07/27/2023 - Construction Update
*Intersection is currently fully closed*
*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*
Work Completed between 07/20/23 to 07/26/23:
Intersection:
- Center of the intersection has been completed with the stamped, colored concrete
- Intersection approaches have been poured
- Grading is complete along Main St and Wood Ave
Dry Utilities:
- Communication lines have been pulled underground through the Joint Utility Trench, with splicing occurring at a later date
07/19/23 - Placement of welded mesh wire and dowels within the pour area of the center of the intersection.
07/20/23 - Red colored concrete prior to stamping, at the southwest corner in front of NAPA.
Work in Progress between 07/27/23 to 08/02/23:
Intersection:
- Temporary pave northwest and southeast corners within the sidewalk where the existing signal poles are located
- Pave legs of Main St and Wood Ave
- Signal will be restrung across the intersection
Sidewalks:
- Final sidewalk panels will be poured
Upcoming Work between 08/03/23 and 08/04/23:
Intersection:
- Temporary striping will be placed
- Temporary intersection lighting will be installed
Sidewalks:
- Bollards will be installed at corners of the intersection within the sidewalk