04/10/2022 Construction Update


Upcoming Downtown Construction Impact Meeting

April 19th 8:30-9:30 or 5:30-6:30 at City Hall



WORK COMPLETED FOR WEEK ENDING 04/07/2023

  • Alder Ave and Park St intersection
    • Completed demolishing pavement
    • Began installing storm drainage
  • Cherry Avenue (Maple to Main
    • Began testing storm
    • Began installing illumination system
  • Cherry Ave and Maple St intersection
    • Began testing water
    • Began installing storm drainage
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Completed demolishing pavement
    • Completed installing storm drainage
    • Completed installing fiber optic conduit

04/04/2023: Demolishing the intersection of Alder Avenue with Park Street 04/05/2023: Pouring concrete sidewalk and ramps on the northeast corner of Alder Avenue and Academy Street

04/06/2023: Trenching for fiber optic conduit at the intersection with Main Street with Alder Avenue and Kincaid Avenue.


04/07/2023: Grading the SW corner of Alder Avenue and Academy Street

WORK IN PROGRESS THIS WEEK (4/10/2023 - 04/14/2023)


  • Alder Ave and Park St intersection
    • Complete water service transfers
    • Complete water tie-ins on Alder
  • Cherry Avenue (Maple to Main
    • Complete testing storm
    • Complete installing illumination system
  • Cherry Ave and Maple St intersection
    • Complete testing water
    • Complete water tie-ins on Maple
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Complete roadway excavation and grading
    • Begin pouring concrete curb and gutter

UPCOMING WORK THROUGH (04/27/2023)

  • Alder Ave and Park St intersection
    • Complete installing storm drainage
    • Complete roadway excavation and grading
  • Cherry Avenue (Maple to Main
    • Complete installing irrigation sleeves
    • Complete roadway excavation and grading
  • Cherry Ave and Maple St intersection
    • Complete installing storm drainage
    • Complete roadway excavation and grading
    • Begin pouring concrete curb and gutter
  • Main St intersection with Kincaid Ave and Cherry Ave
    • Complete roadway excavation and grading
    • Complete pouring concrete curb and gutter
    • Complete pouring concrete sidewalks and ramps
    • Begin pouring concrete roadway
Categories: Construction Update