4/17/2023 Construction Update

Upcoming Downtown Construction Impact Meeting

April 19th 8:30am-9:30am or 5:30pm-6:30pm at City Hall



WORK COMPLETED FOR WEEK ENDING 04/14/2023

  • Alder Ave and Park St intersection
    • Complete water service transfers
    • Complete water tie-ins on Alder
  • Cherry Avenue (Maple to Main
    • Complete testing storm
    • Complete installing illumination system
  • Cherry Ave and Maple St intersection
    • Complete testing water
    • Complete water tie-ins on Maple
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Complete roadway excavation and grading
    • Begin pouring concrete curb and gutter
04/12/2023 Alder and Park Intersection - Water Service Transfers and Tie Ins


04/14/2023 Main St Intersection with Kincaid & Cherry - Roadway Excavation and Grading
04/14/2023 Cherry Ave - Installing Illumination System


WORK IN PROGRESS THIS WEEK (4/17/2023 - 04/21/2023)

  • Alder Ave and Park St intersection
    • Complete water service transfers
    • Complete water tie-ins on Alder
  • Cherry Avenue (Maple to Main
    • Begin installing irrigation sleeves
    • Begin roadway excavation
    • Complete storm testing
    • Begin CSBS
  • Cherry Ave and Maple St intersection
    • Begin installing storm system
    • Begin roadway excavation
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Complete pouring concrete curb and gutter
    • Begin pouring concrete sidewalks and ramps

UPCOMING WORK THROUGH (05/05/2023)

  • Alder Ave and Park St intersection
    • Complete installing storm drainage
    • Complete roadway excavation and grading
  • Cherry Avenue (Maple to Main)
    • Complete installing irrigation sleeves
    • Complete roadway excavation and grading
  • Cherry Ave and Maple St intersection
    • Complete installing storm drainage
    • Complete roadway excavation and grading
    • Begin pouring concrete curb and gutter
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Complete roadway excavation and grading
    • Complete pouring concrete curb and gutter
    • Complete pouring concrete sidewalks and ramps
    • Begin pouring concrete roadway
Categories: Construction Update