Work completed for Week Ending 09/09/2022:
- Kincaid Avenue (Maple to Main):
- Complete installation of fiber optic trench
- Kincaid Avenue and Maple Street intersection:
- Complete waterline installation at intersection
Work in progress this week (09/12/2022 - 09/16/2022):
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.
Upcoming Work through 09/30/2022:
- Kincaid Avenue (Maple to Main):
- Complete JUT installation
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.
- Kincaid Avenue (Park to Academy)
- Begin waterline installation.