08/03/2023 - Construction Update
*Intersection opens on Friday, 08/04/2023*
Work Completed between 07/27/23 and 08/02/23:
Intersection:
- Joint sealed the stamped concrete panels
- Main St and Wood Ave were paved
- Signal was restrung across the intersection
Sidewalks:
- Sidewalks were finished
- Temporary asphalt was placed where the new signal poles will be installed at the northwest and southeast corners of the intersection
- Concrete sidewalk will be placed when the poles are installed
- Bollards were installed at the corners of the intersection
- Asphalt was placed in front of Dairy Freeze and the Bike Shop
07/27/2023 - Paving of Main St in front of Napa and the Day and Night Grocery Store.
08/01/2023 - Coring for placement of bollards in front of the Dairy Freeze.
Upcoming Work between 08/03/23 and 08/04/23:
Intersection:
- Final clean up
- Temporary striping of parking stalls and roadway
- Final striping will take place after 21 days of the asphalt being in place
*Project will be suspended until end of August when additional work can be completed under traffic control*