Category Construction Update   Show all

  • 1/23/2023 Construction Update

    Work Completed for Week ending 01/20/2023

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Intersection of Kincaid Avenue and Academy Street
      • Begin grading for concrete curbs and sidewalk
    • Alder Avenue (Park to Academy)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    01/17/2023 - Alder Avenue (Academy to Maple) - Water main installation

    01/17/2023 - Kincaid Avenue (Maple to Main) - Complete pouring concrete pavement
    1/17/2023 - Intersection of Kincaid Avenue and Academy Street - Begin concrete curbs and sidewalk


    Work in progress this week (1/23/2023 - 1/27/2023)

    • Park Street (Kincaid to Alder)
      • Continue water service transfers
      • Complete HMA
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Complete HMA
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
      • Complete HMA
    • Kincaid Avenue (Academy to Maple)
      • Complete water service transfers
      • Complete HMA
    • Kincaid Avenue (Maple to Main)
      • Complete ADA strip concrete
      • Complete sewer CIPP
    • Alder Avenue (Park to Maple
      • Begin installation of water services, hydrants, and sample station
    • Alder Avenue (Maple to Main)
      • Complete sewer CIPP
    • Cherry Avenue (Maple to Main)
      • Complete sewer CIPP
      • Complete tree removal

    Upcoming Work through (02/10/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
  • 1/17/2023 Construction Update

    Work Completed for Week ending 01/13/2023

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Continue water main installation on Alder Avenue (Academy to Park)
    • Continue water main installation

    Work in progress this week (1/16/2023 - 1/20/2023)

    • Kincaid Avenue (Academy to Kincaid)
      • Complete water service transfers
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
    • Park Street (Kincaid to Alder)
      • Complete water service transfers
    • Alder Avenue (Academy to Park)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    Upcoming Work through (02/03/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Begin grading for concrete curbs and sidewalk
    • Prepping for HMA (Maple to Main)
  • 1/09/2023 Construction Update

    Work Completed for Week ending 01/06/2023

    • Kincaid Avenue (Maple to Main)
      • Completed grading for concrete pavement
      • Continued pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continued storm drainage improvements
    • Alder Avenue (Academy to Park)
    • Begin water main installation
    • 1/06/2023 - Kincaid Avenue Maple to Main Street Concrete Pavement1/06/2023 - Intersection of Kincaid Avenue and Park Street storm drain improvements

    1/06/2023 - Alder Avenue Academy to Park Water Main Installation

    Work in progress this week (1/09/2023 - 1/13/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Kincaid Avenue (Academy to Kincaid)
      • Complete water service transfers
    • Kincaid Avenue (Park to Academy)
      • Complete water service transfers
    • Park Street (Kincaid to Alder)
      • Complete water service transfers
    • Alder Avenue (Academy to Park)
      • Continue water main installation
    • Alder Avenue (Academy to Maple)
      • Begin water main installation

    Upcoming Work through (1/27/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Begin grading for concrete curbs and sidewalks
  • 1/3/2022 Construction Update

    Work Completed for Week ending 12/30/2022

    • No Construction Due to Holiday

    Work in progress this week (1/03/2023 - 1/06/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
    • Alder Avenue (Academy to Park)
      • Begin water main installation

    Upcoming Work through (1/20/2023)

    • Cherry Avenue (Maple to Main)
      • Set up traffic control
      • Complete clear and grub
      • Begin demolition
      • Begin storm drainage installation
    • Alder Avenue (Academy to Park)
      • Complete water main installation


  • 12/26/2022 Construction Update

    Work Completed for Week ending 12/23/22

    • Intersection of Kincaid Avenue and Park Street
      • Continue excavation of intersection
      • Begin water service transfers
      • Water tie in on Kincaid south of Park
      • Begin storm drainage improvements
    • Kincaid Avenue (Maple to Main)
      • Continue pouring concrete curbs and sidewalk
      • Continue grading for concrete pavement
      • Continue pouring concrete pavement

    12/19/2022 Pouring Concrete Sidewalk North End of Kincaid Avenue

    12/19/2022 Excavation of Intersection at Kincaid Avenue and Park Street

    12/20/2022 Water Tie In On Kincaid Avenue South of Park Street

    Work in progress this week (12/26/2022 - 12/30/2022)

    • Week of 12/25 - 12/30 No construction due to Holiday

    Upcoming Work through (1/13/2023)

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
  • 12/19/22 Construction Update

    Work Completed for Week ending 12/16/22

    • Kincaid Avenue (Maple to Main)
      • Pouring concrete curbs and sidewalk
    • Intersection of Kincaid Avenue and Park Street
      • Excavation of intersection

    12/12/2022 Excavation of intersection at Kincaid Avenue and Park Street

    12/13/2022 Pouring parking strip on North end of Kincaid Avenue

    12/13/2022 Stamping concrete parking strip on North end of Kincaid Avenue

    Work in progress this week (12/19/2022 - 12/23/2022)

    • Intersection of Kincaid Avenue and Park Street
      • Begin water service transfers
      • Water tie in on Kincaid south of Park
      • Begin storm drainage improvements
    • Kincaid Avenue (Maple to Main)
      • Continue grading for concrete pavement
      • Continue pouring concrete pavement

    Upcoming Work through (1/6/2023)

    • Week of 12/25 - 12/30 No construction due to Holiday
    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete pavement
      • Complete pouring concrete pavement
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
    • Intersection of Kincaid Avenue and Park Street
      • Continue storm drainage improvements
  • 12/12/22 Construction Update

    Work completed for Week Ending 12/09/2022:

    • Kincaid Avenue (Maple to Main)
      • Continue pouring concrete curbs and sidewalk
    • Intersection of Kincaid Avenue and Park Street
      • Complete excavation of intersection.

    12/06/22: Finishing concrete sidewalk on the east side of Kincaid Avenue north of Maple Street. 12/07/22: Spreading geotextile fabric over the roadway subgrade at the intersection of Kincaid Avenue and Park Street. 12/08/22: Concrete formwork for driveway on the east side of Kincaid Avenue north of Maple Street 12/09/22: Finishing concrete driveway on east side of Kincaid Avenue north of Maple Street.

    Work in progress this week (12/12/2022 - 12/16/2022):

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete curbs and sidewalk
      • Complete grading for concrete
      • Start pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete intersection grading
      • Begin storm drainage improvements

    Upcoming Work through 12/30/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
  • 12/05/22 Construction Update

    Work completed for Week Ending 12/02/2022:

    • Kincaid Avenue (Maple to Main)
      • Continued pouring concrete curbs and sidewalk
    • Intersection of Kincaid Avenue and Park Street
      • Complete demolition of sidewalks

    11/28/22: Pouring and finishing new concrete sidewalk on the west side of Kincaid Avenue north of Maple Street 11/29/22: Demolishing intersection of Kincaid Avenue and Park Street.

    11/29/22: Temporary asphalt on the south side of intersection of Main Street/Kincaid Avenue/Cherry Avenue for the Santa Parade.

    11/30/22: Formwork for planters on the east side of Kincaid Avenue south of Main Street.

    Work in progress this week (12/05/2022 - 12/09/2022):

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete
      • Complete pouring curbs and sidewalks
      • Start pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete demolition
      • Begin storm drainage improvements

    Upcoming Work through 12/23/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete pouring concrete roadway
    • Kincaid Avenue (Academy to Maple)
      • Begin pouring curbs
    • Kincaid Avenue (Park to Academy)
      • Begin pouring curbs
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Complete roadway excavation and grading for intersection paving
    • Alder Avenue (Academy to Maple)
      • Begin water main installation
  • 11/28/22 Construction Update

    Work completed for Week Ending 11/25/2022:

    • Kincaid Avenue (Maple to Main)
      • Started pouring concrete curbs and sidewalk

    11/21/22: Concrete curb formwork on Kincaid between Main Street and Maple Street.

    11/21/22: Concrete sidewalk poured on the west side of Kincaid Avenue south of Main Street.

    11/23/22: New concrete sidewalk on the west side of Kincaid Avenue south of Main Street.

    11/23/22: Grading Kincaid Avenue for concrete roadway south of Main Street.

    Work in progress this week (11/28/2022 - 12/02/2022):

    • Kincaid Avenue (Maple to Main)
      • Complete grading for concrete
      • Complete pouring curbs and sidewalks
      • Start pouring concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete demolition of sidewalks
      • Begin storm drainage improvements

    Upcoming Work through 12/16/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete pouring concrete roadway
    • Kincaid Avenue (Academy to Maple)
      • Begin pouring curbs and sidewalks
    • Kincaid Avenue (Park to Academy)
      • Begin pouring curbs and sidewalks
    • Intersection of Kincaid Avenue and Park Street
      • Complete storm drainage improvements
      • Complete roadway excavation and grading for intersection paving
    • Academy Street
      • Begin water main installation
  • 11/21/22 Construction Update

    Work completed for Week Ending 11/18/2022:

    • Kincaid Avenue (Maple to Main)
      • Completed sidewalk demolition and grading
      • Completed pouring concrete curb
      • Started pouring concrete sidewalk
    • Kincaid Avenue (Park to Academy)
      • Completed trench restoration

    11/14/22: Pouring concrete over water service connection crossings on Kincaid Avenue south of Academy Street.

    11/15/22: Checking subgrade elevation on Kincaid Avenue south of Main Street.


    11/16/22: Pouring concrete curb on the east side of Kincaid Avenue between Maple Street and Main Street.


    11/17/22: Formwork for concrete planter on the east side of Kincaid Avenue between Maple Street and Main Street.



    11/18/22: New concrete sidewalk on the east side of Kincaid Avenue south of Main Street.


    Work in progress this week (11/21/2022 - 11/25/2022):

    • Kincaid Avenue (Maple to Main)
      • Continue pouring curbs and sidewalks

    Upcoming Work through 12/09/2022:

    • Kincaid Avenue (Maple to Main):
      • Complete pouring curbs and sidewalks
      • Pour concrete roadway
    • Intersection of Kincaid Avenue and Park Street
      • Complete demolition of sidewalks
      • Complete storm drainage improvements
      • Complete roadway excavation for intersection paving