• 08/21/2024 - Construction Update

    Upcoming Work in September:

    - Signal Pole installation

    - Signal wiring and programming

    *This work will be done with Uniformed Police Officers and Flaggers*

  • 08/15/2023 - Construction Update

    Upcoming Work between 08/21/2023 through 08/25/2023:

    - Permanent striping of the roadway with the final intersection channelization

    - Sealing of the concrete panels in front of Heritage Bank on Wood Ave

    *This work will be done with Uniformed Police Officers and Flaggers*

  • 08/03/2023 - Construction Update

    *Intersection opens on Friday, 08/04/2023*

    Work Completed between 07/27/23 and 08/02/23:

    Intersection:

    • Joint sealed the stamped concrete panels
    • Main St and Wood Ave were paved
    • Signal was restrung across the intersection

    Sidewalks:

    • Sidewalks were finished
    • Temporary asphalt was placed where the new signal poles will be installed at the northwest and southeast corners of the intersection
      • Concrete sidewalk will be placed when the poles are installed
    • Bollards were installed at the corners of the intersection
    • Asphalt was placed in front of Dairy Freeze and the Bike Shop



    07/27/2023 - Paving of Main St in front of Napa and the Day and Night Grocery Store.


    08/01/2023 - Coring for placement of bollards in front of the Dairy Freeze.



    Upcoming Work between 08/03/23 and 08/04/23:

    Intersection:

    • Final clean up
    • Temporary striping of parking stalls and roadway
      • Final striping will take place after 21 days of the asphalt being in place

    *Project will be suspended until end of August when additional work can be completed under traffic control*

  • 07/27/2023 - Construction Update

    *Intersection is currently fully closed*

    *Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*


    Work Completed between 07/20/23 to 07/26/23:

    Intersection:

    • Center of the intersection has been completed with the stamped, colored concrete
    • Intersection approaches have been poured
    • Grading is complete along Main St and Wood Ave

    Dry Utilities:

    • Communication lines have been pulled underground through the Joint Utility Trench, with splicing occurring at a later date



    07/19/23 - Placement of welded mesh wire and dowels within the pour area of the center of the intersection.


    07/20/23 - Red colored concrete prior to stamping, at the southwest corner in front of NAPA.



    Work in Progress between 07/27/23 to 08/02/23:

    Intersection:

    • Temporary pave northwest and southeast corners within the sidewalk where the existing signal poles are located
    • Pave legs of Main St and Wood Ave
    • Signal will be restrung across the intersection

    Sidewalks:

    • Final sidewalk panels will be poured


    Upcoming Work between 08/03/23 and 08/04/23:

    Intersection:

    • Temporary striping will be placed
    • Temporary intersection lighting will be installed

    Sidewalks:

    • Bollards will be installed at corners of the intersection within the sidewalk
  • 07/20/2023 - Construction Update

    *Intersection is currently full closed*

    *Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*


    Work Completed between 07/13/23 to 07/19/23:

    Intersection:

    • Poured two large sections of the intersection with the stamped colored concrete
    • Demolition of intersection legs
    • Graded south leg of Wood Ave

    Dry Utilities:

    • PSE relocated their overhead power to the Joint Utility Trench
    • PSE removed one of the existing poles at the northwest corner of the intersection, near the Day and Night Grocery



    07/17/23 - Demolition of the western leg of Main St


    07/18/23 - Stamping of the red colored concrete



    Work in Progress between 07/20/23 to 07/26/23:

    Intersection:

    • Finalizing the paving of the stamped colored concrete in the center of the intersection
    • Pouring the intersection approaches with gray concrete
    • Final grading of the north leg of Wood Ave
    • Final grading of the east leg of Main St


    Upcoming Work between 07/27/23 to 08/02/23:

    Intersection:

    • Paving Main St and Wood Ave
  • 07/13/2023 - Construction Update

    *Intersection is currently fully closed, and will last for approximately 4 weeks*

    *Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery from both Main St and Wood Ave*

    Work Completed between 07/05/23 to 07/12/23:

    Intersection:

    • Removed signal from spanning the intersection
    • Demolition of the intersection
    • Start of demolition and grading of the intersection legs

    Sidewalks, Curb, and Gutter:

    • Removed walkways in front of the Dairy Freeze and Bike Shop
    • Finished pouring sidewalks in front of Napa, Heritage Bank, and the Dairy Freeze

    Dry Utilities:

    • PSE installed two new utility poles and made connections
    • Finalization of the JUT


    07/10/23 - PSE placing a new pole near the alley along Wood Ave, just north of the Day and Night Grocery


    07/10/23 - Placement of base course that will be underneath the intersection



    Work in Progress between 07/13/23 and 07/19/23:

    Intersection:

    • Forming of intersection to prepare for the concrete pour
    • Pouring stamped colored concrete in the center of the intersection
    • Continuing to demo and grade intersection legs

    Dry Utilities:

    • PSE to relocate the overhead power that spans over the intersection into the JUT

    Upcoming Work between 07/20/23 to 07/26/23:

    Intersection:

    • Continuing to pour the center of the intersection
    • Prepare the intersection legs for paving
    • Prepare areas in front of the Dairy Freeze and the Bike Shop for paving
  • 07/06/2023 - Construction Update

    *Intersection is currently fully closed, and will last for approximately 4 weeks*


    Work Completed between 06/29/23 and 07/05/23:

    Intersection:

    • Installation of temporary parking along Main St for business access
    • Start of intersection demolition



    06/28/23: Finishing of newly constructed ADA curb ramp at the northeast corner of Main St and Wood Ave.


    06/29/23: Forming of curb along the south side of Main St in front of the Dairy Freeze.



    Work in Progress between 07/06/23 and 07/12/23:

    Sidewalks, Curb, and Gutter:

    • Finish forming and pouring of curb and gutter
    • Finish sidewalk pours

    Intersection:

    • Complete demolition of intersection
    • Grade intersection
    • Start form and pour of intersection

    Wood Ave and Main St Approaches:

    • Demolition of south leg of Wood Ave



    Upcoming Work between 07/13/23 and 07/19/23:

    Intersection:

    • Continuing to form and pour the intersection

    Wood Ave and Main St Approaches:

    • Grade south leg of Wood Ave
    • Demo and grade west leg of Main St
  • 06/29/2023 - Construction Update

    *Intersection will be fully closed for approximately 4 weeks, starting on the morning of Wednesday July 5th*

    *There will be no work on Tuesday July 4th*

    Work Completed between 06/22/23 and 06/28/23:

    Sidewalks, Curb, and Gutter:

    • Forming and pouring of curb and gutter
    • Pouring of sidewalks




    06/26/23 - Forming of curb on the north side of Main St in front of the Day and Night Grocery.


    06/27/23 - Freshly poured curb on the south side of Main St in front of NAPA Auto Parts.



    Work In Progress between 06/29/23 and 07/05/23:

    Sidewalks, Curb, and Gutter:

    • Finishing forming and pouring of curb and gutter
    • Finishing sidewalk pours

    Intersection:

    • Installation of temporary parking
    • Demolition of the center of the intersection


    Upcoming Work Between 07/06/23 and 07/12/23:

    Intersection:

    • Excavation and grading of the intersection
    • Pouring of the intersection
    • Start demolition of sections of Main St and Wood Ave
    • Start grading sections of Main St and Wood Ave
  • 06/22/2023 - Construction Update

    * Intersection full closure (24/7) will start the morning of Wednesday July 5th and is anticipated to last until the beginning of August *

    * Businesses will remain open and parking will be maintained along Main St for access to businesses at the intersection *


    Work Completed between 06/15/23 and 06/21/23:

    Dry Utilities:

    • Finalized JUT
    • Pouring of signal bases for new signal poles at each corner of the intersection

    Concrete Curb, Gutter, and Sidewalks:

    • Demolition of existing sidewalks, curb, and parking
    • Staking of sidewalk and curb locations




    06/16/23 - Pouring of concrete for new signal base at the southwest corner of the intersection, in front of NAPA.


    06/19/23 - Making signal connections to new signal foundation at the southwest corner of the intersection, in front of NAPA.




    Work in Progress 06/22/23 to 06/28/23:

    Dry Utilities:

    • Temporary Signal Pole installation
    • Finalize signal connections

    Concrete Curb, Gutter, and Sidewalks:

    • Pour of sidewalks, curb, and gutter


    Upcoming Work between 06/29/23 to 07/05/23:

    Concrete Curb, Gutter, and Sidewalks:

    • Finish pouring of sidewalks, curb, and gutter

    * There will be no work on Tuesday July 4th – Fourth of July Holiday *

  • 06/15/2023 - Construction Update

    Work Completed between 06/08/23 and 06/14/23:

    Sewer:

    • Finalized all connections

    Dry Utilities:

    • Continued work on the Joint Utility Trench (JUT) and signal connections

    Concrete Curb, Gutter, and Sidewalks:

    • Demolition and grading in preparation of pouring of sidewalks

    06/12/23 - Mayor Kathy Hayden on site holding conduit for the Joint Utility Trench (JUT).

    06/13/23 - Front of the Dairy Freeze after the asphalt was removed to prepare for the construction of new sidewalks.



    Work in Progress this Week between 06/15/23 and 06/21/23:

    Dry Utilities:

    • Finalize JUT and signal connections
    • Installation of temporary signal pole to allow for space for the new signal base
    • Pouring bases for new signal poles

    Concrete Curb, Gutter, and Sidewalks:

    • Finalize demolition of sidewalks
    • Staking of sidewalk locations
    • Pouring of sidewalks

    Upcoming Work between 06/22/23 and 06/28/23:

    Concrete Curb, Gutter, and Sidewalks:

    • Continuation of sidewalk pouring