12/26/2022 Construction Update

Work Completed for Week ending 12/23/22

  • Intersection of Kincaid Avenue and Park Street
    • Continue excavation of intersection
    • Begin water service transfers
    • Water tie in on Kincaid south of Park
    • Begin storm drainage improvements
  • Kincaid Avenue (Maple to Main)
    • Continue pouring concrete curbs and sidewalk
    • Continue grading for concrete pavement
    • Continue pouring concrete pavement

12/19/2022 Pouring Concrete Sidewalk North End of Kincaid Avenue

12/19/2022 Excavation of Intersection at Kincaid Avenue and Park Street

12/20/2022 Water Tie In On Kincaid Avenue South of Park Street

Work in progress this week (12/26/2022 - 12/30/2022)

  • Week of 12/25 - 12/30 No construction due to Holiday

Upcoming Work through (1/13/2023)

  • Kincaid Avenue (Maple to Main)
    • Complete grading for concrete pavement
    • Complete pouring concrete pavement
  • Alder Avenue (Academy to Maple)
    • Begin water main installation
  • Intersection of Kincaid Avenue and Park Street
    • Continue storm drainage improvements
Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>