02/20/2023 Construction Update

Work Completed for Week ending 02/10/2023

  • Park Street (Kincaid to Alder)
    • Continue transferring water services.
    • Continue concrete sidewalks and ADA ramps
  • Alder Avenue (Park to Maple)
    • Continue installing water services, hydrants, and sample station
  • Cherry Avenue (Maple to Main)
    • Continue demolition
    • Continue installing storm drainage
  • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
    • 2/14-2/17 PSE will be setting new poles. Parking area will be closed for PSE work.

2/13/2023 Cherry Avenue - Continue Demolition


02/16/2023 Park Street - Continue Concrete Sidewalks and ADA Ramps



Work in progress this week (2/20/2023 - 2/24/2023)

  • Cherry Avenue (Maple to Main)
    • Continue Storm Drainage Installation
    • Continue potholing for water.
    • Begin replacing sanitary sewer laterals
  • Kincaid Avenue (Park to Maple)
    • Curb Patches
    • Water Testing
  • Alder Avenue (Park to Maple)
    • Water Testing
    • Begin doweling concrete for rebar trench line and pour concrete
  • Academy Street (Alder to Ryan)
    • Water Testing
    • Begin doweling concrete for rebar trench line and pour concrete
  • PSE Pole Relocations in Alley south of Main between Kincaid and Alder
    • 2/23-2/24 PSE will be transferring power to new poles. Parking area will be closed for PSE work.
    • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.

Upcoming Work through (03/10/2023)

  • Main Street intersection at Cherry/Kincaid
    • Begin construction on south side of intersection. Main Street will be west bound only.
  • Alder Avenue (Park to Academy)
    • Complete water main installation
    • Complete water services and hydrant
    • Complete water testing
    • Temporary Asphalt
  • Kincaid Avenue (Park to Maple)
    • Temporary asphalt over trenches
  • Alder Avenue (Park to Maple)
    • Temporary asphalt over trenches
  • Cherry Avenue (Maple to Main)
    • Complete joint utility trench
    • Complete water tie-in at Maple St
    • Begin Illumination
    • Begin Storm
    • Begin Water
    • PSE setting new poles and transferring services to new poles.
Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>