02/13/2023 Construction Update
Work Completed for Week ending 02/10/2023
- Park Street (Kincaid to Alder)
- Continue transferring water services.
- Continue grading for concrete sidewalks and ADA ramps.
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station
- Continue installing storm drainage
- Cherry Avenue (Maple to Main)
- Begin demolition
Work in progress this week (2/13/2023 - 2/17/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Begin potholing for water.
- Academy Street (Alder to Park)
- Continue Water Main installation.
- Kincaid Avenue and Park Street Intersection
- Continue concrete sidewalks and ADA ramps
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
Upcoming Work through (03/03/2023)
- Alder Avenue (Park to Academy)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Kincaid Avenue (Park to Maple)
- Curb Patches
- Water Testing
- Cherry Avenue (Maple to Main)
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- PSE setting new poles and transferring services to new poles.
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.