09/12/22 Construction Update

Work completed for Week Ending 09/09/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete installation of fiber optic trench
  • Kincaid Avenue and Maple Street intersection:
    • Complete waterline installation at intersection

09/06/22: Excavating for waterline installation across the intersection of Maple Street and Kincaid Avenue 09/07/22: Trenching for waterline installation on Kincaid Avenue between Academy Street and Maple Street

Work in progress this week (09/12/2022 - 09/16/2022):

  • Kincaid Avenue (Academy to Maple):
    • Continue waterline installation south of Maple Street.

Upcoming Work through 09/30/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete JUT installation
    • Begin illumination system.
    • Begin irrigation system.
  • Kincaid Avenue (Academy to Maple):
    • Continue waterline installation south of Maple Street.
  • Kincaid Avenue (Park to Academy)
    • Begin waterline installation.