3/06/2023 Construction Update
Work Completed for Week ending 02/24/2023
- Alder Avenue (Park to Maple)
- Continue installing water services, hydrants, and sample station.
- Complete doweling concrete for rebar trench line and pour concrete.
- Complete asphalt over water trenches
- Cherry Avenue (Maple to Main)
- Continue installing storm drainage.
- Complete replacing sanitary sewer laterals and clean out.
- Academy / Ryan Intersection
- Begin demolition
- Academy Street (Alder to Ryan)
- Begin demolition
Work in progress this week (2/27/2023 - 3/03/2023)
- Cherry Avenue (Maple to Main)
- Continue Storm Drainage Installation
- Kincaid Avenue (Park to Maple)
- Continue concrete flatwork
- Continue Curb Patches
- Continue Water Testing
- Academy / Ryan Intersection
- Complete demolition
- Complete water tie in at Academy and Ryan
- Academy Street (Alder to Ryan)
- Complete demolition
- Begin Storm Drainage Installation
Upcoming Work through (03/17/2023) - Work on Main Street will not begin until after the Daffodil Parade (4/1/23)
- Alder Avenue (Park to Maple)
- Complete water main installation
- Complete water services and hydrant
- Complete water testing
- Complete curb and sidewalk
- Park/Alder intersection
- Complete water tie-in
- Academy / Ryan Intersection
- Complete demolition
- Complete water tie-in
- Complete Paving
- Academy Street (Alder to Ryan)
- Complete demolition
- Complete water-tie
- Complete installing storm drainage
- Complete Paving
- Complete curb and sidewalk
- Complete gravel borrow and csbc
- Cherry Avenue (Maple to Main)
- Complete installing storm drainage
- Complete joint utility trench
- Complete water tie-in at Maple St
- Begin Illumination
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete water tie-in