08/03/2023 - Construction Update

*Intersection opens on Friday, 08/04/2023*

Work Completed between 07/27/23 and 08/02/23:

Intersection:

  • Joint sealed the stamped concrete panels
  • Main St and Wood Ave were paved
  • Signal was restrung across the intersection

Sidewalks:

  • Sidewalks were finished
  • Temporary asphalt was placed where the new signal poles will be installed at the northwest and southeast corners of the intersection
    • Concrete sidewalk will be placed when the poles are installed
  • Bollards were installed at the corners of the intersection
  • Asphalt was placed in front of Dairy Freeze and the Bike Shop



07/27/2023 - Paving of Main St in front of Napa and the Day and Night Grocery Store.


08/01/2023 - Coring for placement of bollards in front of the Dairy Freeze.



Upcoming Work between 08/03/23 and 08/04/23:

Intersection:

  • Final clean up
  • Temporary striping of parking stalls and roadway
    • Final striping will take place after 21 days of the asphalt being in place

*Project will be suspended until end of August when additional work can be completed under traffic control*