03/20/2023 Construction Update

Work Completed for Week ending 03/17/2023

  • Kincaid (Maple to Main)
    • Pour and Stamp Concrete
  • Cherry Avenue (Maple to Main)
    • Continue installing storm drainage.
    • Continue replacing sanitary sewer laterals and clean out.
    • Begin installing joint utility trench
    • Complete water tie-in south of Main Street
  • Academy Street (Alder to Ryan)
    • Complete installing storm drainage
    • Continue Road excavation / gravel borrow and csbc

Cherry Ave - Continue installing storm drainage and connecting road drainage.

Kincaid Ave (Maple to Main) - Pour and stamp concrete

Work in progress this week (3/20/2023 - 3/24/2023)


  • Kincaid (Maple to Main)
    • Begin installation of Bollards
      • Kincaid Ave will be closed Thursday (3/23) & Friday (3/24)
  • Cherry Avenue (Maple to Main)
    • Complete storm drainage demolition and installation
    • Complete joint utility trench
  • Academy Street (Alder to Ryan)
    • Complete road excavation / gravel borrow and csbc
    • Complete curb and gutter
    • Begin concrete flat work and ramps
    • Complete water tie in at Academy/Alder intersection

Upcoming Work through (04/07/2023) - Work on Main Street will not begin until after the Daffodil Parade (04/01/23)

  • Academy / Ryan Intersection
    • Complete asphalt paving (1st lift)
  • Academy Street (Alder to Ryan)
    • Complete trench restoration
    • Complete asphalt paving (1st lift)
  • Cherry Avenue (Maple to Main)
    • Complete Illumination
    • Begin irrigation
    • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • Maple/Cherry intersection
    • Complete installing water main
    • Complete water tie-in
    • Complete storm drainage
  • Prepare for Daffodil Parade
    • Open Driveway from Alleyway to Kincaid
  • Main Street / Cherry Avenue / Kincaid Avenue intersection
    • Main Street in westbound only condition from Alder Avenue to Traffic Avenue (eastbound local access from Traffic Avenue to BNSF)
    • Begin demolition on south side
    • Begin installation of storm drainage