06/29/2023 - Construction Update

*Intersection will be fully closed for approximately 4 weeks, starting on the morning of Wednesday July 5th*

*There will be no work on Tuesday July 4th*

Work Completed between 06/22/23 and 06/28/23:

Sidewalks, Curb, and Gutter:

  • Forming and pouring of curb and gutter
  • Pouring of sidewalks




06/26/23 - Forming of curb on the north side of Main St in front of the Day and Night Grocery.


06/27/23 - Freshly poured curb on the south side of Main St in front of NAPA Auto Parts.



Work In Progress between 06/29/23 and 07/05/23:

Sidewalks, Curb, and Gutter:

  • Finishing forming and pouring of curb and gutter
  • Finishing sidewalk pours

Intersection:

  • Installation of temporary parking
  • Demolition of the center of the intersection


Upcoming Work Between 07/06/23 and 07/12/23:

Intersection:

  • Excavation and grading of the intersection
  • Pouring of the intersection
  • Start demolition of sections of Main St and Wood Ave
  • Start grading sections of Main St and Wood Ave
Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>