-
08/21/2024 - Construction Update
Upcoming Work in September:
- Signal Pole installation
- Signal wiring and programming
*This work will be done with Uniformed Police Officers and Flaggers*
-
08/15/2023 - Construction Update
Upcoming Work between 08/21/2023 through 08/25/2023:
- Permanent striping of the roadway with the final intersection channelization
- Sealing of the concrete panels in front of Heritage Bank on Wood Ave
*This work will be done with Uniformed Police Officers and Flaggers*
-
08/03/2023 - Construction Update
*Intersection opens on Friday, 08/04/2023*
Work Completed between 07/27/23 and 08/02/23:
Intersection:
- Joint sealed the stamped concrete panels
- Main St and Wood Ave were paved
- Signal was restrung across the intersection
Sidewalks:
- Sidewalks were finished
- Temporary asphalt was placed where the new signal poles will be installed at the northwest and southeast corners of the intersection
- Concrete sidewalk will be placed when the poles are installed
- Bollards were installed at the corners of the intersection
- Asphalt was placed in front of Dairy Freeze and the Bike Shop
07/27/2023 - Paving of Main St in front of Napa and the Day and Night Grocery Store.
08/01/2023 - Coring for placement of bollards in front of the Dairy Freeze.
Upcoming Work between 08/03/23 and 08/04/23:
Intersection:
- Final clean up
- Temporary striping of parking stalls and roadway
- Final striping will take place after 21 days of the asphalt being in place
*Project will be suspended until end of August when additional work can be completed under traffic control*
-
07/27/2023 - Construction Update
*Intersection is currently fully closed*
*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*
Work Completed between 07/20/23 to 07/26/23:
Intersection:
- Center of the intersection has been completed with the stamped, colored concrete
- Intersection approaches have been poured
- Grading is complete along Main St and Wood Ave
Dry Utilities:
- Communication lines have been pulled underground through the Joint Utility Trench, with splicing occurring at a later date
07/19/23 - Placement of welded mesh wire and dowels within the pour area of the center of the intersection.
07/20/23 - Red colored concrete prior to stamping, at the southwest corner in front of NAPA.
Work in Progress between 07/27/23 to 08/02/23:
Intersection:
- Temporary pave northwest and southeast corners within the sidewalk where the existing signal poles are located
- Pave legs of Main St and Wood Ave
- Signal will be restrung across the intersection
Sidewalks:
- Final sidewalk panels will be poured
Upcoming Work between 08/03/23 and 08/04/23:
Intersection:
- Temporary striping will be placed
- Temporary intersection lighting will be installed
Sidewalks:
- Bollards will be installed at corners of the intersection within the sidewalk
-
07/20/2023 - Construction Update
*Intersection is currently full closed*
*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*
Work Completed between 07/13/23 to 07/19/23:
Intersection:
- Poured two large sections of the intersection with the stamped colored concrete
- Demolition of intersection legs
- Graded south leg of Wood Ave
Dry Utilities:
- PSE relocated their overhead power to the Joint Utility Trench
- PSE removed one of the existing poles at the northwest corner of the intersection, near the Day and Night Grocery
07/17/23 - Demolition of the western leg of Main St
07/18/23 - Stamping of the red colored concrete
Work in Progress between 07/20/23 to 07/26/23:
Intersection:
- Finalizing the paving of the stamped colored concrete in the center of the intersection
- Pouring the intersection approaches with gray concrete
- Final grading of the north leg of Wood Ave
- Final grading of the east leg of Main St
Upcoming Work between 07/27/23 to 08/02/23:
Intersection:
- Paving Main St and Wood Ave
-
07/13/2023 - Construction Update
*Intersection is currently fully closed, and will last for approximately 4 weeks*
*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery from both Main St and Wood Ave*
Work Completed between 07/05/23 to 07/12/23:
Intersection:
- Removed signal from spanning the intersection
- Demolition of the intersection
- Start of demolition and grading of the intersection legs
Sidewalks, Curb, and Gutter:
- Removed walkways in front of the Dairy Freeze and Bike Shop
- Finished pouring sidewalks in front of Napa, Heritage Bank, and the Dairy Freeze
Dry Utilities:
- PSE installed two new utility poles and made connections
- Finalization of the JUT
07/10/23 - PSE placing a new pole near the alley along Wood Ave, just north of the Day and Night Grocery
07/10/23 - Placement of base course that will be underneath the intersection
Work in Progress between 07/13/23 and 07/19/23:
Intersection:
- Forming of intersection to prepare for the concrete pour
- Pouring stamped colored concrete in the center of the intersection
- Continuing to demo and grade intersection legs
Dry Utilities:
- PSE to relocate the overhead power that spans over the intersection into the JUT
Upcoming Work between 07/20/23 to 07/26/23:
Intersection:
- Continuing to pour the center of the intersection
- Prepare the intersection legs for paving
- Prepare areas in front of the Dairy Freeze and the Bike Shop for paving
-
07/06/2023 - Construction Update
*Intersection is currently fully closed, and will last for approximately 4 weeks*
Work Completed between 06/29/23 and 07/05/23:
Intersection:
- Installation of temporary parking along Main St for business access
- Start of intersection demolition
06/28/23: Finishing of newly constructed ADA curb ramp at the northeast corner of Main St and Wood Ave.
06/29/23: Forming of curb along the south side of Main St in front of the Dairy Freeze.
Work in Progress between 07/06/23 and 07/12/23:
Sidewalks, Curb, and Gutter:
- Finish forming and pouring of curb and gutter
- Finish sidewalk pours
Intersection:
- Complete demolition of intersection
- Grade intersection
- Start form and pour of intersection
Wood Ave and Main St Approaches:
- Demolition of south leg of Wood Ave
Upcoming Work between 07/13/23 and 07/19/23:
Intersection:
- Continuing to form and pour the intersection
Wood Ave and Main St Approaches:
- Grade south leg of Wood Ave
- Demo and grade west leg of Main St
-
06/29/2023 - Construction Update
*Intersection will be fully closed for approximately 4 weeks, starting on the morning of Wednesday July 5th*
*There will be no work on Tuesday July 4th*
Work Completed between 06/22/23 and 06/28/23:
Sidewalks, Curb, and Gutter:
- Forming and pouring of curb and gutter
- Pouring of sidewalks
06/26/23 - Forming of curb on the north side of Main St in front of the Day and Night Grocery.
06/27/23 - Freshly poured curb on the south side of Main St in front of NAPA Auto Parts.
Work In Progress between 06/29/23 and 07/05/23:
Sidewalks, Curb, and Gutter:
- Finishing forming and pouring of curb and gutter
- Finishing sidewalk pours
Intersection:
- Installation of temporary parking
- Demolition of the center of the intersection
Upcoming Work Between 07/06/23 and 07/12/23:
Intersection:
- Excavation and grading of the intersection
- Pouring of the intersection
- Start demolition of sections of Main St and Wood Ave
- Start grading sections of Main St and Wood Ave
-
06/22/2023 - Construction Update
* Intersection full closure (24/7) will start the morning of Wednesday July 5th and is anticipated to last until the beginning of August *
* Businesses will remain open and parking will be maintained along Main St for access to businesses at the intersection *
Work Completed between 06/15/23 and 06/21/23:
Dry Utilities:
- Finalized JUT
- Pouring of signal bases for new signal poles at each corner of the intersection
Concrete Curb, Gutter, and Sidewalks:
- Demolition of existing sidewalks, curb, and parking
- Staking of sidewalk and curb locations
06/16/23 - Pouring of concrete for new signal base at the southwest corner of the intersection, in front of NAPA.
06/19/23 - Making signal connections to new signal foundation at the southwest corner of the intersection, in front of NAPA.
Work in Progress 06/22/23 to 06/28/23:
Dry Utilities:
- Temporary Signal Pole installation
- Finalize signal connections
Concrete Curb, Gutter, and Sidewalks:
- Pour of sidewalks, curb, and gutter
Upcoming Work between 06/29/23 to 07/05/23:
Concrete Curb, Gutter, and Sidewalks:
- Finish pouring of sidewalks, curb, and gutter
* There will be no work on Tuesday July 4th – Fourth of July Holiday *
-
06/15/2023 - Construction Update
Work Completed between 06/08/23 and 06/14/23:
Sewer:
- Finalized all connections
Dry Utilities:
- Continued work on the Joint Utility Trench (JUT) and signal connections
Concrete Curb, Gutter, and Sidewalks:
- Demolition and grading in preparation of pouring of sidewalks
06/12/23 - Mayor Kathy Hayden on site holding conduit for the Joint Utility Trench (JUT).
06/13/23 - Front of the Dairy Freeze after the asphalt was removed to prepare for the construction of new sidewalks.
Work in Progress this Week between 06/15/23 and 06/21/23:
Dry Utilities:
- Finalize JUT and signal connections
- Installation of temporary signal pole to allow for space for the new signal base
- Pouring bases for new signal poles
Concrete Curb, Gutter, and Sidewalks:
- Finalize demolition of sidewalks
- Staking of sidewalk locations
- Pouring of sidewalks
Upcoming Work between 06/22/23 and 06/28/23:
Concrete Curb, Gutter, and Sidewalks:
- Continuation of sidewalk pouring