4/17/2023 Construction Update
Upcoming Downtown Construction Impact Meeting
April 19th 8:30am-9:30am or 5:30pm-6:30pm at City Hall
WORK COMPLETED FOR WEEK ENDING 04/14/2023
- Alder Ave and Park St intersection
- Complete water service transfers
- Complete water tie-ins on Alder
- Cherry Avenue (Maple to Main
- Complete testing storm
- Complete installing illumination system
- Cherry Ave and Maple St intersection
- Complete testing water
- Complete water tie-ins on Maple
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
WORK IN PROGRESS THIS WEEK (4/17/2023 - 04/21/2023)
- Alder Ave and Park St intersection
- Complete water service transfers
- Complete water tie-ins on Alder
- Cherry Avenue (Maple to Main
- Begin installing irrigation sleeves
- Begin roadway excavation
- Complete storm testing
- Begin CSBS
- Cherry Ave and Maple St intersection
- Begin installing storm system
- Begin roadway excavation
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete pouring concrete curb and gutter
- Begin pouring concrete sidewalks and ramps
UPCOMING WORK THROUGH (05/05/2023)
- Alder Ave and Park St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Cherry Avenue (Maple to Main)
- Complete installing irrigation sleeves
- Complete roadway excavation and grading
- Cherry Ave and Maple St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Complete pouring concrete curb and gutter
- Complete pouring concrete sidewalks and ramps
- Begin pouring concrete roadway
- Alder Ave and Park St intersection
-
04/10/2022 Construction Update
Upcoming Downtown Construction Impact Meeting
April 19th 8:30-9:30 or 5:30-6:30 at City Hall
WORK COMPLETED FOR WEEK ENDING 04/07/2023
- Alder Ave and Park St intersection
- Completed demolishing pavement
- Began installing storm drainage
- Cherry Avenue (Maple to Main
- Began testing storm
- Began installing illumination system
- Cherry Ave and Maple St intersection
- Began testing water
- Began installing storm drainage
- Main St intersection with Kincaid Ave and Cherry Ave
- Completed demolishing pavement
- Completed installing storm drainage
- Completed installing fiber optic conduit
WORK IN PROGRESS THIS WEEK (4/10/2023 - 04/14/2023)
- Alder Ave and Park St intersection
- Complete water service transfers
- Complete water tie-ins on Alder
- Cherry Avenue (Maple to Main
- Complete testing storm
- Complete installing illumination system
- Cherry Ave and Maple St intersection
- Complete testing water
- Complete water tie-ins on Maple
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
UPCOMING WORK THROUGH (04/27/2023)
- Alder Ave and Park St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Cherry Avenue (Maple to Main
- Complete installing irrigation sleeves
- Complete roadway excavation and grading
- Cherry Ave and Maple St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Complete pouring concrete curb and gutter
- Complete pouring concrete sidewalks and ramps
- Begin pouring concrete roadway
- Alder Ave and Park St intersection
-
03/20/2023 Construction Update
Work Completed for Week ending 03/17/2023
- Kincaid (Maple to Main)
- Pour and Stamp Concrete
- Cherry Avenue (Maple to Main)
- Continue installing storm drainage.
- Continue replacing sanitary sewer laterals and clean out.
- Begin installing joint utility trench
- Complete water tie-in south of Main Street
- Academy Street (Alder to Ryan)
- Complete installing storm drainage
- Continue Road excavation / gravel borrow and csbc
Work in progress this week (3/20/2023 - 3/24/2023)
- Kincaid (Maple to Main)
- Begin installation of Bollards
- Kincaid Ave will be closed Thursday (3/23) & Friday (3/24)
- Begin installation of Bollards
- Cherry Avenue (Maple to Main)
- Complete storm drainage demolition and installation
- Complete joint utility trench
- Academy Street (Alder to Ryan)
- Complete road excavation / gravel borrow and csbc
- Complete curb and gutter
- Begin concrete flat work and ramps
- Complete water tie in at Academy/Alder intersection
Upcoming Work through (04/07/2023) - Work on Main Street will not begin until after the Daffodil Parade (04/01/23)
- Academy / Ryan Intersection
- Complete asphalt paving (1st lift)
- Academy Street (Alder to Ryan)
- Complete trench restoration
- Complete asphalt paving (1st lift)
- Cherry Avenue (Maple to Main)
- Complete Illumination
- Begin irrigation
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete installing water main
- Complete water tie-in
- Complete storm drainage
- Prepare for Daffodil Parade
- Open Driveway from Alleyway to Kincaid
- Main Street / Cherry Avenue / Kincaid Avenue intersection
- Main Street in westbound only condition from Alder Avenue to Traffic Avenue (eastbound local access from Traffic Avenue to BNSF)
- Begin demolition on south side
- Begin installation of storm drainage
- Kincaid (Maple to Main)
-
03/13/2023 Construction Update
Work Completed for Week ending 03/10/2023
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station.
- Cherry Avenue (Maple to Main)
- Continue installing storm drainage.
- Complete replacing sanitary sewer laterals and clean out.
- Academy / Ryan Intersection
- Complete demolition
- Complete water tie in at Academy and Ryan
- Academy Street (Alder to Ryan)
- Complete demolition
- Continue installing storm drainage
Work in progress this week (3/13/2023 - 3/17/2023)
- Cherry Avenue (Maple to Main)
- Complete Storm Drainage Installation
- Academy Street (Alder to Ryan)
- Begin Road excavation / gravel borrow and csbc
- Complete Storm Drainage Installation
Upcoming Work through (03/31/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)
- Alder Avenue (Park to Maple)
- Complete water services and hydrant
- Complete water testing
- Complete curb and sidewalk
- Academy / Ryan Intersection
- Complete Paving
- Academy / Alder Intersection
- Complete water tie-in
- Academy Street (Alder to Ryan)
- Complete road excavation / gravel borrow and csbc
- Complete curb and sidewalk
- Complete Paving
- Cherry Avenue (Maple to Main)
- Complete joint utility trench
- Complete water tie-in south of Main St.
- Begin Illumination
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete water tie-in
- Begin installing water main
- Prepare for Daffodil Parade
- Open Driveway from Alleyway to Kincaid
- Alder Avenue (Park to Maple)
-
3/06/2023 Construction Update
Work Completed for Week ending 02/24/2023
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station.
- Complete doweling concrete for rebar trench line and pour concrete.
- Complete asphalt over water trenches
- Cherry Avenue (Maple to Main)
- Continue installing storm drainage.
- Complete replacing sanitary sewer laterals and clean out.
- Academy / Ryan Intersection
- Begin demolition
- Academy Street (Alder to Ryan)
- Begin demolition
Work in progress this week (2/27/2023 - 3/03/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Kincaid Avenue (Park to Maple)
- Continue concrete flatwork
- Continue Curb Patches
- Continue Water Testing
- Academy / Ryan Intersection
- Complete demolition
- Complete water tie in at Academy and Ryan
- Academy Street (Alder to Ryan)
- Complete demolition
- Begin Storm Drainage Installation
Upcoming Work through (03/17/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)
- Alder Avenue (Park to Maple)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Complete curb and sidewalk
- Park/Alder intersection
- Complete water tie-in
- Academy / Ryan Intersection
- Complete demolition
- Complete water tie-in
- Complete Paving
- Academy Street (Alder to Ryan)
- Complete demolition
- Complete water-tie
- Complete installing storm drainage
- Complete Paving
- Complete curb and sidewalk
- Complete gravel borrow and csbc
- Cherry Avenue (Maple to Main)
- Complete installing storm drainage
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete water tie-in
- Alder Avenue (Park to Maple)
-
2/27/2023 Construction Update
Work Completed for Week ending 02/24/2023
- Park Street (Kincaid to Alder)
- Continue transferring water services.
- Continue concrete sidewalks and ADA ramps
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station
- Complete doweling concrete for rebar trench line and pour concrete
- Cherry Avenue (Maple to Main)
- Continue demolition
- Continue installing storm drainage.
- Begin replacing sanitary sewer laterals and clean out.
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- PSE transferred power to new poles.
Work in progress this week (2/27/2023 - 3/03/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Continue replacing sanitary sewer laterals and clean out.
- Kincaid Avenue (Park to Maple)
- Continue concrete flatwork
- Continue Curb Patches
- Continue Water Testing
- Alder Avenue (Park to Maple
- Complete asphalt over water trenches
- Academy / Ryan Intersection
- Begin demolition
- Academy Street (Alder to Ryan)
- Begin demolition
Upcoming Work through (03/17/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)
- Alder Avenue (Park to Maple)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Park/Alder intersection
- Complete water tie-in
- Academy / Ryan Intersection
- Complete demolition
- Complete water tie-in
- Academy Street (Alder to Ryan)
- Complete demolition
- Complete water-tie
- Complete installing storm drainage
- Cherry Avenue (Maple to Main)
- Complete installing storm drainage
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- Begin Storm
- Begin Water
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete water tie-in
- Park Street (Kincaid to Alder)
-
02/20/2023 Construction Update
Work Completed for Week ending 02/10/2023
- Park Street (Kincaid to Alder)
- Continue transferring water services.
- Continue concrete sidewalks and ADA ramps
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station
- Cherry Avenue (Maple to Main)
- Continue demolition
- Continue installing storm drainage
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
Work in progress this week (2/20/2023 - 2/24/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Continue potholing for water.
- Begin replacing sanitary sewer laterals
- Kincaid Avenue (Park to Maple)
- Curb Patches
- Water Testing
- Alder Avenue (Park to Maple)
- Water Testing
- Begin doweling concrete for rebar trench line and pour concrete
- Academy Street (Alder to Ryan)
- Water Testing
- Begin doweling concrete for rebar trench line and pour concrete
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
Upcoming Work through (03/10/2023)
- Main Street intersection at Cherry/Kincaid
- Begin construction on south side of intersection. Main Street will be west bound only.
- Alder Avenue (Park to Academy)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Temporary Asphalt
- Kincaid Avenue (Park to Maple)
- Temporary asphalt over trenches
- Alder Avenue (Park to Maple)
- Temporary asphalt over trenches
- Cherry Avenue (Maple to Main)
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- Begin Storm
- Begin Water
- PSE setting new poles and transferring services to new poles.
- Park Street (Kincaid to Alder)
-
02/13/2023 Construction Update
Work Completed for Week ending 02/10/2023
- Park Street (Kincaid to Alder)
- Continue transferring water services.
- Continue grading for concrete sidewalks and ADA ramps.
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station
- Continue installing storm drainage
- Cherry Avenue (Maple to Main)
- Begin demolition
Work in progress this week (2/13/2023 - 2/17/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Begin potholing for water.
- Academy Street (Alder to Park)
- Continue Water Main installation.
- Kincaid Avenue and Park Street Intersection
- Continue concrete sidewalks and ADA ramps
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
Upcoming Work through (03/03/2023)
- Alder Avenue (Park to Academy)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Kincaid Avenue (Park to Maple)
- Curb Patches
- Water Testing
- Cherry Avenue (Maple to Main)
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- PSE setting new poles and transferring services to new poles.
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Park Street (Kincaid to Alder)
-
02/06/2023 Construction Update
Work Completed for Week ending 02/03/2023
- Park Street (Kincaid to Alder)
- Continue transferring water services.
- Continue grading for concrete sidewalks and ADA ramps.
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station
- Continue installing storm drainage
- Cherry Avenue (Maple to Main)
- Begin demolition.
Work in progress this week (2/06/2023 - 2/10/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Begin potholing for water.
- Academy Street (Alder to Park)
- Begin Water Main installation.
- Kincaid Avenue and Park Street Intersection
- Begin concrete sidewalks and ADA ramps
Upcoming Work through (02/24/2023)
- Alder Avenue (Park to Academy)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Kincaid Avenue (Park to Maple)
- Curb Patches
- Water Testing
- Cherry Avenue (Maple to Main)
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- PSE setting new poles and transferring services to new poles.
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
- 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Park Street (Kincaid to Alder)
-
1/30/2023 Construction Update
Work Completed for Week ending 01/27/2023
- Kincaid Avenue (Maple to Main)
- Complete pouring concrete pavement
- Intersection of Kincaid Avenue and Park Street.
- Continue storm drainage improvements.
- Intersection of Kincaid Avenue and Academy Street
- Continue grading for concrete curbs and sidewalk.
- Alder Avenue (Park to Academy)
- Continue water main installation.
- Alder Avenue (Academy to Maple)
- Begin water main installation.
Work in progress this week (1/30/2023 - 2/03/2023)
- Park Street (Kincaid to Alder)
- Continue water service transfers.
- Continue grade for concrete.
- Alder Avenue (Park to Maple)
- Continue installation of water services, hydrants, and sample station
- Continue Storm drainage installation.
- Cherry Avenue (Maple to Main)
- Set up traffic control.
- Complete clear and grub
- Begin demolition.
- Begin storm drainage installation.
Upcoming Work through (02/17/2023)
- Alder Avenue (Academy to Park)
- Complete water main installation
- Complete water services and hydrants
- Complete water testing
- Kincaid Avenue (Maple to Main)