09/26/22 Construction Update

Work completed for Week Ending 09/23/2022:

  • Kincaid Avenue (Maple to Main)
    • Complete demolition
  • Kincaid Avenue (Park to Academy):
    • Complete waterline installation (still need to complete water service connections)

09/19/22: Kincaid Avenue waterline trench looking north towards Academy Street 09/20/22: Contractor installing a trench box for waterline installation on Kincaid Avenue. 09/21/22: Contractor installing new fire hydrant on east side of Kincaid Avenue across from 816 Kincaid Avenue. 09/22/22: Completion of demolition at the north end of Kincaid Avenue near the intersection with Main Street.

Work in progress this week (09/26/2022 - 09/30/2022):

  • Academy Street (Kincaid to Alder)
    • Begin waterline and water service connection installation
  • Park Street (Kincaid to Alder)
    • Begin waterline and water service connection installation

Upcoming Work through 10/14/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
  • Kincaid Avenue (Academy to Maple):
    • Begin water service connections.
  • Kincaid Avenue (Park to Academy)
    • Begin water service connections.