09/19/22 Construction Update
Work completed for Week Ending 09/16/2022:
- Kincaid Avenue (Maple to Main)
- Complete demolition
- Complete JUT installation
- Kincaid Avenue (Academy to Maple):
- Complete waterline installation (still need to complete water service connections)
Work in progress this week (09/19/2022 - 09/23/2022):
- Kincaid Avenue (Park to Academy):
- Continue waterline installation (still need to complete water service connections)
Upcoming Work through 10/07/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Complete water service connections.
- Kincaid Avenue (Park to Academy)
- Continue water service connection installation.
- Academy Street (Kincaid to Alder)
- Begin waterline and water service connection installation
- Park Street (Kincaid to Alder)
- Begin waterline and water service connection installation