03/13/2023 Construction Update
Work Completed for Week ending 03/10/2023
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station.
- Cherry Avenue (Maple to Main)
- Continue installing storm drainage.
- Complete replacing sanitary sewer laterals and clean out.
- Academy / Ryan Intersection
- Complete demolition
- Complete water tie in at Academy and Ryan
- Academy Street (Alder to Ryan)
- Complete demolition
- Continue installing storm drainage
Work in progress this week (3/13/2023 - 3/17/2023)
- Cherry Avenue (Maple to Main)
- Complete Storm Drainage Installation
- Academy Street (Alder to Ryan)
- Begin Road excavation / gravel borrow and csbc
- Complete Storm Drainage Installation
Upcoming Work through (03/31/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)
- Alder Avenue (Park to Maple)
- Complete water services and hydrant
- Complete water testing
- Complete curb and sidewalk
- Academy / Ryan Intersection
- Complete Paving
- Academy / Alder Intersection
- Complete water tie-in
- Academy Street (Alder to Ryan)
- Complete road excavation / gravel borrow and csbc
- Complete curb and sidewalk
- Complete Paving
- Cherry Avenue (Maple to Main)
- Complete joint utility trench
- Complete water tie-in south of Main St.
- Begin Illumination
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete water tie-in
- Begin installing water main
- Prepare for Daffodil Parade
- Open Driveway from Alleyway to Kincaid