07/20/2023 - Construction Update
*Intersection is currently full closed*
*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*
Work Completed between 07/13/23 to 07/19/23:
Intersection:
- Poured two large sections of the intersection with the stamped colored concrete
- Demolition of intersection legs
- Graded south leg of Wood Ave
Dry Utilities:
- PSE relocated their overhead power to the Joint Utility Trench
- PSE removed one of the existing poles at the northwest corner of the intersection, near the Day and Night Grocery
07/17/23 - Demolition of the western leg of Main St
07/18/23 - Stamping of the red colored concrete
Work in Progress between 07/20/23 to 07/26/23:
Intersection:
- Finalizing the paving of the stamped colored concrete in the center of the intersection
- Pouring the intersection approaches with gray concrete
- Final grading of the north leg of Wood Ave
- Final grading of the east leg of Main St
Upcoming Work between 07/27/23 to 08/02/23:
Intersection:
- Paving Main St and Wood Ave