07/20/2023 - Construction Update

*Intersection is currently full closed*

*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery*


Work Completed between 07/13/23 to 07/19/23:

Intersection:

  • Poured two large sections of the intersection with the stamped colored concrete
  • Demolition of intersection legs
  • Graded south leg of Wood Ave

Dry Utilities:

  • PSE relocated their overhead power to the Joint Utility Trench
  • PSE removed one of the existing poles at the northwest corner of the intersection, near the Day and Night Grocery



07/17/23 - Demolition of the western leg of Main St


07/18/23 - Stamping of the red colored concrete



Work in Progress between 07/20/23 to 07/26/23:

Intersection:

  • Finalizing the paving of the stamped colored concrete in the center of the intersection
  • Pouring the intersection approaches with gray concrete
  • Final grading of the north leg of Wood Ave
  • Final grading of the east leg of Main St


Upcoming Work between 07/27/23 to 08/02/23:

Intersection:

  • Paving Main St and Wood Ave
Categories: Construction Update