Category Construction Update   Show all

  • 11/14/22 Construction Update

    Work completed for Week Ending 11/11/2022:

    • Kincaid Avenue (Maple to Main)
      • Complete illumination system.
      • Complete irrigation system
    • Maple Street
      • Complete water main connections.

    11/09/22: Pounding rebar into existing concrete roadway over water service connection trenches.

    11/10/22: Completed water main connections on Maple Street on either side of Kincaid Avenue.

    Work in progress this week (11/14/2022 - 11/18/2022):

    • Kincaid Avenue (Maple to Main)
      • Complete demolition of sidewalks
      • Complete grading for concrete
      • Pour curbs and sidewalks

    Upcoming Work through 12/02/2022:

    • Kincaid Avenue (Maple to Main):
      • Pour flush curbs
      • Pour concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete demolition of sidewalks
      • Complete storm drainage improvements
      • Complete roadway excavation for intersection paving
  • 11/07/22 Construction Update

    Work completed for Week Ending 11/04/2022:

    • Intersection of Kincaid Avenue and Academy Street
      • Complete demolition of sidewalks
      • Complete storm drainage improvements

    11/01/22: Demolition on Kincaid Avenue north of Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings. 11/03/22: Excavation on the NW corner of Kincaid Avenue and Academy Street for the reconstruction of this intersection to create ADA-accessible curb ramps and crossings. 11/03/22: Laying geotextile fabric on the subgrade to support the roadway structure on the NW corner of Kincaid Avenue and Academy Street.

    11/03/22: Rolling to compact on the NW corner of Kincaid Avenue and Academy Street.

    Work in progress this week (11/07/2022 - 11/11/2022):

    • Kincaid Avenue (Maple to Main)
      • Complete illumination system.
      • Complete irrigation system
      • Complete trench restoration

    Upcoming Work through 11/25/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete installation of curbs
      • Complete sidewalks (currently projected 11/21-11/23, but this may change)
    • Intersection of Kincaid Avenue and Park Street
      • Complete demolition of sidewalks
      • Begin storm drainage improvements
  • 10/31/22 Construction Update

    Work completed for Week Ending 10/28/2022:

    • Kincaid Avenue (Maple to Main)
      • Water Testing
      • Complete subgrade preparation and place/compact gravel
    • Kincaid Avenue (Academy to Maple)
      • Water Testing
      • Install rebar over watermain trenches and prepare for concrete pours.
    • Academy Street (Kincaid to Alder)
      • Water Testing
      • Install rebar over watermain trenches and prepare for concrete pours.

    10/24/22: Pouring concrete on watermain trench on Academy Street between Kincaid Avenue and Alder Avenue10/25/22: Grading the exit from the parking area east of Kincaid Avenue in preparation for temporary re-opening 10/26/22: Exit from the parking area east of Kincaid Avenue prepared for temporary re-opening 10/27/22: Kincaid Avenue temporarily re-opened north of Maple Street

    Work in progress this week (10/31/2022 - 11/04/2022):

    • Kincaid Avenue (Maple to Main)
      • Begin illumination system.
    • Intersection of Kincaid Avenue and Academy Street
      • Complete demolition of sidewalks
      • Complete storm drainage improvements

    Upcoming Work through 11/18/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete irrigation system.
      • Begin installation of curbs
    • Intersection of Kincaid Avenue and Academy Street
      • Complete grading of intersection
    • Intersection of Kincaid Avenue and Park Street
      • Complete demolition of sidewalks
      • Begin storm drainage improvements
  • 10/24/22 Construction Update

    Work completed for Week Ending 10/21/2022:

    • Kincaid Avenue (Maple to Main)
      • Water Testing
      • Complete subgrade preparation and place/compact gravel
    • Kincaid Avenue (Academy to Maple)
      • Water Testing
      • Install rebar over watermain trenches and prepare for concrete pours.
    • Academy Street (Kincaid to Alder)
      • Water Testing
      • Install rebar over watermain trenches and prepare for concrete pours.

    10/17/22: Grading on Kincaid Avenue south of Main Street. 10/18/22: Grading on Kincaid Avenue north of Maple Street 10/19/22: Place rock on Kincaid Avenue between Main Street and Maple Street 10/20/22: Compacting rock on Kincaid Avenue south of Main Street 10/21/22: Placing temporary asphalt on Kincaid Avenue south of Maple Street

    Work in progress this week (10/24/2022 - 10/28/2022):

    • Kincaid Avenue (Academy to Maple)
      • Pour concrete over watermain trenches.
      • Place asphalt over watermain trenches.
    • Kincaid Avenue (Park to Academy)
      • Water Testing
    • Kincaid Avenue (south of Park)
      • Water Testing
    • Academy Street (Kincaid to Alder)
      • Pour concrete over watermain trenches.
      • Place asphalt over watermain trenches.
    • Park Street (Kincaid to Alder)
      • Water Testing

    Upcoming Work through 11/11/2022:

    • Kincaid Avenue (Maple to Main):
      • Begin illumination system.
      • Begin irrigation system.
    • Kincaid Avenue (Academy to Maple):
      • Continue water service connections.
    • Kincaid Avenue/Academy Street Intersection
      • Demolition for storm drainage installation.
      • Install storm drainage pipes and structures.
      • Grade for concrete placement.
    • Kincaid Avenue (Park to Academy)
      • Continue water service connections.
      • Water Testing
      • Pour concrete and place asphalt over waterline trenches.
    • Kincaid Avenue (south of Park to tie-in)
      • Continue water service connections.
      • Water Testing
      • Pour concrete and place asphalt over waterline trenches.
    • Park Street (Kincaid to Alder)
      • Continue water service connections.
      • Water Testing
      • Pour concrete and place asphalt over waterline trenches.


  • 10/17/22 Construction Update

    Work completed for Week Ending 10/14/2022:

    • Kincaid (Academy to Maple)
      • Complete water service connection crossings (still need to connect to make connections)
    • Kincaid Avenue (Park to Academy)
      • Complete water service connection crossings (still need to connect to make connections)
    • Kincaid Avenue (south of Park to tie-in)
      • Complete water service connection crossings (still need to connect to make connections)
    • Park Street (Kincaid to Alder)
      • Complete water service connection crossings (still need to connect to make connections)

    10/10/22: Sawcutting for water service connections on Park Street between Kincaid Avenue and Alder Avenue 10/11/22: Removing asphalt for water service connections on Kincaid Avenue between Maple Street and Academy Street

    10/12/22: Asphalt over Concrete pavement removed for water service connections on Kincaid Avenue between Academy Street and Park Street.

    10/13/22: Compacting after water service connection crossing on Park Street east of Kincaid Avenue.

    Work in progress this week (10/17/2022 - 10/21/2022):

    • Kincaid Avenue (Maple to Main)
      • Water Testing
      • Complete subgrade preparation and place/compact gravel
    • Kincaid Avenue (Academy to Maple)
      • Water Testing
    • Academy Street (Kincaid to Alder)
      • Water Testing

    Upcoming Work through 11/04/2022:

    • Kincaid Avenue (Maple to Main):
      • Begin illumination system.
      • Begin irrigation system.
    • Kincaid Avenue (Academy to Maple):
      • Continue water service connections.
      • Pour concrete and place asphalt over waterline trenches.
    • Kincaid Avenue/Academy Street Intersection
      • Demolition for storm drainage installation.
    • Kincaid Avenue (Park to Academy)
      • Continue water service connections.
      • Water Testing
      • Pour concrete and place asphalt over waterline trenches.
    • Kincaid Avenue (south of Park to tie-in)
      • Continue water service connections.
      • Water Testing
      • Pour concrete and place asphalt over waterline trenches.
    • Academy Street (Kincaid to Alder)
      • Continue water service connections.
    • Park Street (Kincaid to Alder)
      • Continue water service connections.
  • 10/10/22 Construction Update

    There was a recent question about this project on the Rumors & Questions page. Click here to see the question and response.

    Work completed for Week Ending 10/07/2022:

    • Kincaid Avenue (south of Park to tie-in)
      • Complete waterline installation (still need to complete water service connections)
    • Park Street (Kincaid to Alder)
      • Complete waterline installation (still need to complete water service connections)

    10/03/22: Removing asphalt for water service connections on Kincaid Avenue between Park Street and Academy Street. 10/04/22: Compacting the backfill on the waterline trench on the NW corner of Kincaid Avenue and Park Street. 10/06/22: Excavating for watermain installation on Park Street west of Alder Avenue.

    Work in progress this week (10/10/2022 - 10/14/2022):

    • Kincaid Avenue (Maple to Main)
      • Continue water service connections
    • Kincaid Avenue (Academy to Maple)
      • Continue water service connections
    • Kincaid Avenue (Park to Academy)
      • Continue water service connections
    • Kincaid Avenue (south of Park to tie-in)
      • Begin water service connection installation
    • Academy Street (Kincaid to Alder)
      • Begin water service connections
      • Complete Installing dowels for concrete panels
    • Park Street (Kincaid to Alder)
      • Begin water service connection installation

    Upcoming Work through 10/28/2022:

    • Kincaid Avenue (Maple to Main):
      • Begin illumination system.
      • Begin irrigation system.
      • Begin testing watermain.
      • Complete roadway subgrade.
    • Kincaid Avenue (Academy to Maple):
      • Begin testing watermain.
      • Continue water service connections.
    • Kincaid Avenue (Park to Academy)
      • Begin testing watermain.
      • Continue water service connections.
    • Kincaid Avenue (south of Park to tie-in)
      • Begin testing watermain.
      • Continue water service connections
    • Academy Street (Kincaid to Alder)
      • Begin testing watermain.
      • Continue water service connections
    • Park Street (Kincaid to Alder)
      • Begin testing watermain.
      • Continue waterline and water service connection installation
  • 10/03/22 Construction Update

    Work completed for Week Ending 09/30/2022:

    • Academy Street (Kincaid to Alder)
      • Complete waterline installation (still need to complete water service connections)

    Looking south from Main Street towards Heritage Park

    09/26/2022: Installing waterline on Academy Street between Kincaid Avenue and Alder Avenue. 09/27/2022: Continuing excavation for waterline installation on Academy Street between Kincaid Avenue and Alder Avenue. 09/28/2022: Installing water service connection to 902 Kincaid Avenue.

    09/29/2022: Compacting water service connection crossings on Kincaid Avenue between Academy Street and Maple Street.

    Work in progress this week (10/03/2022 - 10/07/2022):

    • Kincaid Avenue (Maple to Main)
      • Continue water service connections
    • Kincaid Avenue (Academy to Maple)
      • Continue water service connections
    • Kincaid Avenue (Park to Academy)
      • Continue water service connections
    • Kincaid Avenue (south of Park to tie-in)
      • Begin waterline and water service connection installation
    • Academy Street (Kincaid to Alder)
      • Begin water service connections
      • Complete Installing dowels for concrete panels
    • Park Street (Kincaid to Alder)
      • Begin waterline and water service connection installation

    Upcoming Work through 10/21/2022:

    • Kincaid Avenue (Maple to Main):
      • Begin illumination system.
      • Begin irrigation system.
    • Kincaid Avenue (Academy to Maple):
      • Continue water service connections.
    • Kincaid Avenue (Park to Academy)
      • Continue water service connections.
    • Kincaid Avenue (south of Park to tie-in)
      • Continue water service connections
    • Academy Street (Kincaid to Alder)
      • Continue water service connections
    • Park Street (Kincaid to Alder)
      • Continue waterline and water service connection installation
  • 09/26/22 Construction Update

    Work completed for Week Ending 09/23/2022:

    • Kincaid Avenue (Maple to Main)
      • Complete demolition
    • Kincaid Avenue (Park to Academy):
      • Complete waterline installation (still need to complete water service connections)

    09/19/22: Kincaid Avenue waterline trench looking north towards Academy Street 09/20/22: Contractor installing a trench box for waterline installation on Kincaid Avenue. 09/21/22: Contractor installing new fire hydrant on east side of Kincaid Avenue across from 816 Kincaid Avenue. 09/22/22: Completion of demolition at the north end of Kincaid Avenue near the intersection with Main Street.

    Work in progress this week (09/26/2022 - 09/30/2022):

    • Academy Street (Kincaid to Alder)
      • Begin waterline and water service connection installation
    • Park Street (Kincaid to Alder)
      • Begin waterline and water service connection installation

    Upcoming Work through 10/14/2022:

    • Kincaid Avenue (Maple to Main):
      • Begin illumination system.
      • Begin irrigation system.
    • Kincaid Avenue (Academy to Maple):
      • Begin water service connections.
    • Kincaid Avenue (Park to Academy)
      • Begin water service connections.
  • 09/19/22 Construction Update

    Work completed for Week Ending 09/16/2022:

    • Kincaid Avenue (Maple to Main)
      • Complete demolition
      • Complete JUT installation
    • Kincaid Avenue (Academy to Maple):
      • Complete waterline installation (still need to complete water service connections)

    09/12/22: Demolition of Fountain 09/12/22: Demolition of Fountain09/13/22: Kincaid Avenue looking north towards Main Street 09/15/22: Excavation for waterline installation at the intersection of Kincaid Avenue and Academy Street looking south Work in progress this week (09/19/2022 - 09/23/2022):

    • Kincaid Avenue (Park to Academy):
      • Continue waterline installation (still need to complete water service connections)

    Upcoming Work through 10/07/2022:

    • Kincaid Avenue (Maple to Main):
      • Begin illumination system.
      • Begin irrigation system.
    • Kincaid Avenue (Academy to Maple):
      • Complete water service connections.
    • Kincaid Avenue (Park to Academy)
      • Continue water service connection installation.
    • Academy Street (Kincaid to Alder)
      • Begin waterline and water service connection installation
    • Park Street (Kincaid to Alder)
      • Begin waterline and water service connection installation
  • 09/12/22 Construction Update

    Work completed for Week Ending 09/09/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete installation of fiber optic trench
    • Kincaid Avenue and Maple Street intersection:
      • Complete waterline installation at intersection

    09/06/22: Excavating for waterline installation across the intersection of Maple Street and Kincaid Avenue 09/07/22: Trenching for waterline installation on Kincaid Avenue between Academy Street and Maple Street

    Work in progress this week (09/12/2022 - 09/16/2022):

    • Kincaid Avenue (Academy to Maple):
      • Continue waterline installation south of Maple Street.

    Upcoming Work through 09/30/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete JUT installation
      • Begin illumination system.
      • Begin irrigation system.
    • Kincaid Avenue (Academy to Maple):
      • Continue waterline installation south of Maple Street.
    • Kincaid Avenue (Park to Academy)
      • Begin waterline installation.