02/06/2023 Construction Update

Work Completed for Week ending 02/03/2023

  • Park Street (Kincaid to Alder)
    • Continue transferring water services.
    • Continue grading for concrete sidewalks and ADA ramps.
  • Alder Avenue (Park to Maple)
    • Continue installing water services, hydrants, and sample station
    • Continue installing storm drainage
  • Cherry Avenue (Maple to Main)
    • Begin demolition.


Cherry Ave (Maple to Main Street) - Beginning Demolition


02/01/2023 Cherry Ave (Maple to Main Street) - Beginning Demolition




02/01/2023 Park Street (Kincaid to Alder) - Water Service Transfers

Work in progress this week (2/06/2023 - 2/10/2023)

  • Cherry Avenue (Maple to Main)
    • Continue Storm Drainage Installation
    • Begin potholing for water.
  • Academy Street (Alder to Park)
    • Begin Water Main installation.
  • Kincaid Avenue and Park Street Intersection
    • Begin concrete sidewalks and ADA ramps

Upcoming Work through (02/24/2023)

  • Alder Avenue (Park to Academy)
    • Complete water main installation
    • Complete water services and hydrant
    • Complete water testing
  • Kincaid Avenue (Park to Maple)
    • Curb Patches
    • Water Testing
  • Cherry Avenue (Maple to Main)
    • Complete joint utility trench
    • Complete water tie-in at Maple St
    • Begin Illumination
    • PSE setting new poles and transferring services to new poles.
  • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
    • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
    • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
    • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.