11/14/22 Construction Update
Work completed for Week Ending 11/11/2022:
- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Maple Street
- Complete water main connections.
Work in progress this week (11/14/2022 - 11/18/2022):
- Kincaid Avenue (Maple to Main)
- Complete demolition of sidewalks
- Complete grading for concrete
- Pour curbs and sidewalks
Upcoming Work through 12/02/2022:
- Kincaid Avenue (Maple to Main):
- Pour flush curbs
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Complete roadway excavation for intersection paving
- Kincaid Avenue (Maple to Main)
-
11/07/22 Construction Update
Work completed for Week Ending 11/04/2022:
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Kincaid Avenue (Maple to Main)
- Complete illumination system.
- Complete irrigation system
- Complete trench restoration
Upcoming Work through 11/25/2022:
- Kincaid Avenue (Maple to Main):
- Complete installation of curbs
- Complete sidewalks (currently projected 11/21-11/23, but this may change)
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
- Intersection of Kincaid Avenue and Academy Street
-
10/31/22 Construction Update
Work completed for Week Ending 10/28/2022:
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
- Academy Street (Kincaid to Alder)
- Water Testing
Install rebar over watermain trenches and prepare for concrete pours.
- Kincaid Avenue (Maple to Main)
- Begin illumination system.
- Intersection of Kincaid Avenue and Academy Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
Upcoming Work through 11/18/2022:
- Kincaid Avenue (Maple to Main):
- Complete irrigation system.
- Begin installation of curbs
- Intersection of Kincaid Avenue and Academy Street
- Complete grading of intersection
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
- Kincaid Avenue (Maple to Main)
-
10/24/22 Construction Update
Work completed for Week Ending 10/21/2022:
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
- Academy Street (Kincaid to Alder)
- Water Testing
- Install rebar over watermain trenches and prepare for concrete pours.
Work in progress this week (10/24/2022 - 10/28/2022):
- Kincaid Avenue (Academy to Maple)
- Pour concrete over watermain trenches.
- Place asphalt over watermain trenches.
- Kincaid Avenue (Park to Academy)
- Water Testing
- Kincaid Avenue (south of Park)
- Water Testing
- Academy Street (Kincaid to Alder)
- Pour concrete over watermain trenches.
- Place asphalt over watermain trenches.
- Park Street (Kincaid to Alder)
- Water Testing
Upcoming Work through 11/11/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Kincaid Avenue/Academy Street Intersection
- Demolition for storm drainage installation.
- Install storm drainage pipes and structures.
- Grade for concrete placement.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Park Street (Kincaid to Alder)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (Maple to Main)
-
10/17/22 Construction Update
Work completed for Week Ending 10/14/2022:
- Kincaid (Academy to Maple)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (Park to Academy)
- Complete water service connection crossings (still need to connect to make connections)
- Kincaid Avenue (south of Park to tie-in)
- Complete water service connection crossings (still need to connect to make connections)
- Park Street (Kincaid to Alder)
- Complete water service connection crossings (still need to connect to make connections)
Work in progress this week (10/17/2022 - 10/21/2022):
- Kincaid Avenue (Maple to Main)
- Water Testing
- Complete subgrade preparation and place/compact gravel
- Kincaid Avenue (Academy to Maple)
- Water Testing
- Academy Street (Kincaid to Alder)
- Water Testing
Upcoming Work through 11/04/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue/Academy Street Intersection
- Demolition for storm drainage installation.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections.
- Water Testing
- Pour concrete and place asphalt over waterline trenches.
- Academy Street (Kincaid to Alder)
- Continue water service connections.
- Park Street (Kincaid to Alder)
- Continue water service connections.
- Kincaid (Academy to Maple)
-
10/10/22 Construction Update
There was a recent question about this project on the Rumors & Questions page. Click here to see the question and response.
Work completed for Week Ending 10/07/2022:
- Kincaid Avenue (south of Park to tie-in)
- Complete waterline installation (still need to complete water service connections)
- Park Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (10/10/2022 - 10/14/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin water service connection installation
Upcoming Work through 10/28/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Begin testing watermain.
- Complete roadway subgrade.
- Kincaid Avenue (Academy to Maple):
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Begin testing watermain.
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Begin testing watermain.
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Begin testing watermain.
- Continue water service connections
- Park Street (Kincaid to Alder)
- Begin testing watermain.
- Continue waterline and water service connection installation
- Kincaid Avenue (south of Park to tie-in)
-
10/03/22 Construction Update
Work completed for Week Ending 09/30/2022:
- Academy Street (Kincaid to Alder)
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (10/03/2022 - 10/07/2022):
- Kincaid Avenue (Maple to Main)
- Continue water service connections
- Kincaid Avenue (Academy to Maple)
- Continue water service connections
- Kincaid Avenue (Park to Academy)
- Continue water service connections
- Kincaid Avenue (south of Park to tie-in)
- Begin waterline and water service connection installation
- Academy Street (Kincaid to Alder)
- Begin water service connections
- Complete Installing dowels for concrete panels
- Park Street (Kincaid to Alder)
- Begin waterline and water service connection installation
Upcoming Work through 10/21/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue water service connections.
- Kincaid Avenue (Park to Academy)
- Continue water service connections.
- Kincaid Avenue (south of Park to tie-in)
- Continue water service connections
- Academy Street (Kincaid to Alder)
- Continue water service connections
- Park Street (Kincaid to Alder)
- Continue waterline and water service connection installation
- Academy Street (Kincaid to Alder)
-
09/26/22 Construction Update
Work completed for Week Ending 09/23/2022:
- Kincaid Avenue (Maple to Main)
- Complete demolition
- Kincaid Avenue (Park to Academy):
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (09/26/2022 - 09/30/2022):
- Academy Street (Kincaid to Alder)
- Begin waterline and water service connection installation
- Park Street (Kincaid to Alder)
- Begin waterline and water service connection installation
Upcoming Work through 10/14/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Begin water service connections.
- Kincaid Avenue (Park to Academy)
- Begin water service connections.
- Kincaid Avenue (Maple to Main)
-
09/19/22 Construction Update
Work completed for Week Ending 09/16/2022:
- Kincaid Avenue (Maple to Main)
- Complete demolition
- Complete JUT installation
- Kincaid Avenue (Academy to Maple):
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (09/19/2022 - 09/23/2022):
- Kincaid Avenue (Park to Academy):
- Continue waterline installation (still need to complete water service connections)
Upcoming Work through 10/07/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Complete water service connections.
- Kincaid Avenue (Park to Academy)
- Continue water service connection installation.
- Academy Street (Kincaid to Alder)
- Begin waterline and water service connection installation
- Park Street (Kincaid to Alder)
- Begin waterline and water service connection installation
- Kincaid Avenue (Maple to Main)
-
09/12/22 Construction Update
Work completed for Week Ending 09/09/2022:
- Kincaid Avenue (Maple to Main):
- Complete installation of fiber optic trench
- Kincaid Avenue and Maple Street intersection:
- Complete waterline installation at intersection
Work in progress this week (09/12/2022 - 09/16/2022):
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.
Upcoming Work through 09/30/2022:
- Kincaid Avenue (Maple to Main):
- Complete JUT installation
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.
- Kincaid Avenue (Park to Academy)
- Begin waterline installation.
- Kincaid Avenue (Maple to Main):