06/29/2023 - Construction Update
*Intersection will be fully closed for approximately 4 weeks, starting on the morning of Wednesday July 5th*
*There will be no work on Tuesday July 4th*
Work Completed between 06/22/23 and 06/28/23:
Sidewalks, Curb, and Gutter:
- Forming and pouring of curb and gutter
- Pouring of sidewalks
06/26/23 - Forming of curb on the north side of Main St in front of the Day and Night Grocery.
06/27/23 - Freshly poured curb on the south side of Main St in front of NAPA Auto Parts.
Work In Progress between 06/29/23 and 07/05/23:
Sidewalks, Curb, and Gutter:
- Finishing forming and pouring of curb and gutter
- Finishing sidewalk pours
Intersection:
- Installation of temporary parking
- Demolition of the center of the intersection
Upcoming Work Between 07/06/23 and 07/12/23:
Intersection:
- Excavation and grading of the intersection
- Pouring of the intersection
- Start demolition of sections of Main St and Wood Ave
- Start grading sections of Main St and Wood Ave