02/20/2023 Construction Update
Work Completed for Week ending 02/10/2023
- Park Street (Kincaid to Alder)
- Continue transferring water services.
- Continue concrete sidewalks and ADA ramps
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station
- Cherry Avenue (Maple to Main)
- Continue demolition
- Continue installing storm drainage
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.
Work in progress this week (2/20/2023 - 2/24/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Continue potholing for water.
- Begin replacing sanitary sewer laterals
- Kincaid Avenue (Park to Maple)
- Curb Patches
- Water Testing
- Alder Avenue (Park to Maple)
- Water Testing
- Begin doweling concrete for rebar trench line and pour concrete
- Academy Street (Alder to Ryan)
- Water Testing
- Begin doweling concrete for rebar trench line and pour concrete
- PSE Pole Relocations in Alley south of Main between Kincaid and Alder
- 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
Upcoming Work through (03/10/2023)
- Main Street intersection at Cherry/Kincaid
- Begin construction on south side of intersection. Main Street will be west bound only.
- Alder Avenue (Park to Academy)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Temporary Asphalt
- Kincaid Avenue (Park to Maple)
- Temporary asphalt over trenches
- Alder Avenue (Park to Maple)
- Temporary asphalt over trenches
- Cherry Avenue (Maple to Main)
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- Begin Storm
- Begin Water
- PSE setting new poles and transferring services to new poles.