Town Center: Utility & Woonerf Project

Cherry Avenue and Kincaid Avenue Woonerfs surrounding Reuben A. Knoblauch Heritage Park

The City of Sumner adopted the Town Center Plan in 2018 allowing for redevelopment of properties in and adjacent to the historical Sumner downtown corridor. To provide public services in accordance with that plan the City seeks to upgrade road, sidewalk, storm drainage, sanitary sewer, and domestic water facilities within and adjacent to Alder Avenue and Kincaid Avenue between Main Street and Park Street.

In addition, the City of Sumner has secured grant funding for the delineation of a bike route between the Sumner Sound Transit Station and Wood Avenue. The project will involve the reconstruction of curbs, sidewalks, signage, street striping, and utilities to accommodate the bike lanes.

In 2021, the City of Sumner adopted the Main Street Visioning Plan. This plan captured the community's vision that eventally led to the inclusion of the woonerfs around Heritage Park (Cherry Avenue and Kincaid Avenue between Main St and Maple Street) in this project.

Project extents are shown below:


The City of Sumner adopted the Town Center Plan in 2018 allowing for redevelopment of properties in and adjacent to the historical Sumner downtown corridor. To provide public services in accordance with that plan the City seeks to upgrade road, sidewalk, storm drainage, sanitary sewer, and domestic water facilities within and adjacent to Alder Avenue and Kincaid Avenue between Main Street and Park Street.

In addition, the City of Sumner has secured grant funding for the delineation of a bike route between the Sumner Sound Transit Station and Wood Avenue. The project will involve the reconstruction of curbs, sidewalks, signage, street striping, and utilities to accommodate the bike lanes.

In 2021, the City of Sumner adopted the Main Street Visioning Plan. This plan captured the community's vision that eventally led to the inclusion of the woonerfs around Heritage Park (Cherry Avenue and Kincaid Avenue between Main St and Maple Street) in this project.

Project extents are shown below:


  • 02/13/2023 Construction Update

    Work Completed for Week ending 02/10/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue grading for concrete sidewalks and ADA ramps.
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
      • Continue installing storm drainage
    • Cherry Avenue (Maple to Main)
      • Begin demolition

    02/07/2023 - Installing meter and setter boxes along Kincaid.

    2/10/2023 - Demolition on Cherry Ave (Maple to Main)



    Work in progress this week (2/13/2023 - 2/17/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Begin potholing for water.
    • Academy Street (Alder to Park)
      • Continue Water Main installation.
    • Kincaid Avenue and Park Street Intersection
      • Continue concrete sidewalks and ADA ramps
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.

    Upcoming Work through (03/03/2023)

    • Alder Avenue (Park to Academy)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
    • Kincaid Avenue (Park to Maple)
      • Curb Patches
      • Water Testing
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • PSE setting new poles and transferring services to new poles.
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • 02/06/2023 Construction Update

    Work Completed for Week ending 02/03/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue grading for concrete sidewalks and ADA ramps.
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
      • Continue installing storm drainage
    • Cherry Avenue (Maple to Main)
      • Begin demolition.


    Cherry Ave (Maple to Main Street) - Beginning Demolition


    02/01/2023 Cherry Ave (Maple to Main Street) - Beginning Demolition




    02/01/2023 Park Street (Kincaid to Alder) - Water Service Transfers

    Work in progress this week (2/06/2023 - 2/10/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Begin potholing for water.
    • Academy Street (Alder to Park)
      • Begin Water Main installation.
    • Kincaid Avenue and Park Street Intersection
      • Begin concrete sidewalks and ADA ramps

    Upcoming Work through (02/24/2023)

    • Alder Avenue (Park to Academy)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
    • Kincaid Avenue (Park to Maple)
      • Curb Patches
      • Water Testing
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • PSE setting new poles and transferring services to new poles.
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
      • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • 1/30/2023 Construction Update

    Work Completed for Week ending 01/27/2023

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street.
      • Continue storm drainage improvements.
    • Intersection of Kincaid Avenue and Academy Street
      • Continue grading for concrete curbs and sidewalk.
    • Alder Avenue (Park to Academy)
      • Continue water main installation.
    • Alder Avenue (Academy to Maple)
      • Begin water main installation.

    01/25/2023 - Intersection of Kincaid Avenue and Academy Street - Continue concrete curbs and sidewalk

    01/26/2023 - Kincaid Avenue (Maple to Main) - Complete pouring concrete pavement


    Work in progress this week (1/30/2023 - 2/03/2023)

    • Park Street (Kincaid to Alder)
      • Continue water service transfers.
      • Continue grade for concrete.
    • Alder Avenue (Park to Maple)
      • Continue installation of water services, hydrants, and sample station
      • Continue Storm drainage installation.
    • Cherry Avenue (Maple to Main)
      • Set up traffic control.
      • Complete clear and grub
      • Begin demolition.
      • Begin storm drainage installation.

    Upcoming Work through (02/17/2023)

    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
  • 1/23/2023 Construction Update

    Work Completed for Week ending 01/20/2023

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Intersection of Kincaid Avenue and Academy Street
      • Begin grading for concrete curbs and sidewalk
    • Alder Avenue (Park to Academy)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    01/17/2023 - Alder Avenue (Academy to Maple) - Water main installation

    01/17/2023 - Kincaid Avenue (Maple to Main) - Complete pouring concrete pavement
    1/17/2023 - Intersection of Kincaid Avenue and Academy Street - Begin concrete curbs and sidewalk


    Work in progress this week (1/23/2023 - 1/27/2023)

    • Park Street (Kincaid to Alder)
      • Continue water service transfers
      • Complete HMA
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Complete HMA
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
      • Complete HMA
    • Kincaid Avenue (Academy to Maple)
      • Complete water service transfers
      • Complete HMA
    • Kincaid Avenue (Maple to Main)
      • Complete ADA strip concrete
      • Complete sewer CIPP
    • Alder Avenue (Park to Maple
      • Begin installation of water services, hydrants, and sample station
    • Alder Avenue (Maple to Main)
      • Complete sewer CIPP
    • Cherry Avenue (Maple to Main)
      • Complete sewer CIPP
      • Complete tree removal

    Upcoming Work through (02/10/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
  • 1/17/2023 Construction Update

    Work Completed for Week ending 01/13/2023

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Continue water main installation on Alder Avenue (Academy to Park)
    • Continue water main installation

    Work in progress this week (1/16/2023 - 1/20/2023)

    • Kincaid Avenue (Academy to Kincaid)
      • Complete water service transfers
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
    • Park Street (Kincaid to Alder)
      • Complete water service transfers
    • Alder Avenue (Academy to Park)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    Upcoming Work through (02/03/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Begin grading for concrete curbs and sidewalk
    • Prepping for HMA (Maple to Main)
  • 1/09/2023 Construction Update

    Work Completed for Week ending 01/06/2023

    • Kincaid Avenue (Maple to Main)
      • Completed grading for concrete pavement
      • Continued pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continued storm drainage improvements
    • Alder Avenue (Academy to Park)
    • Begin water main installation
    • 1/06/2023 - Kincaid Avenue Maple to Main Street Concrete Pavement1/06/2023 - Intersection of Kincaid Avenue and Park Street storm drain improvements

    1/06/2023 - Alder Avenue Academy to Park Water Main Installation

    Work in progress this week (1/09/2023 - 1/13/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Kincaid Avenue (Academy to Kincaid)
      • Complete water service transfers
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
    • Park Street (Kincaid to Alder)
      • Complete water service transfers
    • Alder Avenue (Academy to Park)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    Upcoming Work through (1/27/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Begin grading for concrete curbs and sidewalks
  • 1/3/2022 Construction Update

    Work Completed for Week ending 12/30/2022

    • No Construction Due to Holiday

    Work in progress this week (1/03/2023 - 1/06/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Alder Avenue (Academy to Park)
      • Begin water main installation

    Upcoming Work through (1/20/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation


  • 12/26/2022 Construction Update

    Work Completed for Week ending 12/23/22

    • Intersection of Kincaid Avenue and Park Street
      • Continue excavation of intersection
      • Begin water service transfers
      • Water tie in on Kincaid south of Park
      • Begin storm drainage improvements
    • Kincaid Avenue (Maple to Main)
      • Continue pouring concrete curbs and sidewalk
      • Continue grading for concrete pavement
      • Continue pouring concrete pavement

    12/19/2022 Pouring Concrete Sidewalk North End of Kincaid Avenue

    12/19/2022 Excavation of Intersection at Kincaid Avenue and Park Street

    12/20/2022 Water Tie In On Kincaid Avenue South of Park Street

    Work in progress this week (12/26/2022 - 12/30/2022)

    • Week of 12/25 - 12/30 No construction due to Holiday

    Upcoming Work through (1/13/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
  • 12/19/22 Construction Update

    Work Completed for Week ending 12/16/22

    • Kincaid Avenue (Maple to Main)
      • Pouring concrete curbs and sidewalk
    • Intersection of Kincaid Avenue and Park Street
      • Excavation of intersection

    12/12/2022 Excavation of intersection at Kincaid Avenue and Park Street

    12/13/2022 Pouring parking strip on North end of Kincaid Avenue

    12/13/2022 Stamping concrete parking strip on North end of Kincaid Avenue

    Work in progress this week (12/19/2022 - 12/23/2022)

    • Intersection of Kincaid Avenue and Park Street
      • Begin water service transfers
      • Water tie in on Kincaid south of Park
      • Begin storm drainage improvements
    • Kincaid Avenue (Maple to Main)
      • Continue grading for concrete pavement
      • Continue pouring concrete pavement

    Upcoming Work through (1/6/2023)

    • Week of 12/25 - 12/30 No construction due to Holiday
    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
  • 12/12/22 Construction Update

    Work completed for Week Ending 12/09/2022:

    • Kincaid Avenue (Maple to Main)
      • Continue pouring concrete curbs and sidewalk
    • Intersection of Kincaid Avenue and Park Street
      • Complete excavation of intersection.

    12/06/22: Finishing concrete sidewalk on the east side of Kincaid Avenue north of Maple Street. 12/07/22: Spreading geotextile fabric over the roadway subgrade at the intersection of Kincaid Avenue and Park Street. 12/08/22: Concrete formwork for driveway on the east side of Kincaid Avenue north of Maple Street 12/09/22: Finishing concrete driveway on east side of Kincaid Avenue north of Maple Street.

    Work in progress this week (12/12/2022 - 12/16/2022):

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete curbs and sidewalk
      • Complete grading for concrete
      • Start pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete intersection grading
      • Begin storm drainage improvements

    Upcoming Work through 12/30/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
    • Alder Avenue (Academy to Maple)
      • Begin water main installation