09/19/22 Construction Update

Work completed for Week Ending 09/16/2022:

  • Kincaid Avenue (Maple to Main)
    • Complete demolition
    • Complete JUT installation
  • Kincaid Avenue (Academy to Maple):
    • Complete waterline installation (still need to complete water service connections)

09/12/22: Demolition of Fountain 09/12/22: Demolition of Fountain09/13/22: Kincaid Avenue looking north towards Main Street 09/15/22: Excavation for waterline installation at the intersection of Kincaid Avenue and Academy Street looking south Work in progress this week (09/19/2022 - 09/23/2022):

  • Kincaid Avenue (Park to Academy):
    • Continue waterline installation (still need to complete water service connections)

Upcoming Work through 10/07/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
  • Kincaid Avenue (Academy to Maple):
    • Complete water service connections.
  • Kincaid Avenue (Park to Academy)
    • Continue water service connection installation.
  • Academy Street (Kincaid to Alder)
    • Begin waterline and water service connection installation
  • Park Street (Kincaid to Alder)
    • Begin waterline and water service connection installation
Categories: Construction Update