1/30/2023 Construction Update
Work Completed for Week ending 01/27/2023
- Kincaid Avenue (Maple to Main)
- Complete pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street.
- Continue storm drainage improvements.
- Intersection of Kincaid Avenue and Academy Street
- Continue grading for concrete curbs and sidewalk.
- Alder Avenue (Park to Academy)
- Continue water main installation.
- Alder Avenue (Academy to Maple)
- Begin water main installation.
Work in progress this week (1/30/2023 - 2/03/2023)
- Park Street (Kincaid to Alder)
- Continue water service transfers.
- Continue grade for concrete.
- Alder Avenue (Park to Maple)
- Continue installation of water services, hydrants, and sample station
- Continue Storm drainage installation.
- Cherry Avenue (Maple to Main)
- Set up traffic control.
- Complete clear and grub
- Begin demolition.
- Begin storm drainage installation.
Upcoming Work through (02/17/2023)
- Alder Avenue (Academy to Park)
- Complete water main installation
- Complete water services and hydrants
- Complete water testing