04/10/2022 Construction Update
Upcoming Downtown Construction Impact Meeting
April 19th 8:30-9:30 or 5:30-6:30 at City Hall
WORK COMPLETED FOR WEEK ENDING 04/07/2023
- Alder Ave and Park St intersection
- Completed demolishing pavement
- Began installing storm drainage
- Cherry Avenue (Maple to Main
- Began testing storm
- Began installing illumination system
- Cherry Ave and Maple St intersection
- Began testing water
- Began installing storm drainage
- Main St intersection with Kincaid Ave and Cherry Ave
- Completed demolishing pavement
- Completed installing storm drainage
- Completed installing fiber optic conduit
WORK IN PROGRESS THIS WEEK (4/10/2023 - 04/14/2023)
- Alder Ave and Park St intersection
- Complete water service transfers
- Complete water tie-ins on Alder
- Cherry Avenue (Maple to Main
- Complete testing storm
- Complete installing illumination system
- Cherry Ave and Maple St intersection
- Complete testing water
- Complete water tie-ins on Maple
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
UPCOMING WORK THROUGH (04/27/2023)
- Alder Ave and Park St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Cherry Avenue (Maple to Main
- Complete installing irrigation sleeves
- Complete roadway excavation and grading
- Cherry Ave and Maple St intersection
- Complete installing storm drainage
- Complete roadway excavation and grading
- Begin pouring concrete curb and gutter
- Main St intersection with Kincaid Ave and Cherry Ave
- Complete roadway excavation and grading
- Complete pouring concrete curb and gutter
- Complete pouring concrete sidewalks and ramps
- Begin pouring concrete roadway