1/23/2023 Construction Update
Work Completed for Week ending 01/20/2023
- Kincaid Avenue (Maple to Main)
- Complete pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements
- Intersection of Kincaid Avenue and Academy Street
- Begin grading for concrete curbs and sidewalk
- Alder Avenue (Park to Academy)
- Continue water main installation
- Alder Avenue (Academy to Maple)
- Begin water main installation
Work in progress this week (1/23/2023 - 1/27/2023)
- Park Street (Kincaid to Alder)
- Continue water service transfers
- Complete HMA
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete HMA
- Kincaid Avenue (Park to Academy)
- Complete water service transfers
- Complete HMA
- Kincaid Avenue (Academy to Maple)
- Complete water service transfers
- Complete HMA
- Kincaid Avenue (Maple to Main)
- Complete ADA strip concrete
- Complete sewer CIPP
- Alder Avenue (Park to Maple
- Begin installation of water services, hydrants, and sample station
- Alder Avenue (Maple to Main)
- Complete sewer CIPP
- Cherry Avenue (Maple to Main)
- Complete sewer CIPP
- Complete tree removal
Upcoming Work through (02/10/2023)
- Cherry Avenue (Maple to Main)
- Set up traffic control
- Complete clear and grub
- Begin demolition
- Begin storm drainage installation
- Alder Avenue (Academy to Park)
- Complete water main installation
- Complete water services and hydrants
- Complete water testing