Category Construction Update Show all
-
1/23/2023 Construction Update
Work Completed for Week ending 01/20/2023
- Kincaid Avenue (Maple to Main)
- Complete pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements
- Intersection of Kincaid Avenue and Academy Street
- Begin grading for concrete curbs and sidewalk
- Alder Avenue (Park to Academy)
- Continue water main installation
- Alder Avenue (Academy to Maple)
- Begin water main installation
Work in progress this week (1/23/2023 - 1/27/2023)
- Park Street (Kincaid to Alder)
- Continue water service transfers
- Complete HMA
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete HMA
- Kincaid Avenue (Park to Academy)
- Complete water service transfers
- Complete HMA
- Kincaid Avenue (Academy to Maple)
- Complete water service transfers
- Complete HMA
- Kincaid Avenue (Maple to Main)
- Complete ADA strip concrete
- Complete sewer CIPP
- Alder Avenue (Park to Maple
- Begin installation of water services, hydrants, and sample station
- Alder Avenue (Maple to Main)
- Complete sewer CIPP
- Cherry Avenue (Maple to Main)
- Complete sewer CIPP
- Complete tree removal
Upcoming Work through (02/10/2023)
- Cherry Avenue (Maple to Main)
- Set up traffic control
- Complete clear and grub
- Begin demolition
- Begin storm drainage installation
- Alder Avenue (Academy to Park)
- Complete water main installation
- Complete water services and hydrants
- Complete water testing
- Kincaid Avenue (Maple to Main)
-
1/17/2023 Construction Update
Work Completed for Week ending 01/13/2023
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete pavement
- Complete pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements
- Continue water main installation on Alder Avenue (Academy to Park)
- Continue water main installation
Work in progress this week (1/16/2023 - 1/20/2023)
- Kincaid Avenue (Academy to Kincaid)
- Complete water service transfers
- Kincaid Avenue (Park to Academy)
- Complete water service transfers
- Park Street (Kincaid to Alder)
- Complete water service transfers
- Alder Avenue (Academy to Park)
- Continue water main installation
- Alder Avenue (Academy to Maple)
- Begin water main installation
Upcoming Work through (02/03/2023)
- Cherry Avenue (Maple to Main)
- Set up traffic control
- Complete clear and grub
- Begin demolition
- Begin storm drainage installation
- Alder Avenue (Academy to Park)
- Complete water main installation
- Complete water services and hydrants
- Complete water testing
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Begin grading for concrete curbs and sidewalk
- Prepping for HMA (Maple to Main)
- Kincaid Avenue (Maple to Main)
-
1/09/2023 Construction Update
Work Completed for Week ending 01/06/2023
- Kincaid Avenue (Maple to Main)
- Completed grading for concrete pavement
- Continued pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street
- Continued storm drainage improvements
- Alder Avenue (Academy to Park)
- Begin water main installation
Work in progress this week (1/09/2023 - 1/13/2023)
- Kincaid Avenue (Maple to Main)
- Complete pouring concrete pavement
- Kincaid Avenue (Academy to Kincaid)
- Complete water service transfers
- Kincaid Avenue (Park to Academy)
- Complete water service transfers
- Park Street (Kincaid to Alder)
- Complete water service transfers
- Alder Avenue (Academy to Park)
- Continue water main installation
- Alder Avenue (Academy to Maple)
- Begin water main installation
Upcoming Work through (1/27/2023)
- Cherry Avenue (Maple to Main)
- Set up traffic control
- Complete clear and grub
- Begin demolition
- Begin storm drainage installation
- Alder Avenue (Academy to Park)
- Complete water main installation
- Complete water services and hydrants
- Complete water testing
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Begin grading for concrete curbs and sidewalks
- Kincaid Avenue (Maple to Main)
-
1/3/2022 Construction Update
Work Completed for Week ending 12/30/2022
- No Construction Due to Holiday
Work in progress this week (1/03/2023 - 1/06/2023)
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete pavement
- Complete pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements
- Alder Avenue (Academy to Park)
- Begin water main installation
Upcoming Work through (1/20/2023)
- Cherry Avenue (Maple to Main)
- Set up traffic control
- Complete clear and grub
- Begin demolition
- Begin storm drainage installation
- Alder Avenue (Academy to Park)
- Complete water main installation
-
12/26/2022 Construction Update
Work Completed for Week ending 12/23/22
- Intersection of Kincaid Avenue and Park Street
- Continue excavation of intersection
- Begin water service transfers
- Water tie in on Kincaid south of Park
- Begin storm drainage improvements
- Kincaid Avenue (Maple to Main)
- Continue pouring concrete curbs and sidewalk
- Continue grading for concrete pavement
- Continue pouring concrete pavement
12/19/2022 Pouring Concrete Sidewalk North End of Kincaid Avenue
12/19/2022 Excavation of Intersection at Kincaid Avenue and Park Street
12/20/2022 Water Tie In On Kincaid Avenue South of Park Street
Work in progress this week (12/26/2022 - 12/30/2022)
- Week of 12/25 - 12/30 No construction due to Holiday
Upcoming Work through (1/13/2023)
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete pavement
- Complete pouring concrete pavement
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements
- Intersection of Kincaid Avenue and Park Street
-
12/19/22 Construction Update
Work Completed for Week ending 12/16/22
- Kincaid Avenue (Maple to Main)
- Pouring concrete curbs and sidewalk
- Intersection of Kincaid Avenue and Park Street
- Excavation of intersection
12/12/2022 Excavation of intersection at Kincaid Avenue and Park Street
12/13/2022 Pouring parking strip on North end of Kincaid Avenue
12/13/2022 Stamping concrete parking strip on North end of Kincaid Avenue
Work in progress this week (12/19/2022 - 12/23/2022)
- Intersection of Kincaid Avenue and Park Street
- Begin water service transfers
- Water tie in on Kincaid south of Park
- Begin storm drainage improvements
- Kincaid Avenue (Maple to Main)
- Continue grading for concrete pavement
- Continue pouring concrete pavement
Upcoming Work through (1/6/2023)
- Week of 12/25 - 12/30 No construction due to Holiday
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete pavement
- Complete pouring concrete pavement
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Intersection of Kincaid Avenue and Park Street
- Continue storm drainage improvements
- Kincaid Avenue (Maple to Main)
-
12/12/22 Construction Update
Work completed for Week Ending 12/09/2022:
- Kincaid Avenue (Maple to Main)
- Continue pouring concrete curbs and sidewalk
- Intersection of Kincaid Avenue and Park Street
- Complete excavation of intersection.
Work in progress this week (12/12/2022 - 12/16/2022):
- Kincaid Avenue (Maple to Main)
- Complete pouring concrete curbs and sidewalk
- Complete grading for concrete
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete intersection grading
- Begin storm drainage improvements
Upcoming Work through 12/30/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Kincaid Avenue (Maple to Main)
-
12/05/22 Construction Update
Work completed for Week Ending 12/02/2022:
- Kincaid Avenue (Maple to Main)
- Continued pouring concrete curbs and sidewalk
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
Work in progress this week (12/05/2022 - 12/09/2022):
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete
- Complete pouring curbs and sidewalks
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition
- Begin storm drainage improvements
Upcoming Work through 12/23/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Kincaid Avenue (Academy to Maple)
- Begin pouring curbs
- Kincaid Avenue (Park to Academy)
- Begin pouring curbs
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete roadway excavation and grading for intersection paving
- Alder Avenue (Academy to Maple)
- Begin water main installation
- Kincaid Avenue (Maple to Main)
-
11/28/22 Construction Update
Work completed for Week Ending 11/25/2022:
- Kincaid Avenue (Maple to Main)
- Started pouring concrete curbs and sidewalk
Work in progress this week (11/28/2022 - 12/02/2022):
- Kincaid Avenue (Maple to Main)
- Complete grading for concrete
- Complete pouring curbs and sidewalks
- Start pouring concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Begin storm drainage improvements
Upcoming Work through 12/16/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring concrete roadway
- Kincaid Avenue (Academy to Maple)
- Begin pouring curbs and sidewalks
- Kincaid Avenue (Park to Academy)
- Begin pouring curbs and sidewalks
- Intersection of Kincaid Avenue and Park Street
- Complete storm drainage improvements
- Complete roadway excavation and grading for intersection paving
- Academy Street
- Begin water main installation
- Kincaid Avenue (Maple to Main)
-
11/21/22 Construction Update
Work completed for Week Ending 11/18/2022:
- Kincaid Avenue (Maple to Main)
- Completed sidewalk demolition and grading
- Completed pouring concrete curb
- Started pouring concrete sidewalk
- Kincaid Avenue (Park to Academy)
- Completed trench restoration
11/15/22: Checking subgrade elevation on Kincaid Avenue south of Main Street.Work in progress this week (11/21/2022 - 11/25/2022):
- Kincaid Avenue (Maple to Main)
- Continue pouring curbs and sidewalks
Upcoming Work through 12/09/2022:
- Kincaid Avenue (Maple to Main):
- Complete pouring curbs and sidewalks
- Pour concrete roadway
- Intersection of Kincaid Avenue and Park Street
- Complete demolition of sidewalks
- Complete storm drainage improvements
- Complete roadway excavation for intersection paving
- Kincaid Avenue (Maple to Main)