Category Construction Update   Show all

  • 4/17/2023 Construction Update

    Upcoming Downtown Construction Impact Meeting

    April 19th 8:30am-9:30am or 5:30pm-6:30pm at City Hall



    WORK COMPLETED FOR WEEK ENDING 04/14/2023

    • Alder Ave and Park St intersection
      • Complete water service transfers
      • Complete water tie-ins on Alder
    • Cherry Avenue (Maple to Main
      • Complete testing storm
      • Complete installing illumination system
    • Cherry Ave and Maple St intersection
      • Complete testing water
      • Complete water tie-ins on Maple
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete roadway excavation and grading
      • Begin pouring concrete curb and gutter
    04/12/2023 Alder and Park Intersection - Water Service Transfers and Tie Ins


    04/14/2023 Main St Intersection with Kincaid & Cherry - Roadway Excavation and Grading
    04/14/2023 Cherry Ave - Installing Illumination System


    WORK IN PROGRESS THIS WEEK (4/17/2023 - 04/21/2023)

    • Alder Ave and Park St intersection
      • Complete water service transfers
      • Complete water tie-ins on Alder
    • Cherry Avenue (Maple to Main
      • Begin installing irrigation sleeves
      • Begin roadway excavation
      • Complete storm testing
      • Begin CSBS
    • Cherry Ave and Maple St intersection
      • Begin installing storm system
      • Begin roadway excavation
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete pouring concrete curb and gutter
      • Begin pouring concrete sidewalks and ramps

    UPCOMING WORK THROUGH (05/05/2023)

    • Alder Ave and Park St intersection
      • Complete installing storm drainage
      • Complete roadway excavation and grading
    • Cherry Avenue (Maple to Main)
      • Complete installing irrigation sleeves
      • Complete roadway excavation and grading
    • Cherry Ave and Maple St intersection
      • Complete installing storm drainage
      • Complete roadway excavation and grading
      • Begin pouring concrete curb and gutter
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete roadway excavation and grading
      • Complete pouring concrete curb and gutter
      • Complete pouring concrete sidewalks and ramps
      • Begin pouring concrete roadway
  • 04/10/2022 Construction Update


    Upcoming Downtown Construction Impact Meeting

    April 19th 8:30-9:30 or 5:30-6:30 at City Hall



    WORK COMPLETED FOR WEEK ENDING 04/07/2023

    • Alder Ave and Park St intersection
      • Completed demolishing pavement
      • Began installing storm drainage
    • Cherry Avenue (Maple to Main
      • Began testing storm
      • Began installing illumination system
    • Cherry Ave and Maple St intersection
      • Began testing water
      • Began installing storm drainage
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Completed demolishing pavement
      • Completed installing storm drainage
      • Completed installing fiber optic conduit

    04/04/2023: Demolishing the intersection of Alder Avenue with Park Street 04/05/2023: Pouring concrete sidewalk and ramps on the northeast corner of Alder Avenue and Academy Street

    04/06/2023: Trenching for fiber optic conduit at the intersection with Main Street with Alder Avenue and Kincaid Avenue.


    04/07/2023: Grading the SW corner of Alder Avenue and Academy Street

    WORK IN PROGRESS THIS WEEK (4/10/2023 - 04/14/2023)


    • Alder Ave and Park St intersection
      • Complete water service transfers
      • Complete water tie-ins on Alder
    • Cherry Avenue (Maple to Main
      • Complete testing storm
      • Complete installing illumination system
    • Cherry Ave and Maple St intersection
      • Complete testing water
      • Complete water tie-ins on Maple
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete roadway excavation and grading
      • Begin pouring concrete curb and gutter

    UPCOMING WORK THROUGH (04/27/2023)

    • Alder Ave and Park St intersection
      • Complete installing storm drainage
      • Complete roadway excavation and grading
    • Cherry Avenue (Maple to Main
      • Complete installing irrigation sleeves
      • Complete roadway excavation and grading
    • Cherry Ave and Maple St intersection
      • Complete installing storm drainage
      • Complete roadway excavation and grading
      • Begin pouring concrete curb and gutter
    • Main St intersection with Kincaid Ave and Cherry Ave
      • Complete roadway excavation and grading
      • Complete pouring concrete curb and gutter
      • Complete pouring concrete sidewalks and ramps
      • Begin pouring concrete roadway
  • 03/20/2023 Construction Update

    Work Completed for Week ending 03/17/2023

    • Kincaid (Maple to Main)
      • Pour and Stamp Concrete
    • Cherry Avenue (Maple to Main)
      • Continue installing storm drainage.
      • Continue replacing sanitary sewer laterals and clean out.
      • Begin installing joint utility trench
      • Complete water tie-in south of Main Street
    • Academy Street (Alder to Ryan)
      • Complete installing storm drainage
      • Continue Road excavation / gravel borrow and csbc

    Cherry Ave - Continue installing storm drainage and connecting road drainage.

    Kincaid Ave (Maple to Main) - Pour and stamp concrete

    Work in progress this week (3/20/2023 - 3/24/2023)


    • Kincaid (Maple to Main)
      • Begin installation of Bollards
        • Kincaid Ave will be closed Thursday (3/23) & Friday (3/24)
    • Cherry Avenue (Maple to Main)
      • Complete storm drainage demolition and installation
      • Complete joint utility trench
    • Academy Street (Alder to Ryan)
      • Complete road excavation / gravel borrow and csbc
      • Complete curb and gutter
      • Begin concrete flat work and ramps
      • Complete water tie in at Academy/Alder intersection

    Upcoming Work through (04/07/2023) - Work on Main Street will not begin until after the Daffodil Parade (04/01/23)

    • Academy / Ryan Intersection
      • Complete asphalt paving (1st lift)
    • Academy Street (Alder to Ryan)
      • Complete trench restoration
      • Complete asphalt paving (1st lift)
    • Cherry Avenue (Maple to Main)
      • Complete Illumination
      • Begin irrigation
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
    • Maple/Cherry intersection
      • Complete installing water main
      • Complete water tie-in
      • Complete storm drainage
    • Prepare for Daffodil Parade
      • Open Driveway from Alleyway to Kincaid
    • Main Street / Cherry Avenue / Kincaid Avenue intersection
      • Main Street in westbound only condition from Alder Avenue to Traffic Avenue (eastbound local access from Traffic Avenue to BNSF)
      • Begin demolition on south side
      • Begin installation of storm drainage
  • 03/13/2023 Construction Update

    Work Completed for Week ending 03/10/2023

    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station.
    • Cherry Avenue (Maple to Main)
      • Continue installing storm drainage.
      • Complete replacing sanitary sewer laterals and clean out.
    • Academy / Ryan Intersection
      • Complete demolition
      • Complete water tie in at Academy and Ryan
    • Academy Street (Alder to Ryan)
      • Complete demolition
      • Continue installing storm drainage


    03/07/2023 Cherry Ave - Continue installing storm drainage.

    03/09/2023 Academy/Ryan Intersection - Begin water tie in


    Work in progress this week (3/13/2023 - 3/17/2023)

    • Cherry Avenue (Maple to Main)
      • Complete Storm Drainage Installation
    • Academy Street (Alder to Ryan)
      • Begin Road excavation / gravel borrow and csbc
      • Complete Storm Drainage Installation

    Upcoming Work through (03/31/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)

    • Alder Avenue (Park to Maple)
      • Complete water services and hydrant
      • Complete water testing
      • Complete curb and sidewalk
    • Academy / Ryan Intersection
      • Complete Paving
    • Academy / Alder Intersection
      • Complete water tie-in
    • Academy Street (Alder to Ryan)
      • Complete road excavation / gravel borrow and csbc
      • Complete curb and sidewalk
      • Complete Paving
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in south of Main St.
      • Begin Illumination
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
    • Maple/Cherry intersection
      • Complete water tie-in
      • Begin installing water main
    • Prepare for Daffodil Parade
      • Open Driveway from Alleyway to Kincaid
  • 3/06/2023 Construction Update

    Work Completed for Week ending 02/24/2023

    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station.
      • Complete doweling concrete for rebar trench line and pour concrete.
      • Complete asphalt over water trenches
    • Cherry Avenue (Maple to Main)
      • Continue installing storm drainage.
      • Complete replacing sanitary sewer laterals and clean out.
    • Academy / Ryan Intersection
      • Begin demolition
    • Academy Street (Alder to Ryan)
      • Begin demolition

    02/28/2023 Cherry Ave - Replacing sanitary sewer laterals and clean outs.

    02/28/2023 Academy Street - Begin Demolition



    Work in progress this week (2/27/2023 - 3/03/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
    • Kincaid Avenue (Park to Maple)
      • Continue concrete flatwork
      • Continue Curb Patches
      • Continue Water Testing
    • Academy / Ryan Intersection
      • Complete demolition
      • Complete water tie in at Academy and Ryan
    • Academy Street (Alder to Ryan)
      • Complete demolition
      • Begin Storm Drainage Installation

    Upcoming Work through (03/17/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)

    • Alder Avenue (Park to Maple)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
      • Complete curb and sidewalk
    • Park/Alder intersection
      • Complete water tie-in
    • Academy / Ryan Intersection
      • Complete demolition
      • Complete water tie-in
      • Complete Paving
    • Academy Street (Alder to Ryan)
      • Complete demolition
      • Complete water-tie
      • Complete installing storm drainage
      • Complete Paving
      • Complete curb and sidewalk
      • Complete gravel borrow and csbc
    • Cherry Avenue (Maple to Main)
      • Complete installing storm drainage
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
    • Maple/Cherry intersection
      • Complete water tie-in
  • 2/27/2023 Construction Update

    Work Completed for Week ending 02/24/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue concrete sidewalks and ADA ramps
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
      • Complete doweling concrete for rebar trench line and pour concrete
    • Cherry Avenue (Maple to Main)
      • Continue demolition
      • Continue installing storm drainage.
      • Begin replacing sanitary sewer laterals and clean out.
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • PSE transferred power to new poles.

    2/23/2023 Cherry Ave - sewer laterals and clean outs

    2/23/2023 Alder Ave - Doweling concrete for rebar trench line



    Work in progress this week (2/27/2023 - 3/03/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Continue replacing sanitary sewer laterals and clean out.
    • Kincaid Avenue (Park to Maple)
      • Continue concrete flatwork
      • Continue Curb Patches
      • Continue Water Testing
    • Alder Avenue (Park to Maple
      • Complete asphalt over water trenches
    • Academy / Ryan Intersection
      • Begin demolition
    • Academy Street (Alder to Ryan)
      • Begin demolition

    Upcoming Work through (03/17/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)

    • Alder Avenue (Park to Maple)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
    • Park/Alder intersection
      • Complete water tie-in
    • Academy / Ryan Intersection
      • Complete demolition
      • Complete water tie-in
    • Academy Street (Alder to Ryan)
      • Complete demolition
      • Complete water-tie
      • Complete installing storm drainage
    • Cherry Avenue (Maple to Main)
      • Complete installing storm drainage
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • Begin Storm
      • Begin Water
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
    • Maple/Cherry intersection
      • Complete water tie-in
  • 02/20/2023 Construction Update

    Work Completed for Week ending 02/10/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue concrete sidewalks and ADA ramps
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
    • Cherry Avenue (Maple to Main)
      • Continue demolition
      • Continue installing storm drainage
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.

    2/13/2023 Cherry Avenue - Continue Demolition


    02/16/2023 Park Street - Continue Concrete Sidewalks and ADA Ramps



    Work in progress this week (2/20/2023 - 2/24/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Continue potholing for water.
      • Begin replacing sanitary sewer laterals
    • Kincaid Avenue (Park to Maple)
      • Curb Patches
      • Water Testing
    • Alder Avenue (Park to Maple)
      • Water Testing
      • Begin doweling concrete for rebar trench line and pour concrete
    • Academy Street (Alder to Ryan)
      • Water Testing
      • Begin doweling concrete for rebar trench line and pour concrete
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.

    Upcoming Work through (03/10/2023)

    • Main Street intersection at Cherry/Kincaid
      • Begin construction on south side of intersection. Main Street will be west bound only.
    • Alder Avenue (Park to Academy)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
      • Temporary Asphalt
    • Kincaid Avenue (Park to Maple)
      • Temporary asphalt over trenches
    • Alder Avenue (Park to Maple)
      • Temporary asphalt over trenches
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • Begin Storm
      • Begin Water
      • PSE setting new poles and transferring services to new poles.
  • 02/13/2023 Construction Update

    Work Completed for Week ending 02/10/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue grading for concrete sidewalks and ADA ramps.
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
      • Continue installing storm drainage
    • Cherry Avenue (Maple to Main)
      • Begin demolition

    02/07/2023 - Installing meter and setter boxes along Kincaid.

    2/10/2023 - Demolition on Cherry Ave (Maple to Main)



    Work in progress this week (2/13/2023 - 2/17/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Begin potholing for water.
    • Academy Street (Alder to Park)
      • Continue Water Main installation.
    • Kincaid Avenue and Park Street Intersection
      • Continue concrete sidewalks and ADA ramps
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.

    Upcoming Work through (03/03/2023)

    • Alder Avenue (Park to Academy)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
    • Kincaid Avenue (Park to Maple)
      • Curb Patches
      • Water Testing
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • PSE setting new poles and transferring services to new poles.
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • 02/06/2023 Construction Update

    Work Completed for Week ending 02/03/2023

    • Park Street (Kincaid to Alder)
      • Continue transferring water services.
      • Continue grading for concrete sidewalks and ADA ramps.
    • Alder Avenue (Park to Maple)
      • Continue installing water services, hydrants, and sample station
      • Continue installing storm drainage
    • Cherry Avenue (Maple to Main)
      • Begin demolition.


    Cherry Ave (Maple to Main Street) - Beginning Demolition


    02/01/2023 Cherry Ave (Maple to Main Street) - Beginning Demolition




    02/01/2023 Park Street (Kincaid to Alder) - Water Service Transfers

    Work in progress this week (2/06/2023 - 2/10/2023)

    • Cherry Avenue (Maple to Main)
      • Continue Storm Drainage Installation
      • Begin potholing for water.
    • Academy Street (Alder to Park)
      • Begin Water Main installation.
    • Kincaid Avenue and Park Street Intersection
      • Begin concrete sidewalks and ADA ramps

    Upcoming Work through (02/24/2023)

    • Alder Avenue (Park to Academy)
      • Complete water main installation
      • Complete water services and hydrant
      • Complete water testing
    • Kincaid Avenue (Park to Maple)
      • Curb Patches
      • Water Testing
    • Cherry Avenue (Maple to Main)
      • Complete joint utility trench
      • Complete water tie-in at Maple St
      • Begin Illumination
      • PSE setting new poles and transferring services to new poles.
    • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
      • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
      • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
      • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • 1/30/2023 Construction Update

    Work Completed for Week ending 01/27/2023

    • Kincaid Avenue (Maple to Main)
      • Complete pouring concrete pavement
    • Intersection of Kincaid Avenue and Park Street.
      • Continue storm drainage improvements.
    • Intersection of Kincaid Avenue and Academy Street
      • Continue grading for concrete curbs and sidewalk.
    • Alder Avenue (Park to Academy)
      • Continue water main installation.
    • Alder Avenue (Academy to Maple)
      • Begin water main installation.

    01/25/2023 - Intersection of Kincaid Avenue and Academy Street - Continue concrete curbs and sidewalk

    01/26/2023 - Kincaid Avenue (Maple to Main) - Complete pouring concrete pavement


    Work in progress this week (1/30/2023 - 2/03/2023)

    • Park Street (Kincaid to Alder)
      • Continue water service transfers.
      • Continue grade for concrete.
    • Alder Avenue (Park to Maple)
      • Continue installation of water services, hydrants, and sample station
      • Continue Storm drainage installation.
    • Cherry Avenue (Maple to Main)
      • Set up traffic control.
      • Complete clear and grub
      • Begin demolition.
      • Begin storm drainage installation.

    Upcoming Work through (02/17/2023)

    • Alder Avenue (Academy to Park)
      • Complete water main installation
      • Complete water services and hydrants
      • Complete water testing