07/13/2023 - Construction Update

*Intersection is currently fully closed, and will last for approximately 4 weeks*

*Parking is maintained along Main St, and parking lot access is still available to Heritage Bank and the Day and Night Grocery from both Main St and Wood Ave*

Work Completed between 07/05/23 to 07/12/23:

Intersection:

  • Removed signal from spanning the intersection
  • Demolition of the intersection
  • Start of demolition and grading of the intersection legs

Sidewalks, Curb, and Gutter:

  • Removed walkways in front of the Dairy Freeze and Bike Shop
  • Finished pouring sidewalks in front of Napa, Heritage Bank, and the Dairy Freeze

Dry Utilities:

  • PSE installed two new utility poles and made connections
  • Finalization of the JUT


07/10/23 - PSE placing a new pole near the alley along Wood Ave, just north of the Day and Night Grocery


07/10/23 - Placement of base course that will be underneath the intersection



Work in Progress between 07/13/23 and 07/19/23:

Intersection:

  • Forming of intersection to prepare for the concrete pour
  • Pouring stamped colored concrete in the center of the intersection
  • Continuing to demo and grade intersection legs

Dry Utilities:

  • PSE to relocate the overhead power that spans over the intersection into the JUT

Upcoming Work between 07/20/23 to 07/26/23:

Intersection:

  • Continuing to pour the center of the intersection
  • Prepare the intersection legs for paving
  • Prepare areas in front of the Dairy Freeze and the Bike Shop for paving