ending 12/09/2022:

  • Kincaid Avenue (Maple to Main)
    • Continue pouring concrete curbs and sidewalk
  • Intersection of Kincaid Avenue and Park Street
    • Complete excavation of intersection.

12/06/22: Finishing concrete sidewalk on the east side of Kincaid Avenue north of Maple Street. 12/07/22: Spreading geotextile fabric over the roadway subgrade at the intersection of Kincaid Avenue and Park Street. 12/08/22: Concrete formwork for driveway on the east side of Kincaid Avenue north of Maple Street 12/09/22: Finishing concrete driveway on east side of Kincaid Avenue north of Maple Street.

Work in progress this week (12/12/2022 - 12/16/2022):

  • Kincaid Avenue (Maple to Main)
    • Complete pouring concrete curbs and sidewalk
    • Complete grading for concrete
    • Start pouring concrete roadway
  • Intersection of Kincaid Avenue and Park Street
    • Complete intersection grading
    • Begin storm drainage improvements

Upcoming Work through 12/30/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete pouring concrete roadway
  • Intersection of Kincaid Avenue and Park Street
    • Complete storm drainage improvements
  • Alder Avenue (Academy to Maple)
    • Begin water main installation