1/30/2023 Construction Update

Work Completed for Week ending 01/27/2023

  • Kincaid Avenue (Maple to Main)
    • Complete pouring concrete pavement
  • Intersection of Kincaid Avenue and Park Street.
    • Continue storm drainage improvements.
  • Intersection of Kincaid Avenue and Academy Street
    • Continue grading for concrete curbs and sidewalk.
  • Alder Avenue (Park to Academy)
    • Continue water main installation.
  • Alder Avenue (Academy to Maple)
    • Begin water main installation.

01/25/2023 - Intersection of Kincaid Avenue and Academy Street - Continue concrete curbs and sidewalk

01/26/2023 - Kincaid Avenue (Maple to Main) - Complete pouring concrete pavement


Work in progress this week (1/30/2023 - 2/03/2023)

  • Park Street (Kincaid to Alder)
    • Continue water service transfers.
    • Continue grade for concrete.
  • Alder Avenue (Park to Maple)
    • Continue installation of water services, hydrants, and sample station
    • Continue Storm drainage installation.
  • Cherry Avenue (Maple to Main)
    • Set up traffic control.
    • Complete clear and grub
    • Begin demolition.
    • Begin storm drainage installation.

Upcoming Work through (02/17/2023)

  • Alder Avenue (Academy to Park)
    • Complete water main installation
    • Complete water services and hydrants
    • Complete water testing