WORK COMPLETED FOR WEEK ENDING 04/14/2023
- Alder Ave and Park St intersection
- Complete water service transfers
- Complete water tie-ins on Alder
- Cherry Avenue (Maple to Main
- Complete testing storm
- Complete installing illumination system
- Cherry Ave and Maple St intersection
- Complete testing water
- Complete water tie-ins on Maple
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
WORK IN PROGRESS THIS WEEK (4/17/2023 - 04/21/2023)
- Alder Ave and Park St intersection
- Complete water service transfers
- Complete water tie-ins on Alder
- Cherry Avenue (Maple to Main
- Begin installing irrigation sleeves
- Begin roadway excavation
- Complete storm testing
- Begin CSBS
- Cherry Ave and Maple St intersection
- Begin installing storm system
- Begin roadway excavation
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete pouring concrete curb and gutter
- Begin pouring concrete sidewalks and ramps
UPCOMING WORK THROUGH (05/05/2023)
- Alder Ave and Park St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Cherry Avenue (Maple to Main)
- Complete installing irrigation sleeves
- Complete roadway excavation and grading
- Cherry Ave and Maple St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Complete pouring concrete curb and gutter
- Complete pouring concrete sidewalks and ramps
- Begin pouring concrete roadway