03/20/2023 Construction Update
Work Completed for Week ending 03/17/2023
- Kincaid (Maple to Main)
- Pour and Stamp Concrete
- Cherry Avenue (Maple to Main)
- Continue installing storm drainage.
- Continue replacing sanitary sewer laterals and clean out.
- Begin installing joint utility trench
- Complete water tie-in south of Main Street
- Academy Street (Alder to Ryan)
- Complete installing storm drainage
- Continue Road excavation / gravel borrow and csbc
Work in progress this week (3/20/2023 - 3/24/2023)
- Kincaid (Maple to Main)
- Begin installation of Bollards
- Kincaid Ave will be closed Thursday (3/23) & Friday (3/24)
- Begin installation of Bollards
- Cherry Avenue (Maple to Main)
- Complete storm drainage demolition and installation
- Complete joint utility trench
- Academy Street (Alder to Ryan)
- Complete road excavation / gravel borrow and csbc
- Complete curb and gutter
- Begin concrete flat work and ramps
- Complete water tie in at Academy/Alder intersection
Upcoming Work through (04/07/2023) - Work on Main Street will not begin until after the Daffodil Parade (04/01/23)
- Academy / Ryan Intersection
- Complete asphalt paving (1st lift)
- Academy Street (Alder to Ryan)
- Complete trench restoration
- Complete asphalt paving (1st lift)
- Cherry Avenue (Maple to Main)
- Complete Illumination
- Begin irrigation
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete installing water main
- Complete water tie-in
- Complete storm drainage
- Prepare for Daffodil Parade
- Open Driveway from Alleyway to Kincaid
- Main Street / Cherry Avenue / Kincaid Avenue intersection
- Main Street in westbound only condition from Alder Avenue to Traffic Avenue (eastbound local access from Traffic Avenue to BNSF)
- Begin demolition on south side
- Begin installation of storm drainage