12/26/2022 Construction Update
Work Completed for Week ending 12/23/22
- Intersection of Kincaid Avenue and Park Street
- Continue excavation of intersection
- Begin water service transfers
- Water tie in on Kincaid south of Park
- Begin storm drainage improvements
- Kincaid Avenue (Maple to Main)
- Continue pouring concrete curbs and sidewalk
- Continue grading for concrete pavement
- Continue pouring concrete pavement
12/19/2022 Pouring Concrete Sidewalk North End of Kincaid Avenue
12/19/2022 Excavation of Intersection at Kincaid Avenue and Park Street
12/20/2022 Water Tie In On Kincaid Avenue South of Park Street
Work in progress this week (12/26/2022 - 12/30/2022)
- Week of 12/25 - 12/30 No construction due to Holiday
Upcoming Work through (1/13/2023)
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete pavement
- Complete pouring concrete pavement
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements