3/06/2023 Construction Update

Work Completed for Week ending 02/24/2023

  • Alder Avenue (Park to Maple)
    • Continue installing water services, hydrants, and sample station.
    • Complete doweling concrete for rebar trench line and pour concrete.
    • Complete asphalt over water trenches
  • Cherry Avenue (Maple to Main)
    • Continue installing storm drainage.
    • Complete replacing sanitary sewer laterals and clean out.
  • Academy / Ryan Intersection
    • Begin demolition
  • Academy Street (Alder to Ryan)
    • Begin demolition

02/28/2023 Cherry Ave - Replacing sanitary sewer laterals and clean outs.

02/28/2023 Academy Street - Begin Demolition



Work in progress this week (2/27/2023 - 3/03/2023)

  • Cherry Avenue (Maple to Main)
    • Continue Storm Drainage Installation
  • Kincaid Avenue (Park to Maple)
    • Continue concrete flatwork
    • Continue Curb Patches
    • Continue Water Testing
  • Academy / Ryan Intersection
    • Complete demolition
    • Complete water tie in at Academy and Ryan
  • Academy Street (Alder to Ryan)
    • Complete demolition
    • Begin Storm Drainage Installation

Upcoming Work through (03/17/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)

  • Alder Avenue (Park to Maple)
    • Complete water main installation
    • Complete water services and hydrant
    • Complete water testing
    • Complete curb and sidewalk
  • Park/Alder intersection
    • Complete water tie-in
  • Academy / Ryan Intersection
    • Complete demolition
    • Complete water tie-in
    • Complete Paving
  • Academy Street (Alder to Ryan)
    • Complete demolition
    • Complete water-tie
    • Complete installing storm drainage
    • Complete Paving
    • Complete curb and sidewalk
    • Complete gravel borrow and csbc
  • Cherry Avenue (Maple to Main)
    • Complete installing storm drainage
    • Complete joint utility trench
    • Complete water tie-in at Maple St
    • Begin Illumination
    • Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
  • Maple/Cherry intersection
    • Complete water tie-in
Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>