03/13/2023 Construction Update

Work Completed for Week ending 03/10/2023

  • Alder Avenue (Park to Maple)
    • Continue installing water services, hydrants, and sample station.
  • Cherry Avenue (Maple to Main)
    • Continue installing storm drainage.
    • Complete replacing sanitary sewer laterals and clean out.
  • Academy / Ryan Intersection
    • Complete demolition
    • Complete water tie in at Academy and Ryan
  • Academy Street (Alder to Ryan)
    • Complete demolition
    • Continue installing storm drainage


03/07/2023 Cherry Ave - Continue installing storm drainage.

03/09/2023 Academy/Ryan Intersection - Begin water tie in


Work in progress this week (3/13/2023 - 3/17/2023)

  • Cherry Avenue (Maple to Main)
    • Complete Storm Drainage Installation
  • Academy Street (Alder to Ryan)
    • Begin Road excavation / gravel borrow and csbc
    • Complete Storm Drainage Installation

Upcoming Work through (03/31/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)

  • Alder Avenue (Park to Maple)
    • Complete water services and hydrant
    • Complete water testing
    • Complete curb and sidewalk
  • Academy / Ryan Intersection
    • Complete Paving
  • Academy / Alder Intersection
    • Complete water tie-in
  • Academy Street (Alder to Ryan)
    • Complete road excavation / gravel borrow and csbc
    • Complete curb and sidewalk
    • Complete Paving
  • Cherry Avenue (Maple to Main)
    • Complete joint utility trench
    • Complete water tie-in south of Main St.
    • Begin Illumination
    • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • Maple/Cherry intersection
    • Complete water tie-in
    • Begin installing water main
  • Prepare for Daffodil Parade
    • Open Driveway from Alleyway to Kincaid
Categories: Construction Update