07/27/2023 - Construction Update

*Intersection is currently fully closed*

*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*


Work Completed between 07/20/23 to 07/26/23:

Intersection:

  • Center of the intersection has been completed with the stamped, colored concrete
  • Intersection approaches have been poured
  • Grading is complete along Main St and Wood Ave

Dry Utilities:

  • Communication lines have been pulled underground through the Joint Utility Trench, with splicing occurring at a later date



07/19/23 - Placement of welded mesh wire and dowels within the pour area of the center of the intersection.


07/20/23 - Red colored concrete prior to stamping, at the southwest corner in front of NAPA.



Work in Progress between 07/27/23 to 08/02/23:

Intersection:

  • Temporary pave northwest and southeast corners within the sidewalk where the existing signal poles are located
  • Pave legs of Main St and Wood Ave
  • Signal will be restrung across the intersection

Sidewalks:

  • Final sidewalk panels will be poured


Upcoming Work between 08/03/23 and 08/04/23:

Intersection:

  • Temporary striping will be placed
  • Temporary intersection lighting will be installed

Sidewalks:

  • Bollards will be installed at corners of the intersection within the sidewalk