07/13/2023 - Construction Update
*Intersection is currently fully closed, and will last for approximately 4 weeks*
*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery from both Main St and Wood Ave*
Work Completed between 07/05/23 to 07/12/23:
Intersection:
- Removed signal from spanning the intersection
- Demolition of the intersection
- Start of demolition and grading of the intersection legs
Sidewalks, Curb, and Gutter:
- Removed walkways in front of the Dairy Freeze and Bike Shop
- Finished pouring sidewalks in front of Napa, Heritage Bank, and the Dairy Freeze
Dry Utilities:
- PSE installed two new utility poles and made connections
- Finalization of the JUT
07/10/23 - PSE placing a new pole near the alley along Wood Ave, just north of the Day and Night Grocery
07/10/23 - Placement of base course that will be underneath the intersection
Work in Progress between 07/13/23 and 07/19/23:
Intersection:
- Forming of intersection to prepare for the concrete pour
- Pouring stamped colored concrete in the center of the intersection
- Continuing to demo and grade intersection legs
Dry Utilities:
- PSE to relocate the overhead power that spans over the intersection into the JUT
Upcoming Work between 07/20/23 to 07/26/23:
Intersection:
- Continuing to pour the center of the intersection
- Prepare the intersection legs for paving